Commercial Building Permit (New Construction, Tenant Improvement, Remodel, Multi-Family) in Unincorporated Yuma County, Arizona

Required for non-residential new construction, remodels, additions, tenant improvements, and change-of-use in unincorporated Yuma County, and also required for residential construction involving multi-family projects of three or more units, apartment buildings, condominiums, and Mobile Home/RV parks. Reviewed under the county's amended 2018 IBC by the DDS Building Safety Division via the same two-step Administrative + Technical Review process as residential permits, with its own published timelines and fee schedule.

Verified 2026-07-07 · Source

When you need this permit

  • Required for all non-residential new construction, remodels, additions, tenant improvements, and change-of-use, and for residential multi-family projects of 3+ units, apartment buildings, condominiums, and MH/RV parks
  • Two-step review: Administrative Review then Technical Review, verifying compliance with Building Safety (ICC codes), Engineering (PWS I & II), Flood Control (PWS III, Floodplain Regulations), Environmental Health, and MH & RV Park Plan Review (Zoning) as applicable
  • Apply online through the county's Permit Application Center (https://yumacountyaz.portal.opengov.com/) or in person at 2351 West 26th Street, Yuma
  • Administrative Review Building Safety checklist: two (2) site plans scaled on 8.5x11 (one if submitted electronically) and one (1) set of construction documents in any legible format
  • Expedited Review is available, not to exceed 10 business days, for qualifying projects

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee (valuation-based, Table 1-A)Yuma County Commercial Permit Guide, fee schedules table; underlying valuation-based Table 1-A brackets are Attachment #3 to the county's DDS Fee Schedule document.
$310.00 (as published in the current Commercial Permit Guide's fee schedules table)
Building Plan Review FeeYuma County DDS Fee Schedule, Category 1 (Plan Reviews).
65% of the building permit fee, per set of plan review
Grading FeeYuma County Commercial Permit Guide, fee schedules table.
$260.00
Floodplain Use Permit Fee (Commercial or Industrial Facility)Yuma County DDS Fee Schedule, Floodplain Use Permit Fees; confirmed in the Commercial Permit Guide's fee schedules table.
$260.00
Conventional Sewage/Septic Plan Review Fee (Commercial, single unit)Yuma County DDS Fee Schedule, Sewage Disposal Commercial Plan Review Fees, cross-checked against the Commercial Permit Guide fee schedules table.
$515.00 (2-5 units: $335.00 under the general DDS fee schedule; the Commercial Permit Guide's own summary table lists $515.00 for 'Conventional Plan Review Fee')
Alternative Sewage System Plan Review Fee (Commercial)Discrepancy noted between the Commercial Permit Guide's abbreviated fee table ($150.00) and the DDS Fee Schedule's detailed Alternative Sewage System Plan Review Fees table ($515.00 commercial); both are county-published documents, so this file reports both governing figures rather than picking one arbitrarily.
$150.00 (Commercial Permit Guide summary) / $515.00 for full Wisconsin Mound or Evapotranspiration Bed review under the general DDS fee schedule
Water Well Permit FeeYuma County Commercial Permit Guide, fee schedules table.
$100.00 (paid to the Arizona Department of Water Resources, ADWR)

Review timeline

Plan reviewUnincorporated Yuma County’s published plan-review target
10–25 business days

How long did your Commercial Building Permit (New Construction, Tenant Improvement, Remodel, Multi-Family) permit actually take in Unincorporated Yuma County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation/Footing

    Prior to concrete pour, per the county's amended 2018 IBC

  2. 2

    Framing / Structural

    After structural framing complete, before wall cover

  3. 3

    Final

    Completed construction inspected for code compliance prior to occupancy

See the full Unincorporated Yuma County inspection guide — scheduling & re-inspection fees →

Tips

  • Per the Commercial Permit Guide, Multiple Reviews (the standard track) take up to 25 business days; an Expedited Review option is available and is not to exceed 10 business days for qualifying projects.
  • Commercial permits are also the required track for any residential project of 3 or more units (apartments, condominiums, Mobile Home/RV parks) — do not use the single-family Residential Building Permit process for these.
  • The Administrative Review checklist differs slightly from residential: commercial requires only one (1) set of construction documents versus two (2) for residential, but adds Environmental Programs (Notice of Intent & Request to Discharge), Well (ADWR form ff-40), and SWPPP/NOI documentation where applicable.

Frequently asked questions

Unincorporated Yuma County requires a commercial building permit (new construction, tenant improvement, remodel, multi-family) for: Required for all non-residential new construction, remodels, additions, tenant improvements, and change-of-use, and for residential multi-family projects of 3+ units, apartment buildings, condominiums, and MH/RV parks; Two-step review: Administrative Review then Technical Review, verifying compliance with Building Safety (ICC codes), Engineering (PWS I & II), Flood Control (PWS III, Floodplain Regulations), Environmental Health, and MH & RV Park Plan Review (Zoning) as applicable; Apply online through the county's Permit Application Center (https://yumacountyaz.portal.opengov.com/) or in person at 2351 West 26th Street, Yuma; Administrative Review Building Safety checklist: two (2) site plans scaled on 8.5x11 (one if submitted electronically) and one (1) set of construction documents in any legible format; Expedited Review is available, not to exceed 10 business days, for qualifying projects. If your project isn't listed, confirm with Yuma County Department of Development Services (DDS), Building Safety Division at (928) 817-5000 before starting work.

In Unincorporated Yuma County, the published Building Permit Fee (valuation-based, Table 1-A) is: $310.00 (as published in the current Commercial Permit Guide's fee schedules table). Additional published fees: Building Plan Review Fee — 65% of the building permit fee, per set of plan review; Grading Fee — $260.00; Floodplain Use Permit Fee (Commercial or Industrial Facility) — $260.00; Conventional Sewage/Septic Plan Review Fee (Commercial, single unit) — $515.00 (2-5 units: $335.00 under the general DDS fee schedule; the Commercial Permit Guide's own summary table lists $515.00 for 'Conventional Plan Review Fee'); Alternative Sewage System Plan Review Fee (Commercial) — $150.00 (Commercial Permit Guide summary) / $515.00 for full Wisconsin Mound or Evapotranspiration Bed review under the general DDS fee schedule; Water Well Permit Fee — $100.00 (paid to the Arizona Department of Water Resources, ADWR). These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Unincorporated Yuma County's published plan-review target for a commercial building permit (new construction, tenant improvement, remodel, multi-family) is 10–25 business days.

You'll need: Commercial Permit Guide; Scaled Site Plan (8.5 x 11); Construction Documents. See the required-documents checklist on this page for details on each.

Unincorporated Yuma County requires 3 inspection(s) for a commercial building permit (new construction, tenant improvement, remodel, multi-family), in order: Foundation/Footing, Framing / Structural, Final. Schedule each through Yuma County Department of Development Services (DDS), Building Safety Division ((928) 817-5000).

Apply through Yuma County Department of Development Services (DDS), Building Safety Division at 2351 West 26th Street, Yuma, AZ 85364. Phone: (928) 817-5000, email: contact.dds@yumacountyaz.gov. Office hours: Weekdays 8:00 a.m.-5:00 p.m. Inspection requests must be called in before 4:00 p.m. (M-F) for next-business-day service; provide permit number, address, and inspection type: (928) 817-5196. Fax: (928) 817-5020.. Official information: https://www.yumacountyaz.gov/government/development-services/divisions/building-safety.

Unincorporated Yuma County, Arizona has adopted: Arizona has no mandatory statewide building code — code adoption is a per-city/county authority. Yuma County's Department of Development Services (DDS), Building Safety Division independently adopts and administers its own construction codes for unincorporated county territory (areas outside the incorporated cities of Yuma, San Luis, Somerton, and Wellton). Source: Yuma County Building Safety Code Amendments page (yumacountyaz.gov/government/development-services/laws-guidelines/building-safety-code-amendments), which itemizes the county's currently-amended code editions.; 2018 International Building Code (IBC), amended by county-adopted amendments. Source: Yuma County Building Safety Code Amendments page (amendment document: 2018 International Building Code Amendments PDF).; 2018 International Residential Code (IRC), amended by county-adopted amendments (superseding the prior 2012 IRC amendments, which remain separately published on the same page for historical reference). Source: Yuma County Building Safety Code Amendments page.; 2018 International Existing Building Code (IEBC), amended by county-adopted amendments (superseding the prior 2012 IEBC amendments). Source: Yuma County Building Safety Code Amendments page.; 2018 International Swimming Pool and Spa Code (ISPSC), amended by county-adopted amendments. Source: Yuma County Building Safety Code Amendments page.; 2018 International Mechanical Code (IMC), amended by county-adopted amendments dated 2024 (document publish-date 638205375930770000, i.e. 2024). Source: Yuma County Building Safety Code Amendments page.; 2018 International Plumbing Code (IPC), amended by county-adopted amendments dated 2024. Source: Yuma County Building Safety Code Amendments page.; 2018 International Fuel Gas Code (IFGC), amended by county-adopted amendments dated 2024. Source: Yuma County Building Safety Code Amendments page.; 2020 National Electrical Code (NEC), amended by county-adopted amendments dated 2024 (this is a newer NEC edition than several incorporated Yuma County cities have adopted, e.g. San Luis at 2014 NEC). Source: Yuma County Building Safety Code Amendments page.; 2009 International Energy Conservation Code (IECC), amended by county-adopted amendments. This is the most recent energy-code edition found published on the county's amendments page as of this review; no newer IECC adoption document was located. Source: Yuma County Building Safety Code Amendments page.; The full 'Yuma County Comprehensive Building Code' (the county's consolidated code-and-amendments volume) is available for public review at the Board of Supervisors Office (198 S. Main Street, Yuma), the Yuma County Libraries, and the Department of Development Services office (2351 West 26th Street, Yuma). Source: Yuma County Building Safety FAQ, 'Yuma County Comprehensive Building Code, where can I read it?' (yumacountyaz.gov/government/advanced-components/faq-single-list/-seldept-25).. Local amendments apply — see the Unincorporated Yuma County overview page for the full list.

Yes. Yuma County requires a Commercial Building Permit for residential construction involving multi-family projects of three or more units, including apartment buildings, condominiums, and Mobile Home/RV parks — not the single-family Residential Building Permit track. Source: https://www.yumacountyaz.gov/government/development-services/permit-process/commercial-permit-information

Sources & verification

Verified against official sources. Last reviewed 2026-07-07.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Yuma County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Unincorporated Yuma County.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.