Commercial Building Permit (New Construction / Tenant Improvements / Additions) — Fountain Hills, Arizona · Requirements sheet
Verified 2026-07-29 · Source: https://www.fountainhillsaz.gov/204/Building-Safety
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Building Permit (New Construction / Tenant Improvements / Additions) in Fountain Hills, Arizona
Required for new commercial building construction, commercial additions, and tenant improvement/build-out work in the Town of Fountain Hills, reviewed against the 2024 International Building Code (IBC) as adopted and amended by the Town (Ordinance No. 25-06), effective for submittals on/after September 1, 2025. Tenant improvements are folded into the general commercial building permit process, not billed as a separate product: the Town's own Comprehensive Fee Schedule groups new construction, additions, AND tenant improvements together under one combined line item, 'Commercial/Tenant Building Permit & Additions,' billed at the identical per-square-foot rate. A separate, lower 'Commercial Remodel (Existing)' rate applies only when remodeling an already-built-out existing commercial space without new construction or tenant-fit-out scope (see this jurisdiction's change-of-use-permit entry, which uses that rate). Applications are submitted exclusively through T.O.P.P.S., the Town's Citizenserve-hosted online permitting portal.
Verified 2026-07-29 · Source
When you need this permit
- Building permit required for new commercial building construction, commercial additions, and tenant improvement/build-out work within Town limits
- Plans must comply with the 2024 IBC and Town of Fountain Hills amendments (Ordinance No. 25-06), effective for submittals on/after September 1, 2025
- New construction, additions, and tenant improvements are billed under the same combined fee category, 'Commercial/Tenant Building Permit & Additions' — confirming TI is fee-wise folded into the general commercial building permit process rather than priced as a distinct product; a separate, lower 'Commercial Remodel (Existing)' rate applies only to remodeling an existing built-out commercial space with no new construction/TI scope
- New commercial construction commonly also requires a separate Site Plan/Design Review approval through Planning & Zoning (Commercial/Industrial/Multi-Family Site Plan Review fee: $680.00 for the first 5,000 sq ft of property, plus $130.00 per additional 1,000 sq ft) — this is a distinct Planning Fee/process from the building permit itself, not included in the building permit fee
- Public Art Contribution Fee applies to qualifying commercial construction projects on a tiered percentage-of-construction-cost basis; the Town calculates Total Construction Cost per the building code's own valuation standards for this purpose
- Commercial Development Impact Fee ($4,815.00 per 1,000 square feet) applies at permit issuance for new commercial construction, split among Parks & Recreation, Fire, and Streets funds per Council resolution
- Automatic fire sprinkler and/or fire alarm system plan review is billed and inspected separately from the building permit itself where applicable to the commercial scope (see Commercial Automatic Sprinkler System and Commercial Fire Alarm System fees)
- Structural calculations and construction drawings must be sealed, signed and dated by an architect or engineer registered in the State of Arizona for the applicable occupancy classification and scope under the adopted 2024 IBC
- Submittal exclusively via T.O.P.P.S. (Town's Online Permitting and Planning System), a Citizenserve-hosted portal — no paper/walk-in applications accepted
- No dedicated 'Commercial Building Permit' submittal checklist was found published on the Town's Building Permit Forms & Checklists page (fountainhillsaz.gov/502/Building-Permit-Forms-Checklists) — unlike the Town's residential, solar, and pool checklists, no commercial-specific plan-submittal checklist document was located after checking that page and searching the Town's site directly
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Stormwater / Limits Fence
Prior to permit issuance — BMPs, inlets, trackout pad and site limits fence per copy of site plan
- 2
Footing
Prior to placing concrete — copies of compaction tests required
- 3
Foundation
Prior to placing concrete or grout — required hold-downs installed, all steel tied, elevation set
- 4
Under-Slab Plumbing/Heating/Electric
Before fill placement; all piping under test
- 5
Rough Framing / Plumbing / Electrical / Mechanical
Before top-out — gas/DWV/water under test, boxes/panel/service made up, gas appliance venting installed
- 6
Fire Sprinkler Rough
Before top-out — fire approval tag required on riser, where the commercial scope includes fire sprinklers
- 7
Insulation / Drywall
Before and after drywall, per approved plans
- 8
Fire Sprinkler Final
Before building final — sticker required in fire panel, where applicable
- 9
Final Grade & Site Improvements / Landscaping
Before building final — site plan on site, landscape plan complete
- 10
Final Building
Gas/electric meters set, appliances operational
See the full Fountain Hills inspection guide — scheduling & re-inspection fees →
Tips
- Fountain Hills' Comprehensive Fee Schedule literally names its new-construction/addition fee category 'Commercial/Tenant Building Permit & Additions' — new construction and tenant improvements share the identical $0.80 (A/C) / $0.65 (non-A/C) per-square-foot rate, confirming TI is folded into the general commercial building permit process rather than priced or processed as a separate product.
- Commercial Building Permit is one of the few permit types in this jurisdiction with an actual Town-published statutory review-timeframe (90/180/270 Town working days under Resolution 2013-48) — most other permit types in Fountain Hills (residential, electrical, plumbing, mechanical, pool, solar, fence) have no published review-timeframe at all, so don't assume this 270-day ceiling applies elsewhere in this file.
- New commercial construction commonly triggers a separate Site Plan/Design Review approval through Planning & Zoning ($680 base plus $130 per 1,000 sq ft thereafter) — budget for this as a distinct process and fee from the building permit itself.
- The Public Art Contribution Fee (1%/0.75%/0.50% tiered by construction cost) applies to qualifying commercial construction projects — factor this into project cost alongside the per-square-foot building permit fee.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-29.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Fountain Hills building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Fountain Hills.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Fountain Hills
Commercial Building Permit (New Construction / Tenant Improvements / Additions) in other cities
Look up this fee in a different city →
Now live
Build your Fountain Hills project checklist
Describe your project once and get every permit, document, and fee it triggers in Fountain Hills — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →