How to schedule
Inspections are requested through the building department below.
- Address
- 225 West North Street, Grangeville, ID 83530
- Phone
- (208) 983-2851
- Office hours
- Mon–Fri 8:00 AM – 5:00 PM (closed holidays)
- Website
- Official site
Inspection sequence
Applies to: Residential Building Permit (New Construction, Additions, Alterations, Repairs)
- 1
Setback and Hole Inspection
After post/pier holes are dug but before concrete pads are poured (pole-barn/pole-building construction)
- 2
Footings
Before concrete pour — footing depth, rebar placement verified
- 3
Foundation
Foundation and stem wall inspection
- 4
Framing
After framing complete, before insulation or interior covering installed
- 5
Insulation
Insulation installed before sheetrock/wall cover
- 6
Sheetrock
Sheetrock/drywall inspection
- 7
Final
All work complete — electrical, plumbing, heating, and/or sheetrock finished; plans and permit must be on-site
Applies to: Commercial Building Permit (New Construction, Additions, Remodels & Tenant Improvements)
- 1
Footings
Before concrete pour -- footing depth and rebar placement verified
- 2
Foundation
Foundation and stem wall inspection
- 3
Framing
After framing complete, before insulation or interior covering installed
- 4
Insulation
Insulation installed before sheetrock/wall cover
- 5
Sheetrock
Sheetrock/drywall inspection
- 6
Final
All work complete -- electrical, plumbing, heating, and/or sheetrock finished; plans and permit must be on-site
Applies to: Solar Photovoltaic (PV) Permit
- 1
State Electrical Inspection
Performed by an Idaho DOPL inspector; wiring, disconnect placement, and interconnection point verified before energizing; renewable energy installations require a plan check prior to this final inspection
- 2
City Final Inspection (Building)
Racking/roof-penetration attachment and structural compliance verified under the County-contracted building official
Final inspection only: EV Charger / Electric Vehicle Charging Station Permit
Re-inspection fees
Fire Inspection (business/commercial occupancy) · Master Fee Schedule, 'Fire' section, effective 10/21/2025 ($50.00 Fire Inspection line), confirmed against the Fire Inspection Application form (Rev… Show full citationHide
Fire Inspection (business/commercial occupancy) · Master Fee Schedule, 'Fire' section, effective 10/21/2025 ($50.00 Fire Inspection line), confirmed against the Fire Inspection Application form (Rev 1/2020) itself, which has matching $50 checkboxes for the initial inspection and each additional inspection. Requested via a standalone Fire Inspection Application to the Fire Chief; not itself a building-permit line item, and the City's published materials do not state this is a mandatory prerequisite for building-permit issuance or occupancy of a new/converted commercial tenant space -- listed here because it is the closest fire-safety-inspection fee found relevant to opening a commercial business in Grangeville.Fire Inspection (business/commercial occupancy) · Master Fee Schedule, 'Fire' section, effective 10/21/2025, matching the $50 checkboxes on the Fire Inspection Application form (Rev 1/2020) for the… Show full citationHide
Fire Inspection (business/commercial occupancy) · Master Fee Schedule, 'Fire' section, effective 10/21/2025, matching the $50 checkboxes on the Fire Inspection Application form (Rev 1/2020) for the initial inspection and each additional inspection. Requested via a standalone Fire Inspection Application to the Fire Chief; the City's published materials do not state this is a mandatory prerequisite for building-permit issuance or for occupying a new or converted commercial tenant spaceSources & verification
Verified against official sources. Last reviewed 2026-08-02.
Fee schedules
Applications & forms
Checklists & handouts
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Grangeville building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Grangeville building permits
Get alerts for Grangeville
We'll email you when Grangeville's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.