Idaho Falls building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Idaho Falls, Idaho.
Verified 2026-07-03 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 380 Constitution Way, P.O. Box 50220, Idaho Falls, ID 83405
- Phone
- 208-612-8270
- rhall@idahofalls.gov
- Office hours
- Building Division, 380 Constitution Way, Idaho Falls, ID 83405 (mailing: P.O. Box 50220, Idaho Falls, ID 83405); main line 208-612-8270
- Website
- Official site
Inspection sequence
Applies to: Residential Building Permit (New Construction)
- 1
Footing
Before concrete pour
- 2
Foundation
Foundation wall and rebar schedule verification
- 3
Underground Plumbing
Underground/under-slab plumbing before backfill or slab pour
- 4
IF Power Trench
Idaho Falls Power utility trench inspection for underground electrical service
- 5
Wall Sheathing
Structural wall sheathing before covering
- 6
Mechanical, Electrical, and Plumbing Rough-In
Combined MEP rough-in inspection
- 7
Framing
Structural framing complete before insulation/drywall
- 8
Firestop
Fire-resistant rated wall assemblies (Townhomes and Twinhomes)
- 9
Insulation
Insulation installed per energy code before drywall
- 10
Drywall
Drywall/fire-taping verification
- 11
Electrical Service
Electrical service inspection required before the utility will energize the service
- 12
Final
Combined Building, Mechanical, Electrical, Plumbing, Sidewalk, and Water Department final inspection
Applies to: Accessory Dwelling Unit (ADU) Permit
- 1
Footing/Foundation
For detached ADU construction, before concrete pour
- 2
Framing
Structural framing per approved plans
- 3
Mechanical, Electrical, and Plumbing Rough-In
Combined MEP rough-in for the ADU's independent systems
- 4
Final
Combined Building, Mechanical, Electrical, and Plumbing final inspection, including verification of the separate entrance and functional independence from the principal dwelling
Applies to: Residential Addition / Remodel Permit
- 1
Footing/Foundation
Required before concrete pour for additions, garages, and patio cover footings
- 2
Framing
Structural framing and connections to existing structure
- 3
Mechanical, Electrical, and Plumbing Rough-In
For additions/remodels affecting MEP systems
- 4
Final
Combined Building, Mechanical, Electrical, and Plumbing final inspection
Applies to: Electrical Permit
- 1
Rough-In
Wiring, box placement, and service connections before walls are closed
- 2
Electrical Service
Required before the utility (Idaho Falls Power) will energize the service
- 3
Final
Devices installed, panel labeled, protections verified per adopted NEC
Applies to: Plumbing Permit
- 1
Underground Plumbing
Before backfill or slab pour — verify pipe slope, materials, and cleanouts
- 2
Rough-In
After pipes installed, before walls closed
- 3
Final
All fixtures connected, no leaks, verified at combined Building/Mechanical/Electrical/Plumbing final
Applies to: Electric Vehicle (EV) Charger / EVSE Permit
- 1
Rough-In
Circuit, conduit, and disconnect placement before concealment, if applicable
- 2
Final
Charger mounted, circuit labeled, and installation verified per the adopted NEC (Article 625)
Applies to: Mechanical / HVAC Permit
- 1
Rough-In
Ductwork per approved duct design; venting for exhaust fans/HVAC equipment; gas pressure verification; duct sealing; PVC vent pressure testing and labeling
- 2
Final
Equipment sizing matches approved duct design; all venting/registers/grills installed; gas equipment fully operational; air balance report uploaded; A/C equipment fully charged and connected
Applies to: Solar Photovoltaic (PV) Permit
- 1
Rough Electrical
Conduit runs, wire sizing, and disconnect placement before energizing
- 2
Final
Panel mounting, racking attachment, roof penetration sealing, electrical connections, and inverter interconnection verified
Final inspection only: Demolition Permit, Re-Roofing Permit
Sources & verification
Verified against official sources. Last reviewed 2026-07-03.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Idaho Falls building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Idaho Falls building permits
Get alerts for Idaho Falls
We'll email you when Idaho Falls's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.