Residential Building Permit (New Construction) in Cortez, Colorado

Required for construction of new single-family and other residential structures within Cortez city limits, per the Building Permit Application's project-type checklist ('New Residential'). Reviewed under the 2015 IBC/IRC (with the local exception of IRC Section R313, fire sprinklers, not adopted) and Cortez's own structural design criteria. Issued and inspected by the City of Cortez Division of Planning & Building; electrical work is separately permitted and inspected by the State of Colorado (DORA), not the City.

Verified 2026-07-06 · Source

When you need this permit

  • Plans must comply with the 2015 IBC/IRC as locally adopted (IRC Section R313, residential fire sprinklers, is explicitly NOT adopted in Cortez)
  • Must meet Cortez's Structural Design Criteria: 30 psf non-reducible ground snow load, Wind Design 115/51, 32-inch minimum frost depth, Seismic Design Category B, 7-degree F winter design temperature, Moderate/Heavy termite infestation probability, Air Freezing Index 1500, Severe weathering exposure, and required ice barrier underlayment
  • Application must declare a construction value for all applications (required field on the Building Permit Application)
  • All applications must be submitted digitally with 2 sets of copies of construction documents
  • A Site Plan is required (drawn to scale; not necessarily by a surveyor/engineer) along with floor plans; elevations, cross sections, foundation plan, framing plan, and utility plan (with domestic water meter size) may be required for new builds
  • Public improvements (sidewalk, curb, gutter, streetscape) may be required as a condition of the permit
  • Electrical work on the project is separately permitted and inspected by the State of Colorado (DORA, 800-886-7675), not included in this City building permit
  • If plumbing or electrical work is performed and the property is intended for resale, rental, or is a commercial structure, Colorado law requires a licensed plumber and/or electrician Contractor

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — valuation $1.00 to $500.00City of Cortez Fee Schedule, effective January 1, 2026, Planning and Building section
$75.00
Building Permit Fee — valuation $501.00 to $2,000.00
$75.00 for the first $500.00 plus $4.00 for each additional $100.00 or fraction thereof, to and including $2,000.00
Building Permit Fee — valuation $2,001.00 to $25,000.00
$135.00 for the first $2,000.00 plus $13.75 for each additional $1,000.00 or fraction thereof, to and including $25,000.00
Building Permit Fee — valuation $25,001.00 to $50,000.00
$451.25 for the first $25,000.00 plus $10.50 for each additional $1,000.00 or fraction thereof, to and including $50,000.00
Building Permit Fee — valuation $51,000.00 to $100,000.00The fee schedule's own tier boundary reads '$51,000.00' rather than '$50,001.00' — transcribed exactly as published; treat the $50,000-$51,000 gap as a schedule quirk to confirm with the Building Division rather than a transcription choice made here
$713.75 for the first $50,000.00 plus $7.25 for each additional $1,000.00 or fraction thereof, to and including $100,000.00
Building Permit Fee — valuation $100,001.00 to $500,000.00
$1,076.25 for the first $100,000.00 plus $6.00 for each additional $1,000.00 or fraction thereof, to and including $500,000.00
Building Permit Fee — valuation $500,001.00 to $1,000,000.00
$3,476.25 for the first $500,000.00 plus $5.00 for each additional $1,000.00 or fraction thereof, to and including $1,000,000.00
Building Permit Fee — valuation $1,000,001.00 and up
$5,976.25 for the first $1,000,000.00 plus $4.00 for each additional $1,000.00 or fraction thereof
Use TaxThe 2026 Fee Schedule references this ordinance for Use Tax but does not itemize a specific percentage rate on the Planning & Building fee page itself; confirm the current rate with the Building Division before quoting a total project cost
Charged per City Council Ordinance No. 1054, Series 2005 (8/9/2005)

Review timeline

Plan review
Not published — contact the department

How long did your Residential Building Permit (New Construction) permit actually take in Cortez?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation

    Before concrete pour, per 32-inch minimum frost depth

  2. 2

    Rough Framing

    Framing complete before cover

  3. 3

    Rough Plumbing / Rough Mechanical

    Trade rough-ins inspected by the City before concealment; electrical rough-in is inspected separately by the State of Colorado (DORA), not the City

  4. 4

    Final Inspection

    All City-permitted work complete per approved plans and applicable codes; scheduled via the 24-hour inspection line (970-564-4071)

See the full Cortez inspection guide — scheduling & re-inspection fees →

Tips

  • Cortez has NOT adopted IRC Section R313 (residential fire sprinkler systems) — new single-family homes are not required to include fire sprinklers under the local code, unlike jurisdictions that adopt the IRC without this exception.
  • Cortez's design snow load (30 psf, non-reducible) and 32-inch frost depth are meaningfully lower than nearby Front Range/mountain jurisdictions like Golden or Durango — do not reuse a generic high-snow-load Colorado design assumption for a Cortez project.
  • Electrical work is NOT part of the City's building permit — schedule state DORA electrical inspections (800-886-7675) independently of the City's own inspection sequence.
  • Schedule inspections through the 24-hour line (970-564-4071), checked daily at 8:00 a.m.; inspections are only performed 9:00 a.m.-4:30 p.m. Monday-Thursday, so a same-week inspection request near a Thursday deadline should be called in as early as possible.

Frequently asked questions

Cortez requires a residential building permit (new construction) for: Plans must comply with the 2015 IBC/IRC as locally adopted (IRC Section R313, residential fire sprinklers, is explicitly NOT adopted in Cortez); Must meet Cortez's Structural Design Criteria: 30 psf non-reducible ground snow load, Wind Design 115/51, 32-inch minimum frost depth, Seismic Design Category B, 7-degree F winter design temperature, Moderate/Heavy termite infestation probability, Air Freezing Index 1500, Severe weathering exposure, and required ice barrier underlayment; Application must declare a construction value for all applications (required field on the Building Permit Application); All applications must be submitted digitally with 2 sets of copies of construction documents; A Site Plan is required (drawn to scale; not necessarily by a surveyor/engineer) along with floor plans; elevations, cross sections, foundation plan, framing plan, and utility plan (with domestic water meter size) may be required for new builds; Public improvements (sidewalk, curb, gutter, streetscape) may be required as a condition of the permit; Electrical work on the project is separately permitted and inspected by the State of Colorado (DORA, 800-886-7675), not included in this City building permit; If plumbing or electrical work is performed and the property is intended for resale, rental, or is a commercial structure, Colorado law requires a licensed plumber and/or electrician. If your project isn't listed, confirm with City of Cortez Community & Economic Development Department, Division of Planning & Building at 970-565-3402 before starting work.

In Cortez, the published Building Permit Fee — valuation $1.00 to $500.00 is: $75.00. Additional published fees: Building Permit Fee — valuation $501.00 to $2,000.00 — $75.00 for the first $500.00 plus $4.00 for each additional $100.00 or fraction thereof, to and including $2,000.00; Building Permit Fee — valuation $2,001.00 to $25,000.00 — $135.00 for the first $2,000.00 plus $13.75 for each additional $1,000.00 or fraction thereof, to and including $25,000.00; Building Permit Fee — valuation $25,001.00 to $50,000.00 — $451.25 for the first $25,000.00 plus $10.50 for each additional $1,000.00 or fraction thereof, to and including $50,000.00; Building Permit Fee — valuation $51,000.00 to $100,000.00 — $713.75 for the first $50,000.00 plus $7.25 for each additional $1,000.00 or fraction thereof, to and including $100,000.00; Building Permit Fee — valuation $100,001.00 to $500,000.00 — $1,076.25 for the first $100,000.00 plus $6.00 for each additional $1,000.00 or fraction thereof, to and including $500,000.00; Building Permit Fee — valuation $500,001.00 to $1,000,000.00 — $3,476.25 for the first $500,000.00 plus $5.00 for each additional $1,000.00 or fraction thereof, to and including $1,000,000.00; Building Permit Fee — valuation $1,000,001.00 and up — $5,976.25 for the first $1,000,000.00 plus $4.00 for each additional $1,000.00 or fraction thereof; Use Tax — Charged per City Council Ordinance No. 1054, Series 2005 (8/9/2005). These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

The City does not publish a specific plan-review turnaround figure. Colorado is a home-rule state with no statewide review-time statute, and Cortez's own Building Permit Application, FAQ, and Building Division pages do not state a day-count commitment. Contact Planning & Building (970-565-3402) directly for current expectations.

You'll need: City of Cortez Building Permit Application; Site Plan; Floor Plans, Elevations, Foundation Plan, Framing Plan, Utility Plan. See the required-documents checklist on this page for details on each.

Cortez requires 4 inspection(s) for a residential building permit (new construction), in order: Foundation, Rough Framing, Rough Plumbing / Rough Mechanical, Final Inspection. Schedule each through City of Cortez Community & Economic Development Department, Division of Planning & Building (970-565-3402).

Apply through City of Cortez Community & Economic Development Department, Division of Planning & Building at 123 Roger Smith Avenue, Cortez, CO 81321. Phone: 970-565-3402, email: clindquist@cortezco.gov. Office hours: Monday-Thursday 7:30 a.m.-5:00 p.m.; Friday 8:00 a.m.-12:00 p.m. Permit Tech/Deputy City Clerk (Cheryl Lindquist): 970-564-4016. Fire Inspector/Building Inspector (Sean Canada): 970-564-4009. 24-hour inspection scheduling line: 970-564-4071 (checked daily at 8:00 a.m.; inspections performed 9:00 a.m.-4:30 p.m. Monday-Thursday, excluding holidays). Fax: 970-565-8172.. Official information: https://www.cortezco.gov/186/Building-Permits-Applications.

The City of Cortez Division of Planning & Building (Community & Economic Development Department) issues building, plumbing, and mechanical permits for all work within Cortez city limits. Cortez is the only municipality in Montezuma County with a building department — the County itself has none and does not enforce a residential building code in unincorporated areas.

No. All electrical permits and inspections in Cortez are handled by the Colorado Department of Regulatory Agencies (DORA) at 800-886-7675, not the City Building Division.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Cortez building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.