Eagle building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Eagle, Idaho.
Verified 2026-07-17 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 660 E Civic Lane, Eagle, ID 83616
- Phone
- 208-489-8760
- Office hours
- Mon–Fri 9:00 AM – 4:00 PM (phone hours)
- Website
- Official site
Published scheduling rules
- All inspection requests must be submitted through the Contractor Portal (eagle_permit.portal.iworq.net) before 4:00 PM to receive an inspection the next business day. (Residential Building Permit (New Construction))
- All inspection requests submitted through the Contractor Portal before 4:00 PM for next-business-day scheduling. (Commercial Building Permit (New Construction / Tenant Improvement))
- Submit all inspection requests through the Contractor Portal before 4:00 PM for next-business-day scheduling. (Electrical Permit)
- Submit all inspection requests through the Contractor Portal before 4:00 PM for next-business-day scheduling. (EV Charger / EVSE Permit (Electrical Permit))
- Submit all inspection requests through the Contractor Portal before 4:00 PM for next-business-day scheduling. (Mechanical / HVAC Permit)
- Submit inspection requests through the Contractor Portal before 4:00 PM for next-business-day scheduling. (Plumbing Permit)
- Eagle's fee schedule explicitly names 'Solar / Renewable Energy' as its own tier within the 'Other Installations' electrical fee category (grouped with Commercial/Industrial work), rather than folding it into a generic residential electrical fee — request inspections through the City's Contractor Portal. (Solar / Renewable Energy Permit)
- Submit required documentation and plans through the City's Contractor Portal; request inspections through the same portal after permit issuance (Solar / Renewable Energy Permit)
- All inspection requests must be submitted through the Eagle Contractor Portal (eagle_permit.portal.iworq.net) before 4:00 PM to receive an inspection the next business day. After 4:00 PM on Friday = following Tuesday. Weekend requests = following Tuesday. (General)
Inspection sequence
Applies to: Commercial Building Permit (New Construction / Tenant Improvement)
- 1
Foundation Only (commercial only)
Foundation-only permits available for commercial projects — building may proceed with foundation while full permit review continues
- 2
Framing / Structural
After structural framing complete and before wall cover
- 3
Final
All work complete per approved plans and design review conditions; Certificate of Occupancy issued after passing
Applies to: Mechanical / HVAC Permit
- 1
Gas Piping Pressure Test
Required before concealing gas piping — verify no leaks under test pressure
- 2
Rough-In / Ductwork
Mechanical equipment and ductwork before walls closed — verify clearances and support per 2018 IMC
- 3
Final
Equipment operational, combustion air verified, venting correct per 2018 IMC/IFGC
Applies to: Plumbing Permit
- 1
Underground / Slab Plumbing
Before concrete pour — verify pipe slope, materials, and cleanouts per 2017 ISPC
- 2
Rough-In
After pipes installed before walls closed — pressure test required
- 3
Final
All fixtures connected, no leaks, proper venting verified per 2017 Idaho State Plumbing Code
Applies to: Residential Building Permit (New Construction)
- 1
Footing / Foundation
Submit online via Contractor Portal before 4:00 PM for next-business-day inspection; footing inspections shall be approximately one hour prior to pouring concrete. Pouring times must be scheduled between 9 AM and 4 PM.
- 2
Framing
After framing, sheathing, and rough-in trades complete — before insulation or wall cover
- 3
Final
All work complete per approved plans; Certificate of Occupancy issued after passing final inspection
Applies to: Electrical Permit
- 1
Rough-In
After wiring installed before walls closed — verify conductor sizing, box placement, and service connections per 2023 NEC
- 2
Final
All devices installed, panel labeled, GFCI/AFCI protection verified per 2023 NEC
Applies to: EV Charger / EVSE Permit (Electrical Permit)
- 1
Rough-In
After wiring installed before walls closed (if applicable) — verify conductor sizing, box placement, and service connections per 2023 NEC
- 2
Final
Charger circuit/unit installed, panel labeled, GFCI/AFCI protection verified per 2023 NEC
Applies to: Fence and Retaining Wall Permit
- 1
Footing (if structural/over-height fence or retaining wall)
Before concrete pour for footings on fences over 6 ft or retaining walls over 4 ft requiring a building permit
- 2
Final
All construction complete per approved plans and zoning certificate conditions
Applies to: Solar / Renewable Energy Permit
- 1
Building Inspection (Structural/Racking)
City of Eagle inspects the structural/racking portion of the installation
- 2
Electrical Inspection
City of Eagle inspects the interconnection/electrical work under the Solar/Renewable Energy fee tier
Final inspection only: Sign Permit
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-17.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Eagle building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Eagle building permits
Get alerts for Eagle
We'll email you when Eagle's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.