Fire Sprinkler / Fire Alarm Permit (Fire Construction Permit) in Tempe, Arizona
Tempe Fire Medical Rescue Department issues fire construction permits for the installation of and modification to fire and life-safety systems, including automatic fire sprinkler systems (IFC 105.7.1) and fire alarm and detection systems (IFC 105.7.7). Tempe City Code Sec. 14-16 adopts the International Fire Code, 2024 Edition (Ord. No. O2026.24, Sec. 13(Exh. B), adopted June 4, 2026), and Sec. 14-17 provides that it 'shall be enforced by the Fire Medical Rescue Department of the City, under the supervision of the Fire Marshal'; the Tempe amendments create the Community Risk Reduction Division as the fire code official. Construction documents are submitted for review through the Tempe Citizen Access Portal using the Fire [FR] Application. Fees are time-based rather than flat: the adopted fee schedule sets a labor rate of $93.35 per hour plus a published base time in hours for each permit type, cumulative, with additional review or inspection time assessed at the hourly rate.
Verified 2026-08-15 · Source
When you need this permit
- Tempe City Code Sec. 14-16 adopts the International Fire Code, 2024 Edition, together with appendix chapters B, C, H, I, K, O and J
- A construction permit is required for the installation and modification of fire and/or life-safety systems and equipment, and for a broad range of operations and systems involving hazardous materials (Tempe Fire Prevention, Fire Inspections page)
- Construction documents are submitted for review through the Tempe Citizen Access Portal (epermits.tempe.gov/CitizenAccess/Default.aspx)
- Use the Fire [FR] Application. Part 2 of the form requires the applicant to identify Automatic Fire Sprinkler System (Installation or Modification, with the number of sprinkler heads) and/or Fire Alarm and Detection Systems (Installation or Modification, with the number of devices)
- Operational permit applications must be submitted at least 10 working days prior to the anticipated commencement date; a Fire Inspector then contacts the applicant for any additional documentation
- Once a construction permit has been issued and work has begun, all permit inspections must be requested through the 24-hour Interactive Voice Response (IVR) system or scheduled online through the Citizen Access Portal
- Tempe amends IFC Section 903.2 to remove the model code's area and occupant-load sprinkler thresholds: an automatic sprinkler system is required throughout buildings and portions thereof used as Group A-1, A-2, A-3, A-4 and A-5, Group B, Group E, Group F-1, Group M, Group R, Group S-1 and Group S-2 parking garage occupancies
- Tempe amends IFC Section 903.2.11.3 to require an automatic sprinkler system throughout buildings located 55 feet or more above the lowest level of fire department vehicle access
- Tempe adds IFC Section 105.6.26: a construction permit is required for installation of or modification to a Fire Fighter Air Replenishment System (FARS)
- Tempe adds IFC Section 901.6.3.2: on completion of inspection, testing and maintenance of a fire protection system, a tag must be attached in a conspicuous location documenting the date, the contractor and AZROC license number, the individual who performed the work, and whether the system is compliant or deficiencies were noted
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Fire construction permit inspection
Inspection of the installed or modified fire protection system under the issued construction permit. The adopted fee schedule pairs plan review and inspection in a single base-time allowance per permit type. Requested through the 24-hour IVR system or scheduled online through the Tempe Citizen Access Portal.
- 2
Re-inspection (chargeable after the second re-inspection)
Re-inspections after the second re-inspection are assessed at 3.0 hours base time at the $93.35 hourly labor rate under the adopted Fire Prevention and Protection fee schedule.
See the full Tempe inspection guide — scheduling & re-inspection fees →
Tips
- Tempe's fire code is on a different cycle from its building codes. Tempe City Code Sec. 14-16 adopts the 2024 International Fire Code (Ord. No. O2026.24, adopted June 4, 2026, which repealed the former Article II), while the Building Safety codes page still publishes the 2018 I-Code set. Design fire protection to the 2024 IFC plus the Tempe amendments in City Code Chapter 14, Article II, Division 2.
- Fire permit fees are time-based, not flat. Base hours times $93.35 per hour, cumulative across systems, with any additional review or inspection time billed at the same rate. A complex or incomplete submittal costs more than the base time.
- Small modifications are handled over the counter: 1 to 20 sprinkler heads or 1 to 10 alarm devices carry a 2.0-hour OTC permit/inspection base time instead of a full plan review cycle.
- Tempe deletes the model-code sprinkler thresholds. Group A, B, E, F-1, M, R, S-1 and S-2 parking garage occupancies require sprinklers throughout regardless of floor area or occupant load, so do not size a Tempe project off the unamended IFC.
- Do not use Building Safety's Target Turn-Around Times sheet for fire review. Its Fire and Fire Alarm / AFES rows deliberately carry no number and refer you to the Fire Medical Rescue permits, fees and forms page.
- Work started without a permit, and expedited plan review, each double the permit fees under the adopted fire fee schedule.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-15.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Tempe building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Tempe
Fire Sprinkler / Fire Alarm Permit (Fire Construction Permit) in other cities
Compare fire sprinkler / fire alarm permit (fire construction permit) fees across Arizona →
Look up this fee in a different city →
Now live
Build your Tempe project checklist
Describe your project once and get every permit, document, and fee it triggers in Tempe — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →