Sign Permit in Boulder, Colorado
Required before installing or altering most permanent signs on commercial, institutional, or multi-family property in the City of Boulder, per Boulder Revised Code Section 9-9-21. Only a City of Boulder-licensed sign contractor (Class A or Class B) may obtain the permit and install the sign; fees are tiered by review complexity (BRC 4-20-21(b)) rather than a single flat rate, ranging from $92 for a sign needing no plan check to $344 for one needing both plan check and electrical review.
Verified 2026-08-13 · Source
When you need this permit
- Most signs require a permit under BRC 9-9-21; a defined list of small/temporary sign types is exempt (see exemptions below)
- Only a City of Boulder-licensed Sign Contractor may obtain the permit and install the sign — Class A covers manufacture, installation, and servicing of signs, awnings, and canvas canopies; Class B covers painted signs only (BRC 4-20-21)
- Building Owner Authorization Form required if the applicant is not the property owner
- Scaled site plan required showing property lines, streets, easements, building frontage, and all existing/proposed sign locations
- Scaled building elevation drawings required showing heights, facade dimensions, and sign positioning
- Projecting/suspended signs require projection and vertical-clearance dimensions plus engineering for attachment to the structure
- Free-standing signs require a scaled site plan showing setbacks/easements and engineer-stamped foundation details
- Internally illuminated signs require full specification sheets including lumen rating and color temperature
- Prohibited outright, not just unpermitted: signs in the public right-of-way (including A-frame sandwich boards), signs over 25 feet in height or on a roof, animated/moving/twinkling/rotating/pulsating signs, strings of lights, and off-premises signs
- Exempt from a permit: construction-site signs ≤16 sq ft (must be placed by the licensed contractor working the site), up to 3 flags totaling ≤70 sq ft, garage-sale signs, lost-animal notices, noncommercial signs, private traffic signs ≤3 sq ft, real estate signs, utility warning signs ≤16 sq ft, window signs ≤4 sq ft, and vehicle-displayed signs Contractor
- Applications submitted via the CSS Portal
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Final
Verify the installed sign matches the approved plans, structural attachment/anchoring is sound, and electrical connections are complete for an illuminated sign
See the full Boulder inspection guide — scheduling & re-inspection fees →
Tips
- Only a City of Boulder-licensed Sign Contractor (Class A or Class B) may obtain a sign permit and install the sign — unlike Boulder's homeowner exception for building permits, there is no self-install pathway for a property owner.
- Fee is tiered by review complexity rather than a flat rate: a simple sign needing neither plan check nor electrical review is $92, while one needing both plan check and electrical review is $344 (BRC 4-20-21(b)) — confirm which tier applies before budgeting.
- A-frame/sandwich-board signs in the public right-of-way and roof-mounted signs or signs over 25 feet tall are prohibited outright in Boulder, not simply subject to permit review.
- Window signs ≤4 sq ft and several other small/temporary sign types are exempt from the permit requirement entirely — check the exemption list before assuming a permit is needed.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-13.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Boulder building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Boulder
Sign Permit in other cities
Compare sign permit fees across Colorado →
Look up this fee in a different city →
Now live
Build your Boulder project checklist
Describe your project once and get every permit, document, and fee it triggers in Boulder — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →