Commercial Building Permit (New Construction & Additions) in Castle Rock, Colorado

Required for construction of new commercial and multifamily buildings, additions, and core-and-shell buildings within the Town of Castle Rock. Issued and inspected by the Town's own Development Services Building Division (not Douglas County) under the 2024 IBC as locally amended by Ordinance No. 2026-017 (effective June 30, 2026), the 2021 IECC, the 2026 NEC, and — depending on the property's fire intensity classification — the 2025 Colorado Wildfire Resiliency Code (effective July 1, 2026). All commercial projects require plan review; the Town's Development Procedures Manual lists 'Commercial/Multi-Family - Core and Shell' as a distinct building permit type from tenant improvement/remodel work.

Verified 2026-08-02 · Source

When you need this permit

  • All commercial projects require plan review; building permit applications are paperless and submitted electronically in PDF through the eTRAKiT Development Portal (etrakitt9.crgov.com), following the Town's Electronic Submittal Guidelines - Commercial
  • Contractors must hold a valid license from a testing jurisdiction with an ICC-equivalent exam, current Town contractor registration, a certificate of liability insurance, and workers' compensation insurance (if applicable) before applying Contractor
  • Plans must be sealed Architectural, Structural, Plumbing, Mechanical and Electrical drawings from a Colorado Registered Design Professional, with a full code analysis: construction type, use and occupancy classification, mixed-use strategy, occupant loads, means of egress, fire protection systems, energy compliance path and fixture counts (per the Town's commercial submittal checklists)
  • New commercial buildings follow the Town's Development Steps sequence before building permit: Site Development Plan approval (administrative for projects 10 acres or less not adjacent to residential; public-hearing track otherwise), then engineered construction drawings review, then building permit plan review — Town reviews are concurrent across Building, Fire, Utilities, Zoning and Plum Creek Water Reclamation Authority
  • All Fire Protection permits (suppression, alarm, commercial hood systems, tanks, hazmat) are submitted separately and directly to the Castle Rock Fire and Life Safety Division at CRFDFM.com — not through the Building Division
  • All new businesses and construction of new buildings in the Plum Creek Water Reclamation Authority service area (which includes Castle Rock) must complete and submit PCWRA's Industry Information Questionnaire
  • Building valuation is set using the Town's own Building Valuation Table (2024 IBC occupancy groups, Town-published $/sq ft rates — e.g., B Business Type VB $209.02/sq ft, M Mercantile Type VB $133.27/sq ft); shell-only buildings deduct 20%. The table is the minimum valuation the Town will accept for new construction
  • New construction, additions and certain exterior work may be subject to 2025 Colorado Wildfire Resiliency Code requirements depending on the property's low/moderate/high fire intensity classification on the Town's wildfire resiliency map

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 7 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — valuation $0 to $500Town of Castle Rock Development Services Fee Schedule, effective July 1, 2026
$23.50
Building Permit Fee — valuation $501 to $2,000
$23.50 for the first $500 plus $3.05 for each additional $100 or fraction thereof, to and including $2,000
Building Permit Fee — valuation $2,001 to $25,000
$69.25 for the first $2,000 plus $14.00 for each additional $1,000 or fraction thereof, to and including $25,000
Building Permit Fee — valuation $25,001 to $50,000
$391.25 for the first $25,000 plus $10.10 for each additional $1,000 or fraction thereof, to and including $50,000
Building Permit Fee — valuation $50,001 to $100,000
$643.75 for the first $50,000 plus $7.00 for each additional $1,000 or fraction thereof, to and including $100,000
Building Permit Fee — valuation $100,001 to $500,000
$993.75 for the first $100,000 plus $5.60 for each additional $1,000 or fraction thereof, to and including $500,000
Building Permit Fee — valuation $500,001 to $1,000,000
$3,233.75 for the first $500,000 plus $4.75 for each additional $1,000 or fraction thereof, to and including $1,000,000
Building Permit Fee — valuation $1,000,001 and up
$5,608.75 for the first $1,000,000 plus $3.65 for each additional $1,000 or fraction thereof
Plan Review FeeAdditional plan review (if applicable) $125.00/hour, 1-hour minimum; outside consultant plan review at actual cost + $50.00
65% of the Building Permit Fee (not of valuation)
Castle Rock Use TaxPaying use tax at permitting exempts the job from Town and county sales tax on building materials
1/2 valuation x 4.2%
Douglas County Use Tax
1/2 valuation x 1%
Administrative Cost Allocation Recovery Fee — New Non-ResidentialWarehouse buildings instead pay a flat $4,200.00 per building; hotels $262.50 per room
$1,470.00 per 1,000 sq ft (per building)
Development Impact Fees — Non-Residential (Municipal Facilities, Fire, Police, Transportation)Fee Schedule effective July 1, 2026, subtotals of the four impact-fee components
Commercial/Shopping Center: $3,990 per 1,000 sq ft (50,000 sq ft or less) down to $2,645 per 1,000 sq ft (over 200,000 sq ft); Office: $3,626 down to $1,569 per 1,000 sq ft by size tier; Industrial $3,514; Warehousing $3,402 per 1,000 sq ft; Hotel $1,919 per room
Stormwater Impact Fee — Commercial/Industrial
$571 per 1,000 sq ft of gross floor area (Cherry Creek Basin) or $1,281 per 1,000 sq ft (Plum Creek Basin)
Water, Renewable Water and Wastewater System Development Fees — Non-ResidentialWastewater component not charged in Cobblestone Ranch (served by Pinery Water and Wastewater District)
By meter size: 3/4" x 3/4" $51,890 total; 1" $86,656; 1.5" $172,794; 2" C2 $346,106; up to 6" T2 $4,323,994
Temporary Certificate of Occupancy
Initial issuance free (expires after 90 calendar days); first and second extensions $500 per 60-day extension; third and up $1,000 per 60-day extension
Re-inspection FeeInspections outside normal business hours/same day: $125.00 per hour per inspection + $50.00 per hour for each additional inspection
$85.00 / $170.00

Review timeline

Plan reviewCastle Rock’s published plan-review target
28–28 business days

How long did your Commercial Building Permit (New Construction & Additions) permit actually take in Castle Rock?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Footing / Caisson Inspection

    Deep foundation and footing inspections scheduled independently before concrete placement; items that must be approved before being covered up

  2. 2

    Underground Plumbing Inspection

    Under-slab plumbing scheduled independently prior to cover

  3. 3

    Rough Inspections — Framing, Electrical, Plumbing, Mechanical

    Commercial inspections are scheduled per-discipline on an as-needed basis; all disciplines do not have to be ready at once — partial inspections are standard operating procedure on commercial projects per the Town's Development Procedures Manual

  4. 4

    Insulation / Energy Inspection

    Verification of envelope insulation per the 2021 IECC compliance path shown on the approved plans

  5. 5

    Fire and Life Safety Field Inspections

    Conducted by Castle Rock Fire and Life Safety Division under separate fire permits; field inspection requests require 24-hour notice (303-660-1066); on large projects the fire inspector aims to visit every other day

  6. 6

    Final Inspections — All Disciplines

    Building, electrical, plumbing, mechanical finals plus sign-offs from all authorities over the permit (Fire, Health Department, Utilities, Public Works, Metro Districts, etc.)

  7. 7

    Certificate of Occupancy

    Once all final approval letters are submitted (see Commercial CO Checklist), all authorities have signed off and the inspection card is approved, the CO or Certificate of Completion is issued within 24 hours

See the full Castle Rock inspection guide — scheduling & re-inspection fees →

Tips

  • Schedule inspections through eTRAKiT until 6:30 a.m. on the requested date, or via the inspection hotline (303-660-1341) by 3:30 p.m. for next-business-day inspections; sites must be accessible 7:30 a.m.-5 p.m.
  • Budget for far more than the permit fee: on new commercial buildings the development impact fees, stormwater impact fee, water/wastewater system development fees (five to seven figures depending on meter size) and the administrative cost allocation recovery fee are due at issuance and typically dwarf the valuation-based permit fee
  • The Site Development Plan comes first — new construction or complete redevelopment SDP review is $4,800 (over 10 acres) or $3,000 (10 acres or less), and construction document review is $3,000 (up to 5 acres, plus $350/acre over 5) before the building permit stage
  • Check the Town's Colorado Wildfire Resiliency map early: properties classified moderate or high fire intensity carry additional exterior material requirements effective July 1, 2026
  • The Chief Building Official may refund up to 80% of the building permit fee if no work has been done, and up to 80% of the plan review fee if the application is withdrawn before any plan review is performed
  • There is no separate 'large commercial' permit track — big-box and shopping-center projects (e.g., Promenade at Castle Rock scale) use the same commercial building permit, but SDPs over 10 acres or adjacent to residential trigger the public-hearing approval track instead of administrative approval

Frequently asked questions

Castle Rock requires a commercial building permit (new construction & additions) for: All commercial projects require plan review; building permit applications are paperless and submitted electronically in PDF through the eTRAKiT Development Portal (etrakitt9.crgov.com), following the Town's Electronic Submittal Guidelines - Commercial; Contractors must hold a valid license from a testing jurisdiction with an ICC-equivalent exam, current Town contractor registration, a certificate of liability insurance, and workers' compensation insurance (if applicable) before applying; Plans must be sealed Architectural, Structural, Plumbing, Mechanical and Electrical drawings from a Colorado Registered Design Professional, with a full code analysis: construction type, use and occupancy classification, mixed-use strategy, occupant loads, means of egress, fire protection systems, energy compliance path and fixture counts (per the Town's commercial submittal checklists); New commercial buildings follow the Town's Development Steps sequence before building permit: Site Development Plan approval (administrative for projects 10 acres or less not adjacent to residential; public-hearing track otherwise), then engineered construction drawings review, then building permit plan review — Town reviews are concurrent across Building, Fire, Utilities, Zoning and Plum Creek Water Reclamation Authority; All Fire Protection permits (suppression, alarm, commercial hood systems, tanks, hazmat) are submitted separately and directly to the Castle Rock Fire and Life Safety Division at CRFDFM.com — not through the Building Division; All new businesses and construction of new buildings in the Plum Creek Water Reclamation Authority service area (which includes Castle Rock) must complete and submit PCWRA's Industry Information Questionnaire; Building valuation is set using the Town's own Building Valuation Table (2024 IBC occupancy groups, Town-published $/sq ft rates — e.g., B Business Type VB $209.02/sq ft, M Mercantile Type VB $133.27/sq ft); shell-only buildings deduct 20%. The table is the minimum valuation the Town will accept for new construction; New construction, additions and certain exterior work may be subject to 2025 Colorado Wildfire Resiliency Code requirements depending on the property's low/moderate/high fire intensity classification on the Town's wildfire resiliency map. If your project isn't listed, confirm with Town of Castle Rock Development Services, Building Division at 720-733-3527 before starting work.

In Castle Rock, the published Building Permit Fee — valuation $0 to $500 is: $23.50. Additional published fees: Building Permit Fee — valuation $501 to $2,000 — $23.50 for the first $500 plus $3.05 for each additional $100 or fraction thereof, to and including $2,000; Building Permit Fee — valuation $2,001 to $25,000 — $69.25 for the first $2,000 plus $14.00 for each additional $1,000 or fraction thereof, to and including $25,000; Building Permit Fee — valuation $25,001 to $50,000 — $391.25 for the first $25,000 plus $10.10 for each additional $1,000 or fraction thereof, to and including $50,000; Building Permit Fee — valuation $50,001 to $100,000 — $643.75 for the first $50,000 plus $7.00 for each additional $1,000 or fraction thereof, to and including $100,000; Building Permit Fee — valuation $100,001 to $500,000 — $993.75 for the first $100,000 plus $5.60 for each additional $1,000 or fraction thereof, to and including $500,000; Building Permit Fee — valuation $500,001 to $1,000,000 — $3,233.75 for the first $500,000 plus $4.75 for each additional $1,000 or fraction thereof, to and including $1,000,000; Building Permit Fee — valuation $1,000,001 and up — $5,608.75 for the first $1,000,000 plus $3.65 for each additional $1,000 or fraction thereof; Plan Review Fee — 65% of the Building Permit Fee (not of valuation); Castle Rock Use Tax — 1/2 valuation x 4.2%; Douglas County Use Tax — 1/2 valuation x 1%; Administrative Cost Allocation Recovery Fee — New Non-Residential — $1,470.00 per 1,000 sq ft (per building); Development Impact Fees — Non-Residential (Municipal Facilities, Fire, Police, Transportation) — Commercial/Shopping Center: $3,990 per 1,000 sq ft (50,000 sq ft or less) down to $2,645 per 1,000 sq ft (over 200,000 sq ft); Office: $3,626 down to $1,569 per 1,000 sq ft by size tier; Industrial $3,514; Warehousing $3,402 per 1,000 sq ft; Hotel $1,919 per room; Stormwater Impact Fee — Commercial/Industrial — $571 per 1,000 sq ft of gross floor area (Cherry Creek Basin) or $1,281 per 1,000 sq ft (Plum Creek Basin); Water, Renewable Water and Wastewater System Development Fees — Non-Residential — By meter size: 3/4" x 3/4" $51,890 total; 1" $86,656; 1.5" $172,794; 2" C2 $346,106; up to 6" T2 $4,323,994; Temporary Certificate of Occupancy — Initial issuance free (expires after 90 calendar days); first and second extensions $500 per 60-day extension; third and up $1,000 per 60-day extension; Re-inspection Fee — $85.00 / $170.00. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

The Town's published standard is first review comments within 4 weeks for new construction and additions (excluding weekends/holidays; the clock stops if plans are returned incomplete). Reviews by Building, Fire, Utilities, Zoning and Plum Creek Water Reclamation Authority run concurrently. Site Development Plan approval and construction-drawing review happen before this stage for new buildings.

You'll need: Plan Review and Building Permit Application (eTRAKiT); Detailed Narrative / Scope of Work; Sealed Construction Drawings; Supporting Engineering Documents; Commercial Water Calculations / Water Tap Size Certification; Plum Creek Water Reclamation Authority Approval; Castle Rock Fire Department Application. Depending on your project, Castle Rock may also ask for: Manufacturer Specifications and Load Calculations. See the required-documents checklist on this page for details on each.

Apply through Town of Castle Rock Development Services, Building Division at 100 N. Wilcox St., Castle Rock, CO 80104. Phone: 720-733-3527, email: buildingcounter@crgov.com. Office hours: Development Services Building Counter (Town Hall): Monday-Friday, 8 a.m. to 5 p.m. Inspection scheduling line: 303-660-1341.. Official information: https://www.crgov.com/1887/Building.

No. Castle Rock is a home-rule town with its own prequalified Building Division (Development Services, 100 N. Wilcox St.). Douglas County's building department only covers unincorporated areas. Food establishments do, however, need a separate Douglas County Health Department retail food license, and Douglas County collects its 1% use tax through the Town permit.

Permit applications are reviewed under the 2024 I-codes (IBC, IPC, IMC, IFGC, IFC, IEBC) as amended by Ordinance No. 2026-017 effective June 30, 2026, plus the 2021 IECC, the 2026 NEC, ANSI A117.1-2017, and the 2025 Colorado Wildfire Resiliency Code (effective July 1, 2026) where the property's fire intensity classification triggers it.

No. All fire protection permits (suppression, alarm, commercial hoods, storage tanks, hazardous materials) are submitted, paid for and inspected separately through the Castle Rock Fire and Life Safety Division (CRFDFM.com, 303-660-1066).

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Castle Rock.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.