Inspection sequence, scheduling, and re-inspection fees for building permits in Westcliffe, Colorado.

Verified 2026-07-06 · Source

How to schedule

Inspections are requested through the building department below.

Address
1000 Main Street, P.O. Box 406, Westcliffe, CO 81252
Phone
719-783-2282, ext. 12 (Building Department); ext. 10 or 11 (other permit/application forms)
Office hours
Building and Zoning office hours: Monday through Thursday, 8:00 a.m. to 5:00 p.m. (Town Hall general hours: Monday through Friday, 8:00 a.m. to 5:00 p.m.).

Inspection sequence

Applies to: Residential Building Permit (New Construction)

  1. 1

    Foundation

    Before concrete pour, per 40-inch minimum frost line depth

  2. 2

    Framing

    Structural framing complete before cover

  3. 3

    Mechanical Rough-In

    Mechanical/HVAC rough-in before concealment; fee set off cost of job per the Administration Fee Schedule

  4. 4

    Final Inspection

    All work complete per approved plans and applicable codes

Applies to: Accessory Dwelling Unit (ADU) Permit

  1. 1

    Foundation (new-construction ADU only)

    Before concrete pour, if new construction rather than a conversion

  2. 2

    Framing

    Structural framing complete before cover

  3. 3

    Final Inspection

    All work complete per approved plans and applicable codes

Applies to: Commercial Tenant Improvement / Commercial Building Permit

  1. 1

    Foundation

    Before concrete pour

  2. 2

    Framing

    Structural framing complete before cover

  3. 3

    Final Inspection

    All work complete per approved plans and applicable codes

Applies to: Deck / Covered Patio / Carport Permit

  1. 1

    Footing/Foundation

    Before concrete pour, per 40-inch minimum frost line depth, if footings are required

  2. 2

    Final Inspection

    Structure complete per approved plans

Applies to: Electrical Permit

  1. 1

    Rough Electrical (State Inspector)

    Performed by a Colorado State Electrical Inspector before concealment

  2. 2

    Final Inspection (State Inspector)

    Performed by a Colorado State Electrical Inspector; system energized and verified

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough Mechanical

    Ductwork, flues, and equipment placement before concealment

  2. 2

    Final Inspection

    Equipment operational, combustion air and venting verified

Applies to: Plumbing Permit

  1. 1

    Rough Plumbing (State Inspector)

    Performed by a Colorado State Plumbing Inspector before concealment

  2. 2

    Final Inspection (State Inspector)

    Performed by a Colorado State Plumbing Inspector; fixtures connected, no leaks, proper venting verified

Applies to: Residential Addition / Remodel Permit

  1. 1

    Framing

    Framing complete, connection to existing structure verified

  2. 2

    Final Inspection

    All work complete per approved plans

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    Building Final (Town)

    Racking, roof penetrations, and structural attachment verified by the Town Building Official

  2. 2

    Electrical Final (State Inspector)

    Performed by a Colorado State Electrical Inspector; wiring, inverter, and interconnection verified before energizing

Re-inspection fees

Mechanical / HVAC PermitRe-Inspection Fee (contractor requested inspection, not ready)
$50.00 per hour

Westcliffe building permits

Get alerts for Westcliffe

We'll email you when Westcliffe's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.