Castle Rock building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Castle Rock, Colorado.

Verified 2026-07-05 · Source

How to schedule

Inspections are requested through the building department below.

Address
100 N. Wilcox St., Castle Rock, CO 80104
Phone
720-733-3527
Office hours
Development Services Building Counter (Town Hall): Monday-Friday, 8 a.m. to 5 p.m. Inspection scheduling line: 303-660-1341.

Published scheduling rules

  • Schedule inspections through eTRAKiT until 6:30 a.m. on the requested date, or via the inspection hotline (303-660-1341) by 3:30 p.m. for next-business-day inspections; sites must be accessible 7:30 a.m.-5 p.m. (Commercial Building Permit (New Construction & Additions))
  • Sign inspections are scheduled through the same channels as building inspections: phone (303-660-1341), fax (720-733-2207), walk-in, or eTRAKiT. (Sign Permit)
  • Field inspection requests require 24-hour notice (303-660-1066); on large construction projects the fire inspector aims to visit the site every other day (Fire Sprinkler and Fire Alarm Permit)
  • Contact: Development Services Building Counter (Town Hall, 100 N. Wilcox St.) open 8 a.m.-5 p.m. Monday-Friday, phone 720-733-3527, email buildingcounter@crgov.com. Inspection scheduling line: 303-660-1341. All permit applications and plan submittals are electronic-only via the eTRAKiT Development Portal (etrakitt9.crgov.com). (General)

Inspection sequence

Applies to: Commercial Building Permit (New Construction & Additions)

  1. 1

    Footing / Caisson Inspection

    Deep foundation and footing inspections scheduled independently before concrete placement; items that must be approved before being covered up

  2. 2

    Underground Plumbing Inspection

    Under-slab plumbing scheduled independently prior to cover

  3. 3

    Rough Inspections — Framing, Electrical, Plumbing, Mechanical

    Commercial inspections are scheduled per-discipline on an as-needed basis; all disciplines do not have to be ready at once — partial inspections are standard operating procedure on commercial projects per the Town's Development Procedures Manual

  4. 4

    Insulation / Energy Inspection

    Verification of envelope insulation per the 2021 IECC compliance path shown on the approved plans

  5. 5

    Fire and Life Safety Field Inspections

    Conducted by Castle Rock Fire and Life Safety Division under separate fire permits; field inspection requests require 24-hour notice (303-660-1066); on large projects the fire inspector aims to visit every other day

  6. 6

    Final Inspections — All Disciplines

    Building, electrical, plumbing, mechanical finals plus sign-offs from all authorities over the permit (Fire, Health Department, Utilities, Public Works, Metro Districts, etc.)

  7. 7

    Certificate of Occupancy

    Once all final approval letters are submitted (see Commercial CO Checklist), all authorities have signed off and the inspection card is approved, the CO or Certificate of Completion is issued within 24 hours

Applies to: Commercial Tenant Improvement Permit

  1. 1

    Underground / Under-slab Plumbing

    If the TI cuts the slab for new plumbing, inspected independently before cover

  2. 2

    Rough Inspections — Framing, Electrical, Plumbing, Mechanical

    Commercial inspections are scheduled per-discipline as needed; partial inspections are standard operating procedure, so trades do not all have to be ready at once

  3. 3

    Insulation / Energy

    Where the scope touches the envelope or the 2021 IECC compliance path requires it

  4. 4

    Fire and Life Safety Inspections

    Sprinkler/alarm/hood modifications inspected by Castle Rock Fire and Life Safety under separate fire permits; 24-hour notice required (303-660-1066)

  5. 5

    Final Inspections — All Disciplines

    Building and trade finals plus sign-offs from all authorities over the permit (Fire, Health Department for food service, Utilities, etc.)

  6. 6

    Certificate of Occupancy / Completion

    Per the Commercial CO Checklist, issued within 24 hours once all approval letters are in, all authorities have signed off and the inspection card is approved

Applies to: Residential Building Permit (New Construction)

  1. 1

    Foundation

    Before concrete pour; must be inspected/reported by a Colorado-licensed professional engineer or registered architect per local amendment R109.1.1.1, in addition to the Town's own foundation inspection

  2. 2

    Framing

    Structural framing per 2024 IRC and approved plans

  3. 3

    Electrical Rough-In

    Verifies wiring, panel capacity, and — where a solar-ready zone is installed — conduit/prewiring from the solar-ready zone to the electrical panel (local amendment R105.2.4.1)

  4. 4

    Insulation and Fenestration Rough-In

    Verifies insulation types/R-values and fenestration U-factors before interior finish, per local amendment R105.2.4.2

  5. 5

    Final

    All work complete, ready for Certificate of Occupancy

Applies to: Residential Addition / Remodel / Basement Finish Permit

  1. 1

    Foundation (if applicable)

    For additions or garages with new footings — 36-inch minimum frost depth

  2. 2

    Framing

    Structural framing and connection to existing structure

  3. 3

    MEP Rough-In

    Mechanical, electrical, plumbing rough-in before walls closed

  4. 4

    Final

    All work complete per approved plans

Applies to: Fire Sprinkler and Fire Alarm Permit

  1. 1

    Underground Fire Line (if applicable)

    Required only where an underground fire line (UFL) is part of the scope; inspected before cover

  2. 2

    Sprinkler/Alarm Rough-In

    Piping, heads, wiring, and panel installed before concealment; requires 24-hour advance notice (303-660-1066)

  3. 3

    Final / Acceptance Test

    System tested per the applicable NFPA standard for the system type; a Fire Alarm Record of Completion is required at closeout for alarm systems

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    Structural/Racking (Building)

    Roof penetrations and mounting-system attachment verified per the Building Permit

  2. 2

    Electrical Rough-In

    Wiring and conduit verified; if a solar-ready zone was previously installed, conduit/prewiring routing to the panel is specifically checked per local amendment R105.2.4.1

  3. 3

    Final Electrical

    Interconnection, grounding, and disconnects verified per the 2026 NEC before the system is energized

Applies to: Change of Use / Change of Occupancy Permit

  1. 1

    Fire and Life Safety Change-of-Use Inspection

    Verifies the new use/occupancy against current Fire Code requirements; billed as the Fire Department's separate Change of Use inspection fee

  2. 2

    Building Final (if occupancy classification changes)

    Confirms the space meets applicable building/egress requirements for the new occupancy classification before sign-off

Applies to: Electrical Permit

  1. 1

    Rough-In

    Wiring and conduit installed before walls closed; verify solar-ready conduit routing if applicable

  2. 2

    Final

    Devices installed, panel labeled, system energized

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough-In

    New circuit wiring and conduit installed before walls are closed, if applicable; for new construction, verifies EV-ready conduit routing per the 2023 Colorado Model Electric-Ready and Solar-Ready Code

  2. 2

    Final

    Charger unit installed, devices connected, system energized

Applies to: Fence and Retaining Wall Permit

  1. 1

    Footing

    Required for retaining walls with a permit, before backfill

  2. 2

    Final

    Completed fence/wall verified against approved plans

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In / Equipment

    Equipment and ductwork installed before concealment

  2. 2

    Final

    Equipment operational, combustion air and venting verified

Applies to: Plumbing Permit

  1. 1

    Rough-In

    Pipe installation, slope, and materials verified before concealment

  2. 2

    Final

    Fixtures connected, no leaks, proper venting

Re-inspection fees

Commercial Building Permit (New Construction & Additions)Re-inspection Fee · Inspections outside normal business hours/same day: $125.00 per hour per inspection + $50.00 per hour for each additional inspection
$85.00 / $170.00
Commercial Tenant Improvement PermitRe-inspection Fee · Same-day/after-hours inspections $125.00 per hour per inspection + $50.00 per hour each additional
$85.00 / $170.00

Castle Rock building permits

Get alerts for Castle Rock

We'll email you when Castle Rock's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.