Castle Rock building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Castle Rock, Colorado.
Verified 2026-07-05 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 100 N. Wilcox St., Castle Rock, CO 80104
- Phone
- 720-733-3527
- Office hours
- Development Services Building Counter (Town Hall): Monday-Friday, 8 a.m. to 5 p.m. Inspection scheduling line: 303-660-1341.
- Website
- Official site
Published scheduling rules
- Schedule inspections through eTRAKiT until 6:30 a.m. on the requested date, or via the inspection hotline (303-660-1341) by 3:30 p.m. for next-business-day inspections; sites must be accessible 7:30 a.m.-5 p.m. (Commercial Building Permit (New Construction & Additions))
- Sign inspections are scheduled through the same channels as building inspections: phone (303-660-1341), fax (720-733-2207), walk-in, or eTRAKiT. (Sign Permit)
- Field inspection requests require 24-hour notice (303-660-1066); on large construction projects the fire inspector aims to visit the site every other day (Fire Sprinkler and Fire Alarm Permit)
- Contact: Development Services Building Counter (Town Hall, 100 N. Wilcox St.) open 8 a.m.-5 p.m. Monday-Friday, phone 720-733-3527, email buildingcounter@crgov.com. Inspection scheduling line: 303-660-1341. All permit applications and plan submittals are electronic-only via the eTRAKiT Development Portal (etrakitt9.crgov.com). (General)
Inspection sequence
Applies to: Commercial Building Permit (New Construction & Additions)
- 1
Footing / Caisson Inspection
Deep foundation and footing inspections scheduled independently before concrete placement; items that must be approved before being covered up
- 2
Underground Plumbing Inspection
Under-slab plumbing scheduled independently prior to cover
- 3
Rough Inspections — Framing, Electrical, Plumbing, Mechanical
Commercial inspections are scheduled per-discipline on an as-needed basis; all disciplines do not have to be ready at once — partial inspections are standard operating procedure on commercial projects per the Town's Development Procedures Manual
- 4
Insulation / Energy Inspection
Verification of envelope insulation per the 2021 IECC compliance path shown on the approved plans
- 5
Fire and Life Safety Field Inspections
Conducted by Castle Rock Fire and Life Safety Division under separate fire permits; field inspection requests require 24-hour notice (303-660-1066); on large projects the fire inspector aims to visit every other day
- 6
Final Inspections — All Disciplines
Building, electrical, plumbing, mechanical finals plus sign-offs from all authorities over the permit (Fire, Health Department, Utilities, Public Works, Metro Districts, etc.)
- 7
Certificate of Occupancy
Once all final approval letters are submitted (see Commercial CO Checklist), all authorities have signed off and the inspection card is approved, the CO or Certificate of Completion is issued within 24 hours
Applies to: Commercial Tenant Improvement Permit
- 1
Underground / Under-slab Plumbing
If the TI cuts the slab for new plumbing, inspected independently before cover
- 2
Rough Inspections — Framing, Electrical, Plumbing, Mechanical
Commercial inspections are scheduled per-discipline as needed; partial inspections are standard operating procedure, so trades do not all have to be ready at once
- 3
Insulation / Energy
Where the scope touches the envelope or the 2021 IECC compliance path requires it
- 4
Fire and Life Safety Inspections
Sprinkler/alarm/hood modifications inspected by Castle Rock Fire and Life Safety under separate fire permits; 24-hour notice required (303-660-1066)
- 5
Final Inspections — All Disciplines
Building and trade finals plus sign-offs from all authorities over the permit (Fire, Health Department for food service, Utilities, etc.)
- 6
Certificate of Occupancy / Completion
Per the Commercial CO Checklist, issued within 24 hours once all approval letters are in, all authorities have signed off and the inspection card is approved
Applies to: Residential Building Permit (New Construction)
- 1
Foundation
Before concrete pour; must be inspected/reported by a Colorado-licensed professional engineer or registered architect per local amendment R109.1.1.1, in addition to the Town's own foundation inspection
- 2
Framing
Structural framing per 2024 IRC and approved plans
- 3
Electrical Rough-In
Verifies wiring, panel capacity, and — where a solar-ready zone is installed — conduit/prewiring from the solar-ready zone to the electrical panel (local amendment R105.2.4.1)
- 4
Insulation and Fenestration Rough-In
Verifies insulation types/R-values and fenestration U-factors before interior finish, per local amendment R105.2.4.2
- 5
Final
All work complete, ready for Certificate of Occupancy
Applies to: Residential Addition / Remodel / Basement Finish Permit
- 1
Foundation (if applicable)
For additions or garages with new footings — 36-inch minimum frost depth
- 2
Framing
Structural framing and connection to existing structure
- 3
MEP Rough-In
Mechanical, electrical, plumbing rough-in before walls closed
- 4
Final
All work complete per approved plans
Applies to: Fire Sprinkler and Fire Alarm Permit
- 1
Underground Fire Line (if applicable)
Required only where an underground fire line (UFL) is part of the scope; inspected before cover
- 2
Sprinkler/Alarm Rough-In
Piping, heads, wiring, and panel installed before concealment; requires 24-hour advance notice (303-660-1066)
- 3
Final / Acceptance Test
System tested per the applicable NFPA standard for the system type; a Fire Alarm Record of Completion is required at closeout for alarm systems
Applies to: Solar Photovoltaic (PV) Permit
- 1
Structural/Racking (Building)
Roof penetrations and mounting-system attachment verified per the Building Permit
- 2
Electrical Rough-In
Wiring and conduit verified; if a solar-ready zone was previously installed, conduit/prewiring routing to the panel is specifically checked per local amendment R105.2.4.1
- 3
Final Electrical
Interconnection, grounding, and disconnects verified per the 2026 NEC before the system is energized
Applies to: Change of Use / Change of Occupancy Permit
- 1
Fire and Life Safety Change-of-Use Inspection
Verifies the new use/occupancy against current Fire Code requirements; billed as the Fire Department's separate Change of Use inspection fee
- 2
Building Final (if occupancy classification changes)
Confirms the space meets applicable building/egress requirements for the new occupancy classification before sign-off
Applies to: Electrical Permit
- 1
Rough-In
Wiring and conduit installed before walls closed; verify solar-ready conduit routing if applicable
- 2
Final
Devices installed, panel labeled, system energized
Applies to: EV Charger / EVSE Permit
- 1
Rough-In
New circuit wiring and conduit installed before walls are closed, if applicable; for new construction, verifies EV-ready conduit routing per the 2023 Colorado Model Electric-Ready and Solar-Ready Code
- 2
Final
Charger unit installed, devices connected, system energized
Applies to: Fence and Retaining Wall Permit
- 1
Footing
Required for retaining walls with a permit, before backfill
- 2
Final
Completed fence/wall verified against approved plans
Applies to: Mechanical / HVAC Permit
- 1
Rough-In / Equipment
Equipment and ductwork installed before concealment
- 2
Final
Equipment operational, combustion air and venting verified
Applies to: Plumbing Permit
- 1
Rough-In
Pipe installation, slope, and materials verified before concealment
- 2
Final
Fixtures connected, no leaks, proper venting
Final inspection only: Demolition Permit, Roofing Permit (Re-Roof), Sign Permit
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-05.
Fee schedules
Applications & forms
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Castle Rock building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Castle Rock building permits
Get alerts for Castle Rock
We'll email you when Castle Rock's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.