Electric Vehicle (EV) Charger / EVSE Permit — Idaho Falls, Idaho · Requirements sheet
Verified 2026-07-20 · Source: https://www.idahofallsidaho.gov/2080/Electrical
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Electric Vehicle (EV) Charger / EVSE Permit in Idaho Falls, Idaho
Idaho Falls has no dedicated EV charger/EVSE fee line or standalone permit category — EV charger (Level 2 or DC fast charging equipment) circuit installation is electrical work reviewed under the National Electrical Code as adopted by the City (currently 2023 NEC) and billed under the same Electrical Permit fee schedule used for any other electrical service work. Neither the City of Idaho Falls Fee Schedule (October 2025, items 2.10-2.13) nor the Electrical page carries an EV-specific fee line. Idaho Falls self-administers electrical permits through its own Chief Electrical Inspector rather than routing them to Idaho DOPL, so the same general Electrical Permit fee and process applies to EV charger installations as to any other electrical work.
Verified 2026-07-20 · Source
When you need this permit
- Electrical permit required for EV charger/EVSE circuit installation, per IBC/NEC Section 105.1 as adopted by the City
- Governed by the National Electrical Code edition currently adopted by the State of Idaho (2023 NEC per the City's Electrical page), including NEC Article 625 (Electric Vehicle Charging System) provisions
- Electrical contractor must hold Idaho DOPL state electrical licensure; a separate City trade license is not required for electricians
- Apply through the Cityworks online permitting portal
- If the installation increases electrical service demand or requires a panel upgrade, standard service-change documentation applies as for any other electrical service work
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
City of Idaho Falls Fee Schedule (October 2025), item 2.13.a, adopted by Resolution No. Show full citationHide
City of Idaho Falls Fee Schedule (October 2025), item 2.13.a, adopted by Resolution No. 2025-18 (adopted August 20, 2025, effective October 1, 2025): item 2.11.a (Residential Electrical Permits, $5.85 per each electrical service), item 2.10.a.i (Commercial Electrical Wiring Permit, first $20,000 of wiring costs, 1.50%), and item 2.13.a ($30.18 Permit Issuance Fee).Review timeline
Inspection process
- 1
Rough-In
Circuit, conduit, and disconnect placement before concealment, if applicable
- 2
Final
Charger mounted, circuit labeled, and installation verified per the adopted NEC (Article 625)
See the full Idaho Falls inspection guide — scheduling & re-inspection fees →
Tips
- Idaho Falls does not price EV chargers separately from other electrical work — expect the standard $5.85 per-service residential electrical fee (or the commercial wiring-cost-based fee) plus the $30.18 issuance fee, not a flat EV-specific rate.
- Unlike smaller Idaho jurisdictions that route electrical permits through the State DOPL, Idaho Falls issues and inspects its own electrical permits, including for EV chargers, through its own Chief Electrical Inspector.
- If your installation increases panel capacity or requires a service upgrade, budget for the same review as any other residential/commercial electrical service change.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fee schedules
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Idaho Falls building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Idaho Falls's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Idaho Falls yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Idaho Falls lands. Privacy.
Other permits in Idaho Falls
Electric Vehicle (EV) Charger / EVSE Permit in other cities
Compare electric vehicle (ev) charger / evse permit fees across Idaho →
Look up this fee in a different city →