Residential Building Permit (New Construction / Additions) — Fountain Hills, Arizona · Requirements sheet
Verified 2026-07-06 · Source: https://www.fountainhillsaz.gov/204/Building-Safety
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Building Permit (New Construction / Additions) in Fountain Hills, Arizona
Required for new single-family and two-family dwelling construction and building additions in the Town of Fountain Hills. Reviewed against the 2024 IRC and Town of Fountain Hills amendments (Ordinance No. 25-06), effective for submittals on/after September 1, 2025. Applications are submitted exclusively through T.O.P.P.S., the Town's Citizenserve-hosted online permitting portal.
Verified 2026-07-06 · Source
When you need this permit
- Building permit required for new single-family/two-family dwelling construction and additions within Town limits
- Plans must comply with the 2024 IRC and Town of Fountain Hills amendments (Ordinance No. 25-06), including Climatic and Geographic Design Criteria (105 mph wind; Seismic Design Category B; 34°F winter design temperature; 0 psf ground snow load; moderate-to-heavy termite potential)
- Automatic fire sprinklers are required throughout the entire new dwelling, including garages and carports, per the Town's amended IFC Section 903.2 (Ordinance No. 25-06) — plans must be submitted separately for the fire sprinkler system and noted on the house plans
- Engineering (lateral analysis for shear, retaining and gravity where required) must be sealed, signed and dated by an architect or engineer registered in the State of Arizona
- Submittal exclusively via T.O.P.P.S. (Town's Online Permitting and Planning System), a Citizenserve-hosted portal — no paper/walk-in applications accepted
- Full square-footage summary required (livable, garage, covered patios/porches, storage, mechanical), plus site plan, floor plan, foundation/floor/wall/roof framing details, and an energy-code compliance path (prescriptive, performance, or full RES-Check)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 5 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Stormwater / Limits Fence
Prior to permit issuance — BMPs, inlets, trackout pad and site limits fence per copy of site plan
- 2
Footing
Prior to placing concrete — copies of compaction tests required
- 3
Foundation
Prior to placing concrete or grout — required hold-downs installed, all steel tied, elevation set
- 4
Under-Slab Plumbing/Heating/Electric
Before fill placement; all piping under test
- 5
Pre-Slab
Before concrete is placed — pipes sleeved, footings formed
- 6
Roof Diaphragm Nailing / Wall Shear Nailing
Prior to dry-in — stamped truss calcs and ladder on site; windows installed, flashed, NFRC-labeled
- 7
Rough Framing / Plumbing / Electrical / Mechanical
Before top-out — gas/DWV/water under test, boxes/panel/service made up, gas appliance venting installed
- 8
Insulation
Before drywall — per approved plans
- 9
Drywall
After all insulation approved, before taping
- 10
Final Grade & Site Improvements / Landscaping
Before building final — site plan on site, landscape plan complete
- 11
Final Building
Gas/electric meters set, appliances operational, blower door test results provided
See the full Fountain Hills inspection guide — scheduling & re-inspection fees →
Tips
- T.O.P.P.S. is the ONLY way to submit a building permit application in Fountain Hills — there is no paper or in-person submittal option.
- Because the Town's Fire Code amendment (Ordinance No. 25-06, Section 903.2) requires automatic sprinklers throughout ALL new occupancies including garages and carports, budget for the separate Residential Automatic Sprinkler System Plan Review/Inspection fee and a separately submitted fire sprinkler plan set.
- The 2024 IRC/IBC code cycle became effective for Fountain Hills on September 1, 2025 (Ordinance No. 25-06) — plans submitted before that date were reviewed under the prior (2018 I-Codes/2017 NEC) cycle.
- The Town's published A.R.S. §9-835 review-timeframe policy (Resolution 2013-48) sets a 90/180/270 Town-working-day ceiling for 'Commercial Building Permit' and other commercial/platting categories, but does not list Residential Building Permit — no published Town review-timeframe specific to residential new construction was found; call Building Safety at 480-816-5123 for current timing.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Fountain Hills building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Fountain Hills
Residential Building Permit (New Construction / Additions) in other cities
Compare residential building permit (new construction / additions) fees across Arizona →
Look up this fee in a different city →
Now live
Build your Fountain Hills project checklist
Describe your project once and get every permit, document, and fee it triggers in Fountain Hills — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →