Solar Photovoltaic (PV) Permit in Sandpoint, Idaho

Required for installing a rooftop or ground-mount photovoltaic system within Sandpoint city limits. TWO separate permits apply: a City of Sandpoint Building Permit for the structural/roof-mount work (valuation-based, no dedicated solar line item on the City's own Fee Schedule) and a State of Idaho DOPL Electrical Permit for the PV electrical installation (DOPL, not the City, issues electrical permits in Sandpoint, per the City's own 'Permit Types' handout), which DOES publish a dedicated Solar/Renewable Energy fee formula.

Verified 2026-07-20 · Source

When you need this permit

  • City of Sandpoint Building Permit required for the structural/roof-mount component; reviewed under the same valuation-based Building Fee/Valuation table used for all other building work — no solar-specific fee line found on the City's Fee Schedule (effective 8/21/2024, Res 24-061)
  • State of Idaho DOPL Electrical Permit required separately for the PV system's electrical installation — purchased online at dbs.idaho.gov (redirects to dopl.idaho.gov); NOT issued by the City of Sandpoint (confirmed on this jurisdiction's electrical-plumbing-permit-dopl entry)
  • Solar/Renewable Energy box must be checked on the DOPL Electrical Permit Worksheet, with total system cost entered as the Job Value Amount
  • Grid-Connected Renewable Energy systems require a plan-check permit number from DOPL FIRST (1-800-955-3044) before the installation permit can be purchased
  • Building Plan Check Fee (65% of the building permit fee) and Zoning Review (10% of the building permit fee, in addition to Plan Check) apply to the City-side building permit

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

City Building Permit — valuation $0-$2,000City of Sandpoint Fee Schedule (eff. 10/1/2024, Res 24-061), 'Building Fee/Valuation' table; no dedicated solar line item
$64.76 for the first $1,300, plus $3.68 per additional $100
City Building Permit — valuation $2,001-$25,000
$90.52 for the first $2,000, plus $16.84 per additional $1,000
City Building Permit — valuation $25,001-$50,000
$477.84 for the first $25,000, plus $12.04 per additional $1,000
City Building Permit — valuation $50,001-$100,000
$778.84 for the first $50,000, plus $8.43 per additional $1,000
City Building Permit — Minimum Building Permit Fee
$180.54 (applies if the calculated valuation-based fee is lower)
Building Plan Check Fee (standard, up to two reviews)
65% of the building permit fee
Zoning Review
10% of the building permit fee, in addition to Building Plan Check
State of Idaho DOPL Electrical Permit — Solar/Renewable Energy (up to $10,000 system cost)DOPL Electrical Permit Worksheet (Fee Schedule), 'Other Installations including Solar/Renewable Energy' section — statewide formula, same as used elsewhere in Idaho where DOPL (not the local jurisdiction) issues electrical permits
(Total cost of electrical system x 0.02) + $60
State of Idaho DOPL Electrical Permit — Solar/Renewable Energy ($10,001-$100,000 system cost)
((Total cost of electrical system - $10,000) x 0.01) + $260
State of Idaho DOPL Electrical Permit — Solar/Renewable Energy (over $100,001 system cost)
((Total cost of electrical system - $100,000) x 0.005) + $1,160

Review timeline

Plan review
Not published — contact the department

How long did your Solar Photovoltaic (PV) Permit permit actually take in Sandpoint?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    City Building Inspection(s)

    Structural/roof-mount racking and roof-penetration compliance, per the City's standard/single inspections per phase included in the Building Fee/Valuation

  2. 2

    DOPL Electrical Rough-In/Final

    State-inspected; project valuation verified against actual cost at Final

See the full Sandpoint inspection guide — scheduling & re-inspection fees →

Tips

  • Solar in Sandpoint requires TWO separate permits from TWO separate agencies: a City of Sandpoint Building Permit for the structural component (no solar-specific fee line — uses the general valuation table) and a State of Idaho DOPL Electrical Permit for the PV electrical work (which DOES have a dedicated Solar/Renewable Energy fee formula).
  • The City's Building Permit fee is valuation-based like any other building permit; expect Plan Check (65%) and Zoning Review (10%) on top of the base fee, both calculated as a percentage of the building permit fee.
  • A grid-connected system needs a DOPL plan-check permit number BEFORE you can purchase the state electrical installation permit — budget extra lead time for this step, separate from the City's own plan check.

Frequently asked questions

Sandpoint requires a solar photovoltaic (pv) permit for: City of Sandpoint Building Permit required for the structural/roof-mount component; reviewed under the same valuation-based Building Fee/Valuation table used for all other building work — no solar-specific fee line found on the City's Fee Schedule (effective 8/21/2024, Res 24-061); State of Idaho DOPL Electrical Permit required separately for the PV system's electrical installation — purchased online at dbs.idaho.gov (redirects to dopl.idaho.gov); NOT issued by the City of Sandpoint (confirmed on this jurisdiction's electrical-plumbing-permit-dopl entry); Solar/Renewable Energy box must be checked on the DOPL Electrical Permit Worksheet, with total system cost entered as the Job Value Amount; Grid-Connected Renewable Energy systems require a plan-check permit number from DOPL FIRST (1-800-955-3044) before the installation permit can be purchased; Building Plan Check Fee (65% of the building permit fee) and Zoning Review (10% of the building permit fee, in addition to Plan Check) apply to the City-side building permit. If your project isn't listed, confirm with City of Sandpoint Planning & Community Development Department (Building team) at 208-263-3423 (Building); 208-263-3370 (Planning & Community Development general line) before starting work.

No. The City's own Fee Schedule (eff. 10/1/2024) has no solar-specific line item — a solar installation's structural/roof-mount component is billed under the general valuation-based Building Fee/Valuation table. The electrical portion is a separate State of Idaho DOPL permit, which does have a dedicated Solar/Renewable Energy fee formula.

Sandpoint does not publish a plan-review timeline for this permit. Contact City of Sandpoint Planning & Community Development Department (Building team) at 208-263-3423 (Building); 208-263-3370 (Planning & Community Development general line) for current turnaround.

You'll need: City of Sandpoint Building Permit Application; DOPL Homeowner or Contractor Electrical Permit Application and Worksheet. See the required-documents checklist on this page for details on each.

Sandpoint requires 2 inspection(s) for a solar photovoltaic (pv) permit, in order: City Building Inspection(s), DOPL Electrical Rough-In/Final. Schedule each through City of Sandpoint Planning & Community Development Department (Building team) (208-263-3423 (Building); 208-263-3370 (Planning & Community Development general line)).

Apply through City of Sandpoint Planning & Community Development Department (Building team) at 1123 Lake St, Sandpoint, ID 83864. Phone: 208-263-3423 (Building); 208-263-3370 (Planning & Community Development general line), email: Building Official Pete Skon, pskon@sandpointidaho.gov; Department Head Jason Welker, jwelker@sandpointidaho.gov; City Planner Bill Dean, bdean@sandpointidaho.gov. Office hours: Not published as a specific daily schedule on the City's Building or Planning & Community Development pages as of this review (contact 208-263-3423 to confirm); Bonner County Planning Department (a separate, non-city department) publishes Monday-Friday 9:00 a.m.-5:00 p.m. for its own office, but that hours listing does not apply to the City of Sandpoint's Building team.. Official information: https://www.sandpointidaho.gov/building.

Sandpoint, Idaho has adopted: IMPORTANT JURISDICTIONAL NOTE: Sandpoint is a NOTABLE EXCEPTION inside Bonner County. Bonner County itself has adopted NO building code for unincorporated county land (confirmed no-program county, same category as WY Fremont County and NV Eureka County) — the county's own 'Building Location Permit' (BLP) is a zoning/setback/land-use permit only, administered by the Bonner County Planning Department, and is NOT a building-code permit (source: Bonner County Building Location Permit page, bonnercountyid.gov/building-location-permit, and the county's own 'Do I Need a Permit?' brochure, which lists 'Bonner County Planning Department' separately from 'Sandpoint Planning & Building Department' under 'Local Planning & Building Departments,' with construction/electrical/plumbing/HVAC permits routed to the State of Idaho DOPL rather than to the county). Sandpoint is the one incorporated city INSIDE Bonner County that maintains its own dedicated building department, building official, and locally-administered permit process under the International Building Code family — this City building-code requirement applies ONLY inside Sandpoint city limits. Anywhere else in Bonner County (unincorporated land) has no local building-code requirement beyond Idaho's statewide minimums administered by DOPL for the regulated trades. Source: Bonner County 'Do I Need a Permit?' brochure (bonnercountyid.gov/media/Planning/Application%20Information/BLP/Do%20I%20Need%20a%20Permit%20Brochure%2009.12.23.pdf), listing 'Sandpoint Planning & Building Department, 1123 Lake St., Sandpoint, ID 83864, 208-263-3158' as a distinct entry from 'Bonner County Planning Department, 1500 Hwy 2, Sandpoint, ID 83864, 208-265-1458' under the brochure's 'Local Planning & Building Departments' section.; Idaho Building Code Act, Idaho Code Title 39, Chapter 41: establishes a mandatory statewide building code adopted by the Idaho Building Code Board, administered locally by cities/counties that choose to adopt and enforce it per Idaho Code 39-4116. The state's currently adopted cycle (2021 International Codes family) took effect statewide January 1, 2022. Source: Idaho Building Code Act, Idaho Code Title 39 Ch. 41, legislature.idaho.gov/statutesrules/idstat/title39/t39ch41/; City of Sandpoint's own Building Permit Application form (rev. 202601) states the form 'is intended to be used for buildings that are constructed or altered per International Building Code (IBC)' and that construction must be 'in accordance with [all] building codes adopted by the City of Sandpoint,' directing applicants to 'the City of Sandpoint website under ‘Codes’ within Title 8' of City Code for the complete locally-adopted code list. Source: City of Sandpoint Building Permit Application (PDF, rev. 202601), sandpointidaho.gov/media/17816; City of Sandpoint's own Residential Construction Checklist states explicitly: 'Any construction following under the 2018 IRC' — confirming the 2018 International Residential Code is the locally-adopted residential code edition as of this review (NOTE: this is one cycle behind the current 2021 statewide-mandated cycle referenced on the Idaho Building Code Act page; the City's own published checklist has not been updated to reference the newer cycle as of this review — flagged here rather than assumed). Source: City of Sandpoint Residential Construction Checklist (PDF), sandpointidaho.gov/media/19366; Sandpoint City Code Title 8, 'Building Regulations' (codified via Ordinance No. 1436, enacted/effective 2/18/2026 per the Municode Library codification note), is the City's locally-adopted building-code chapter; full itemized code-edition text (specific IBC/IRC/IECC/IMC/IFGC sections and any local amendments) is hosted on Municode's JavaScript-rendered library platform (library.municode.com/id/sandpoint/codes/code_of_ordinances?nodeId=TIT8BURE) and could not be extracted as machine-readable text in this review; the City's own Building Permit Application PDF (above) is the primary source actually used here for the general 'City has adopted the IBC/IRC family under Title 8' fact.; Electrical, plumbing, and mechanical/HVAC trade permitting in Idaho is primarily administered directly by the Idaho Division of Occupational and Professional Licenses (DOPL), Division of Building Safety (208-334-3950 / 208-334-3233), in jurisdictions that have not assumed local authority. The City of Sandpoint's own published 'Permit Submittal' / Building Applications page lists only a Building Permit Application, a Mechanical Permit Application, and a Fire Alarm/Sprinkler Application as City-issued forms — NO separate City-issued Electrical or Plumbing permit application is published, consistent with DOPL retaining direct electrical and plumbing permitting/inspection jurisdiction in Sandpoint (the City issues Building and Mechanical/HVAC permits locally; Electrical and Plumbing work is permitted through DOPL). This could not be triple-confirmed against DOPL's own jurisdiction chart (referenced by DOPL's Electrical FAQ as a PDF chart of jurisdiction by geography, but a direct working link to that chart was not found in this review) — flagged rather than asserted with full certainty; the inference is based on the City's own silence on Electrical/Plumbing applications plus DOPL's own FAQ language that permit requirements 'vary widely' by whether a city/county has 'assumed jurisdiction.' Source: City of Sandpoint Building Applications / Permit Submittal page, sandpointidaho.gov/building/page/building-permit-forms; DOPL Electrical FAQ, dopl.idaho.gov/ele/ele-faqs/; Bonner County 'Do I Need a Permit?' brochure, bonnercountyid.gov/media/Planning/Application%20Information/BLP/Do%20I%20Need%20a%20Permit%20Brochure%2009.12.23.pdf. Local amendments apply — see the Sandpoint overview page for the full list.

The State of Idaho, through DOPL (Division of Occupational and Professional Licenses, formerly branded Division of Building Safety/DBS). The City of Sandpoint's own 'Permit Types' handout confirms electrical permits are issued through the State, not the City.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Sandpoint building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.