Inspection sequence, scheduling, and re-inspection fees for building permits in Cortez, Colorado.

Verified 2026-07-06 · Source

How to schedule

Inspections are requested through the building department below.

Address
123 Roger Smith Avenue, Cortez, CO 81321
Phone
970-565-3402
Office hours
Monday-Thursday 7:30 a.m.-5:00 p.m.; Friday 8:00 a.m.-12:00 p.m. Permit Tech/Deputy City Clerk (Cheryl Lindquist): 970-564-4016. Fire Inspector/Building Inspector (Sean Canada): 970-564-4009. 24-hour inspection scheduling line: 970-564-4071 (checked daily at 8:00 a.m.; inspections performed 9:00 a.m.-4:30 p.m. Monday-Thursday, excluding holidays). Fax: 970-565-8172.

Published scheduling rules

  • Schedule inspections through the 24-hour line (970-564-4071), checked daily at 8:00 a.m.; inspections are only performed 9:00 a.m.-4:30 p.m. Monday-Thursday, so a same-week inspection request near a Thursday deadline should be called in as early as possible. (Residential Building Permit (New Construction))
  • Inspections are scheduled via a 24-hour line (970-564-4071, checked daily at 8:00 a.m.) but only performed Monday-Thursday, 9:00 a.m.-4:30 p.m. — plan around the compressed Friday-off inspection week (City Hall itself is also only open until noon on Fridays). (General)

Inspection sequence

Applies to: Residential Addition / Remodel Permit

  1. 1

    Foundation (if new footings)

    Before concrete pour, per 32-inch minimum frost depth

  2. 2

    Rough Framing

    Framing tied into existing structure, complete before cover

  3. 3

    Rough Plumbing / Rough Mechanical

    Trade rough-ins before concealment; electrical rough-in inspected separately by the State of Colorado (DORA)

  4. 4

    Final Inspection

    All City-permitted work complete per approved plans

Applies to: Residential Building Permit (New Construction)

  1. 1

    Foundation

    Before concrete pour, per 32-inch minimum frost depth

  2. 2

    Rough Framing

    Framing complete before cover

  3. 3

    Rough Plumbing / Rough Mechanical

    Trade rough-ins inspected by the City before concealment; electrical rough-in is inspected separately by the State of Colorado (DORA), not the City

  4. 4

    Final Inspection

    All City-permitted work complete per approved plans and applicable codes; scheduled via the 24-hour inspection line (970-564-4071)

Applies to: Accessory Dwelling Unit (ADU) Permit

  1. 1

    Foundation (if new construction)

    Before concrete pour, per 32-inch minimum frost depth

  2. 2

    Rough Framing / Rough Plumbing / Rough Mechanical

    Trade rough-ins before concealment; electrical rough-in inspected separately by the State of Colorado (DORA)

  3. 3

    Final Inspection

    All City-permitted work complete per approved plans and Conditional Use Permit conditions

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough Mechanical

    Ductwork, flues, and equipment placement before concealment

  2. 2

    Final Inspection

    Equipment operational, combustion air and venting verified

Applies to: Plumbing Permit

  1. 1

    Rough Plumbing

    Pipe, drain, waste, and vent installation before concealment; scheduled via the 24-hour inspection line

  2. 2

    Final Inspection

    Fixtures connected, no leaks, proper venting verified

Applies to: Solar PV Permit (Split City/State Jurisdiction)

  1. 1

    City Building Inspection (Structural/Racking)

    City of Cortez inspects the structural/racking portion of the installation

  2. 2

    State Electrical Inspection

    Colorado State Electrical Board inspects the interconnection/electrical work, since this is not handled by the City

Cortez building permits

Get alerts for Cortez

We'll email you when Cortez's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.