EV Charger / EVSE Permit — Boulder, Colorado · Requirements sheet
Verified 2026-07-20 · Source: https://bouldercolorado.gov/services/building-permits-and-inspections
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit in Boulder, Colorado
Installing a Level 1 or Level 2 electric vehicle charging station (EVSE) at a residential or commercial property in the City of Boulder is permitted as an Electrical Permit — there is no separate EV-charger-specific permit type or fee line item in the city's published fee schedule. As a 'covered municipality' under Colorado HB24-1173 (population over 10,000), Boulder had to either adopt the state's EV Charging Model Land Use Code, adopt its own standards with an applicant checklist, or formally opt to keep its existing process by December 31, 2025. bouldercolorado.gov publishes no distinct EV-charger permitting page, checklist, or model-code adoption notice, so the city continues to route EV charger installs through its standard Electrical Permit / CSS Portal process rather than a new dedicated pathway.
Verified 2026-07-20 · Source
When you need this permit
- Submitted as an Electrical Permit via the CSS Portal (EnerGov-based), same portal used for photovoltaic and other electrical work
- Dedicated branch circuit sized to the EVSE manufacturer's specifications, per the 2023 NEC as amended by the City of Boulder (Article 625, Electric Vehicle Charging Systems)
- Panel/service capacity load calculation required if the added EVSE circuit could exceed existing service capacity
- State of Colorado electrical licensure verified under Boulder's 'Contemporaneous Reviews of Electrical and Plumbing Licenses' program for the installing contractor
- No EV-charger-specific application form, checklist, or fee category was found published separately from the general Electrical Permit
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
2026 Planning and Development Services Schedule of Fees, Electrical Permit Fees (Section 4-20-8) — no distinct 'EV charger' or 'EVSE' line item exists in the fee schedule; Show full citationHide
2026 Planning and Development Services Schedule of Fees, Electrical Permit Fees (Section 4-20-8) — no distinct 'EV charger' or 'EVSE' line item exists in the fee schedule; an EVSE circuit is billed under the standard residential or nonresidential electrical fee tiers depending on scopeReview timeline
Inspection process
- 1
Rough-In / Final Electrical
Circuit wiring, breaker sizing, and EVSE connection verified; may be combined into a single final inspection for a simple circuit-extension job
See the full Boulder inspection guide — scheduling & re-inspection fees →
Tips
- Boulder does not publish a distinct EV charger / EVSE permit fee — expect the same Electrical Permit fee tiers used for any other circuit addition or service change (e.g., $36.70 for a residential service-change-only scope).
- Confirm with Planning & Development Services whether Boulder has adopted a specific EV-charger permitting checklist under HB24-1173; the city's public-facing pages do not show one.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fee schedules
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Boulder building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Property Access
Boulder's permit history is searchable by address
335,625 permits on record for Boulder, 1979–2026 — searchable by street address, with permit type, status, issued date and valuation where the city publishes them.
Other permits in Boulder
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Colorado →
Look up this fee in a different city →
Related guides