Change of Use / Change of Occupancy in Estes Park, Colorado

Estes Park has no standalone permit literally titled 'change of use permit' — confirmed absent from the Town's Planning Forms and References page and its Fee Schedule (Development Review Fees, effective January 2024), both checked directly this session. Instead, a change in use runs through the Estes Park Development Code's (EPDC) Chapter 4 (Zoning Districts) use tables and, where a proposed use doesn't clearly fit an existing classification, the EPDC Section 3.12 Use Classification determination process — a genuinely published staff-level review with a real 30-day turnaround, confirmed via the Town's own 'Use Classifications' guide. If the proposed use requires zoning approval beyond a use allowed by right, a Conditional Use Permit ($900.00, or $250.00 for an accessory dwelling unit) is required. Existing nonconforming uses are separately governed by EPDC Chapter 6. Distinctively for this file, unlike Berthoud (a peer Larimer County jurisdiction in this corpus that adopted the 2024 IEBC), Estes Park's own codesAdopted list does not include an adopted International Existing Building Code — a genuine gap surfaced honestly here rather than invented; where a change of use is accompanied by construction or alteration, the ordinary Town commercial-building-permit or commercial-tenant-improvement-permit process (both already documented in this file) applies under the 2021 IBC as locally amended.

Verified 2026-08-13 · Source

When you need this permit

  • No standalone change-of-use permit, application, or fee line by that name is published by the Town — confirmed absent from the Planning Forms and References page and the Fee Schedule (Development Review Fees, effective January 2024), both checked directly this session
  • The Estes Park Development Code (EPDC) Chapter 4 (Zoning Districts) contains the use tables listing which land uses are allowed by right, allowed only as a conditional/special-review use, or prohibited within each zoning district
  • Where a proposed use does not clearly fit an existing EPDC use classification, EPDC Section 3.12 (Use Classification) provides a formal determination process: a voluntary but Town-encouraged pre-application conference, followed by a staff review that must reach a final written determination within 30 days of a complete application being submitted — confirmed directly via the Town's own 'Use Classifications' guide (Planning Division, revised April 2020)
  • The staff determination weighs factors including the proposed use's actual/projected characteristics against the use classifications already permitted in the zoning district, site area/floor space devoted to the use, relative sales and employee counts, hours of operation, vehicle trips generated, signage, and consistency with the Code's stated intent; an official record is kept on file with the Community Development Department
  • A Use Classification determination may be appealed to the Town Board
  • If the proposed use requires approval as a conditional/special-review use rather than being allowed by right in the applicable zoning district, a Conditional Use Permit application and $900.00 fee is required ($250.00 if the conditional use is specifically an accessory dwelling unit) — the Town's Fee Schedule lists this fee, but unlike Berthoud, the Town's public Development Review Guides list does not include a dedicated Conditional Use Permit / Special Review process guide, so the specific hearing, notice, and timeline steps for THIS stage were not independently confirmed during this research pass — an honest gap
  • Existing nonconforming uses (legally established before the current use regulations took effect, but no longer matching them) are separately governed by EPDC Chapter 6: they may continue and be repaired/maintained, but generally cannot be altered or extended, and a nonconforming use that is abandoned or discontinued for 12 consecutive months permanently loses its nonconforming status
  • If the change of use is accompanied by construction, remodeling, or a formal occupancy-classification change requiring building-code compliance work, the ordinary Town Building Permit process applies (see this file's commercial-building-permit and commercial-tenant-improvement-permit entries), billed under the general valuation-based Table 1-A fee schedule (Ordinance 03-16) — no distinct change-of-use fee line exists on the Building Division's own side
  • Unlike Berthoud, this file's codesAdopted list for Estes Park does not include an adopted International Existing Building Code (IEBC); Estes Park's 2021 IBC adoption (Municipal Code Section 14.12.010) includes only the standard IBC Section 101.4 secondary-code references with the fire-code subsection stricken — no IEBC-specific change-of-occupancy provision was independently located during this research pass, an honest gap surfaced rather than an invented process

Required documents

Check off what you have — your progress is saved on this device.

Fee schedule

Land Use and Zoning Determination — StandardTown of Estes Park Fee Schedule, Development Review Fees, effective January 2024
$75.00
Land Use and Zoning Determination — Complex
$100.00 + $50.00 per hour
Conditional Use Permit
$900.00
Conditional Use Permit — Accessory Dwelling Unit
$250.00
Building Permit Fee (if construction/alteration accompanies the use change)No distinct change-of-use fee line exists on the Building Division's own fee schedule
Valuation-based per Table 1-A, Ordinance 03-16 — same schedule documented elsewhere in this file

Review timeline

Plan reviewEstes Park’s published plan-review target
Up to 30 business days

How long did your Change of Use / Change of Occupancy permit actually take in Estes Park?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Use Classification / Zoning Compliance Review

    A document-and-record review by Community Development Department staff (and, for conditional uses, ultimately the Town Board) — not a physical site inspection

  2. 2

    Building Division Inspections (if construction accompanies the use change)

    The standard inspection sequence for the applicable Town building-permit type applies; see this file's commercial-building-permit and commercial-tenant-improvement-permit entries

See the full Estes Park inspection guide — scheduling & re-inspection fees →

Tips

  • Start with EPDC Section 3.12 if you're not sure whether your proposed use is even allowed — a voluntary pre-application conference is encouraged, and the Town commits to a genuine 30-day written determination once your application is complete.
  • The $900.00 Conditional Use Permit fee only applies if your use isn't allowed by right in your zoning district — check the EPDC Chapter 4 use tables, or call Planning at 970-577-3721, before assuming you need one.
  • A legally nonconforming use that sits vacant or unused for 12 straight months permanently loses its nonconforming status under EPDC Chapter 6 — don't let a grandfathered use lapse if you're planning to bring in a new but similar tenant.
  • If your change of use also involves construction or a restaurant/commercial-kitchen fit-out, layer in this file's commercial-tenant-improvement-permit entry (and its Estes Valley Fire Protection District and health-department dependencies) — the zoning-side Use Classification/Conditional Use Permit process and the Building Division's permit process are genuinely separate tracks with separate fees.

Frequently asked questions

Estes Park requires a change of use / change of occupancy permit for: No standalone change-of-use permit, application, or fee line by that name is published by the Town — confirmed absent from the Planning Forms and References page and the Fee Schedule (Development Review Fees, effective January 2024), both checked directly this session; The Estes Park Development Code (EPDC) Chapter 4 (Zoning Districts) contains the use tables listing which land uses are allowed by right, allowed only as a conditional/special-review use, or prohibited within each zoning district; Where a proposed use does not clearly fit an existing EPDC use classification, EPDC Section 3.12 (Use Classification) provides a formal determination process: a voluntary but Town-encouraged pre-application conference, followed by a staff review that must reach a final written determination within 30 days of a complete application being submitted — confirmed directly via the Town's own 'Use Classifications' guide (Planning Division, revised April 2020); The staff determination weighs factors including the proposed use's actual/projected characteristics against the use classifications already permitted in the zoning district, site area/floor space devoted to the use, relative sales and employee counts, hours of operation, vehicle trips generated, signage, and consistency with the Code's stated intent; an official record is kept on file with the Community Development Department; A Use Classification determination may be appealed to the Town Board; If the proposed use requires approval as a conditional/special-review use rather than being allowed by right in the applicable zoning district, a Conditional Use Permit application and $900.00 fee is required ($250.00 if the conditional use is specifically an accessory dwelling unit) — the Town's Fee Schedule lists this fee, but unlike Berthoud, the Town's public Development Review Guides list does not include a dedicated Conditional Use Permit / Special Review process guide, so the specific hearing, notice, and timeline steps for THIS stage were not independently confirmed during this research pass — an honest gap; Existing nonconforming uses (legally established before the current use regulations took effect, but no longer matching them) are separately governed by EPDC Chapter 6: they may continue and be repaired/maintained, but generally cannot be altered or extended, and a nonconforming use that is abandoned or discontinued for 12 consecutive months permanently loses its nonconforming status; If the change of use is accompanied by construction, remodeling, or a formal occupancy-classification change requiring building-code compliance work, the ordinary Town Building Permit process applies (see this file's commercial-building-permit and commercial-tenant-improvement-permit entries), billed under the general valuation-based Table 1-A fee schedule (Ordinance 03-16) — no distinct change-of-use fee line exists on the Building Division's own side; Unlike Berthoud, this file's codesAdopted list for Estes Park does not include an adopted International Existing Building Code (IEBC); Estes Park's 2021 IBC adoption (Municipal Code Section 14.12.010) includes only the standard IBC Section 101.4 secondary-code references with the fire-code subsection stricken — no IEBC-specific change-of-occupancy provision was independently located during this research pass, an honest gap surfaced rather than an invented process. If your project isn't listed, confirm with Town of Estes Park Community Development Department — Division of Building Safety (administered by SAFEbuilt Colorado) at (970) 577-3735 before starting work.

In Estes Park, the published Land Use and Zoning Determination — Standard is: $75.00. Additional published fees: Land Use and Zoning Determination — Complex — $100.00 + $50.00 per hour; Conditional Use Permit — $900.00; Conditional Use Permit — Accessory Dwelling Unit — $250.00; Building Permit Fee (if construction/alteration accompanies the use change) — Valuation-based per Table 1-A, Ordinance 03-16 — same schedule documented elsewhere in this file. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

The Town's own EPDC Section 3.12 guide states a 30-day turnaround, from a complete application to a final written staff determination, for the Use Classification step specifically. No separate numeric timeline is published for the Conditional Use Permit hearing process itself.

Depending on your project, Estes Park may also ask for: Land Use and Zoning Determination Application (Community Connect / Community Core, PLANNING tab); Conditional Use Permit Application; Building Permit Application (Community Connect Portal). See the required-documents checklist on this page for details on each.

Estes Park requires 2 inspection(s) for a change of use / change of occupancy permit, in order: Use Classification / Zoning Compliance Review, Building Division Inspections (if construction accompanies the use change). Schedule each through Town of Estes Park Community Development Department — Division of Building Safety (administered by SAFEbuilt Colorado) ((970) 577-3735).

Apply through Town of Estes Park Community Development Department — Division of Building Safety (administered by SAFEbuilt Colorado) at 170 MacGregor Avenue, Room 230, PO Box 1200, Estes Park, CO 80517. Phone: (970) 577-3735, email: building@estes.org. Office hours: Monday-Friday 8:00am-4:00pm, second floor of Town Hall. Official information: https://estespark.colorado.gov/building-safety.

No standalone change-of-use permit exists. A change in use is evaluated under the Estes Park Development Code's Chapter 4 use tables, and, where the use doesn't clearly fit an existing classification, through the EPDC Section 3.12 Use Classification determination process. If the use requires zoning approval beyond a use allowed by right, a $900.00 Conditional Use Permit ($250.00 for an ADU) is required.

Per EPDC Chapter 6, a legally nonconforming use can continue and be repaired/maintained, but generally cannot be altered or extended. If the use is abandoned or discontinued for 12 consecutive months, its nonconforming status permanently terminates and any further use of the property must conform to current regulations.