Unincorporated Yuma County building inspections

Inspection sequence, scheduling, and re-inspection fees for building permits in Unincorporated Yuma County, Arizona.

Reviewed 2026-07-07 · Source

How to schedule

Inspections are requested through the building department below.

Address
2351 West 26th Street, Yuma, AZ 85364
Phone
(928) 817-5000
Office hours
Weekdays 8:00 a.m.-5:00 p.m. Inspection requests must be called in before 4:00 p.m. (M-F) for next-business-day service; provide permit number, address, and inspection type: (928) 817-5196. Fax: (928) 817-5020.

Published scheduling rules

  • Inspection requests must be called in by 4:00 p.m. (Monday-Friday) for next-business-day service: (928) 817-5196. Have your permit number, address, and inspection type ready. (General)

Inspection sequence

Applies to: Change of Use / New Certificate of Occupancy

  1. 1

    Zoning conformance review

    The zoning inspector issues the permit only when it appears the proposed use fully conforms to the Zoning Ordinance, and must withhold it in any other case (Sec. 1201.01)

  2. 2

    Outdoor lighting compliance review

    All outdoor lighting related to the new use must be reviewed and made to comply with Section 623.00 of the Zoning Ordinance when the use of an existing building, structure or premises changes (Sec. 623.07(B))

  3. 3

    Certificate of Occupancy issuance

    New Certificate of Occupancy signed by the County Building Official or designee, stating that the building, structure or use complies with the Zoning Ordinance and may be used for the purposes stated; the Assessor and the Arizona Department of Revenue are notified on issuance (Sec. 1201.00(C))

Applies to: Commercial Building Permit (New Construction, Tenant Improvement, Remodel, Multi-Family)

  1. 1

    Foundation/Footing

    Prior to concrete pour, per the county's amended 2018 IBC

  2. 2

    Framing / Structural

    After structural framing complete, before wall cover

  3. 3

    Final

    Completed construction inspected for code compliance prior to occupancy

Applies to: Fire Permit (Fire Code Construction and Operational Permits)

  1. 1

    Fire Pre Inspection

    Yuma County Development Services publishes a 'Fire Pre Inspection' public information brochure describing the county's own fire inspection process (https://www.yumacountyaz.gov/government/development-services/divisions/customer-service/public-information-brochures)

  2. 2

    Fire Inspection

    County fire inspection against the adopted International Fire Code; DDS publishes a companion brochure, 'Deficiencies Found During Fire Inspections,' listing the issues it most often cites

  3. 3

    Sprinkler System Maintenance

    Ongoing obligation rather than a one-time sign-off — DDS publishes a 'Maintaining a Sprinkler System' public information brochure for owners of sprinklered buildings in unincorporated Yuma County

Applies to: Residential Building Permit (New Construction, Addition, Remodel)

  1. 1

    Foundation/Footing

    Prior to concrete pour — verify forms, rebar, and footing dimensions per the county's amended 2018 IRC/IBC

  2. 2

    Framing

    Structural framing complete per approved plans, before insulation or wall cover

  3. 3

    Final

    Completed construction inspected for code compliance; schedule by calling (928) 817-5196 before 4:00 p.m. for next-business-day service

Applies to: Sign Permit

  1. 1

    Footing / Foundation (freestanding and off-site signs)

    Sign footing and structural support inspected before concrete pour, under the inspection procedures of the Yuma County Comprehensive Building and Safety Code incorporated by Zoning Ordinance Sec. 800.02

  2. 2

    Electrical (illuminated signs)

    Sign illumination wiring inspected under the 2020 National Electrical Code as amended and adopted by Yuma County, and against the Outdoor Lighting Section (Sec. 1109.00) limits on intermittent, flashing, or varying-intensity illumination

  3. 3

    Final

    Sign erected per approved plans; for freestanding and off-site signs, verify the permit number and date of issue are permanently affixed in a conspicuous place and legible (Sec. 800.08)

Applies to: Electric Vehicle (EV) Charging Station / EVSE Permit

  1. 1

    Rough-In

    EVSE circuit wiring before walls are closed, per the applicable amended electrical code

  2. 2

    Final

    Charging equipment installed and energized; verified by a building inspector before close-out

Applies to: Electrical, Plumbing & Mechanical Permit

  1. 1

    Rough-In

    Wiring, piping, or ductwork installed before walls closed, per the applicable amended 2018/2020 trade code

  2. 2

    Final

    All work complete and operational; verified by a building inspector before clearance/close-out

Unincorporated Yuma County building permits

Get alerts for Unincorporated Yuma County

We'll email you when Unincorporated Yuma County's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.