Plumbing Permit in Eagle, Idaho

Required for plumbing installations, alterations, and repairs in Eagle residential and commercial properties, including water heaters, fixture additions, sewer/water service lines, backflow prevention devices, and lawn sprinklers. Governed by the 2017 Idaho State Plumbing Code (ISPC — IAPMO). Apply through the Eagle Contractor Portal.

Verified 2026-06-29 · Source

When you need this permit

Required documents

Fee schedule

Fee typeAmountNotes
All plumbing permits — fees calculated from Verified Contract Price TableCost up to $20,000: multiply by 3% plus $60; cost $20,001–$100,000: subtract $20,000, multiply by 2%, plus $660; cost over $100,001: subtract $100,000, multiply by 1%, plus $2,260Eagle Building Department Fee Schedule (Resolution 23-34, Jan 2023) — Plumbing Fees section. Fees based on fair market project value (total labor, materials, equipment including overhead and profit). Not reducible for owner-supplied materials.
Water Heater / Water Softener$65.00Eagle Building Department Fee Schedule (Resolution 23-34)
Backflow Prevention Device$65.00Eagle Building Department Fee Schedule (Resolution 23-34)
Sewer Line Installation (base fee not applicable)$65.00Eagle Building Department Fee Schedule (Resolution 23-34)
Water Line Installation (base fee not applicable)$65.00Eagle Building Department Fee Schedule (Resolution 23-34)
Sewer and Water Combination (base fee not applicable)$65.00Eagle Building Department Fee Schedule (Resolution 23-34)
Additional Fixtures Each (excluding garbage disposals and dishwashers)$10.00 eachEagle Building Department Fee Schedule (Resolution 23-34)
Replacement Fixtures Each$10.00 eachEagle Building Department Fee Schedule (Resolution 23-34)
Swimming Pools — Basic Fee (covers 3 required inspections)$195.00Eagle Building Department Fee Schedule (Resolution 23-34)
Multipurpose Fire Sprinklers and Domestic Water Supply System (1–2 family)$65.00 or $4 per fire sprinkler head, whichever is greaterEagle Building Department Fee Schedule (Resolution 23-34)
Re-inspection Fee$65.00 minimumEagle Building Department Fee Schedule (Resolution 23-34)

Review timeline

~15 business days

Typical estimate — confirm current times with the Eagle building department

Inspection process

  1. 1

    Underground / Slab Plumbing

    Before concrete pour — verify pipe slope, materials, and cleanouts per 2017 ISPC

  2. 2

    Rough-In

    After pipes installed before walls closed — pressure test required

  3. 3

    Final

    All fixtures connected, no leaks, proper venting verified per 2017 Idaho State Plumbing Code

Tips

Frequently asked questions

Do I need a permit to replace a water heater in Eagle?
Yes. Water heater and water softener replacements require a plumbing permit in Eagle. The fee is $65. Apply through the Eagle Contractor Portal (eagle_permit.portal.iworq.net) or in person at 660 E Civic Lane. Source: Eagle Building Department Fee Schedule, Resolution 23-34.

Sources & verification

Verified against official sources. Last reviewed 2026-06-29.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Eagle building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Other permits in Eagle

Related guides

Get the AI compliance checklist

Upload your project scope, get a jurisdiction-specific checklist of everything you need. Coming soon.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.