Inspection sequence, scheduling, and re-inspection fees for building permits in Sandpoint, Idaho.

Verified 2026-08-21 · Source

How to schedule

Inspections are requested through the building department below.

Address
1123 Lake St, Sandpoint, ID 83864
Phone
208-263-3423 (Building); 208-263-3370 (Planning & Community Development general line)
Office hours
Not published as a specific daily schedule on the City's Building or Planning & Community Development pages as of the last verification (contact 208-263-3423 to confirm); Bonner County Planning Department (a separate, non-city department) publishes Monday-Friday 9:00 a.m.-5:00 p.m. for its own office, but that hours listing does not apply to the City of Sandpoint's Building team.

Inspection sequence

Applies to: Commercial Building Permit (New Commercial, Multi-Family, and Industrial Construction)

  1. 1

    Foundation/Footing

    Before placing concrete or grout (standard IBC-based inspection sequence; a specific commercial inspection checklist is not separately published beyond the submittal-document requirements in the City's Commercial Construction Checklist)

  2. 2

    Framing

    Floor and roof framing, fire separations and assembly listings, prior to concealment

  3. 3

    Fire/Life-Safety and Accessibility

    Verification of fire-resistance-rated assemblies, means-of-egress compliance (required where total occupant load exceeds 50), and accessible-route/accessible-element compliance per the Commercial Construction Checklist's floor-plan requirements

  4. 4

    Final

    Final inspection required prior to occupancy/Certificate of Occupancy

Applies to: Residential Building Permit (New Single-Family Construction)

  1. 1

    Foundation/Footing

    Before placing concrete or grout (standard IRC-based inspection sequence; specific checklist not separately itemized beyond the Design Criteria/Framing plan requirements published by the City)

  2. 2

    Framing

    Floor and roof framing, fire separations, prior to concealment

  3. 3

    Final

    Final inspection required prior to occupancy

Applies to: Commercial Tenant Improvement Permit

  1. 1

    Rough-In (scope-dependent)

    Framing, fire-separation, and any mechanical/plumbing rough-in inspection appropriate to the altered space, before concealment; a TI-specific inspection sequence is not separately published by the City

  2. 2

    Final

    Final inspection required prior to occupancy of the altered/changed-use tenant space

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In

    Ductwork, gas piping, and mechanical equipment rough-in before concealment

  2. 2

    Final

    Equipment operational, gas appliance shutoff/combustion air verified

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    City Building Inspection(s)

    Structural/roof-mount racking and roof-penetration compliance, per the City's standard/single inspections per phase included in the Building Fee/Valuation

  2. 2

    DOPL Electrical Rough-In/Final

    State-inspected; project valuation verified against actual cost at Final

Final inspection only: EV Charger / EVSE Permit

Sources & verification

Verified against official sources. Last reviewed 2026-08-21.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Sandpoint building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Sandpoint building permits

Get alerts for Sandpoint

We'll email you when Sandpoint's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.