Solar Photovoltaic (PV) Permit — Grangeville, Idaho · Requirements sheet
Verified 2026-07-20 · Source: https://dopl.idaho.gov/wp-content/uploads/2023/11/ELE-Contractor-Electrical-Permit-Application.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar Photovoltaic (PV) Permit in Grangeville, Idaho
Required for installation of rooftop or ground-mount solar photovoltaic systems within Grangeville city limits and its Area of Impact. Requires a City Building Permit (structural/racking, valuation-based per the City's Master Fee Schedule) plus a State of Idaho electrical permit (wiring/interconnection) issued by the Division of Occupational and Professional Licenses (DOPL, formerly Division of Building Safety) -- Grangeville does not run its own electrical permitting program. The state's own Contractor Electrical Permit Worksheet has a dedicated checkbox and valuation-based fee formula for 'Solar, Renewable Energy, power generation, power production, or energy storage systems.'
Verified 2026-07-20 · Source
When you need this permit
- City Building Permit & Plan Review Application submitted to Grangeville City Hall for the structural/racking scope; plan review and inspections performed under contract by a Nez Perce County building official
- Electrical wiring/interconnection scope requires a State of Idaho DOPL Contractor Electrical Permit (or Homeowner Electrical Permit if self-installed) -- not a City permit, since Grangeville has no electrical-permit program of its own
- On the DOPL Electrical Permit Worksheet, check the 'Solar, Renewable Energy, power generation, power production, or energy storage systems' box under 'Other Installations including Commercial/Industrial/Solar/Renewable Energy' and enter the total cost of the electrical system
- Renewable energy installations require a plan check prior to final inspection, per the DOPL Electrical Permit Worksheet
- As of January 1, 2023, all DOPL permits must be purchased online at dbs.idaho.gov rather than by mailed paper application
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
State Electrical Inspection
Performed by an Idaho DOPL inspector; wiring, disconnect placement, and interconnection point verified before energizing; renewable energy installations require a plan check prior to this final inspection
- 2
City Final Inspection (Building)
Racking/roof-penetration attachment and structural compliance verified under the County-contracted building official
See the full Grangeville inspection guide — scheduling & re-inspection fees →
Tips
- Grangeville splits solar permitting across two agencies: the City issues the structural Building Permit, but the State of Idaho (DOPL, dbs.idaho.gov) issues the electrical permit, since Grangeville has no electrical permitting program of its own.
- On the state electrical permit worksheet, make sure to check the dedicated 'Solar, Renewable Energy, power generation, power production, or energy storage systems' box -- this routes the project to the correct valuation-based fee formula rather than a generic electrical fee category.
- Renewable energy installations require a plan check prior to final inspection under the state's own worksheet -- budget extra lead time for this step.
- As of January 1, 2023, DOPL permits must be purchased online at dbs.idaho.gov rather than mailed in.
- Re-chase pass (2026-07-20): downloaded and read the current State of Idaho DOPL Application for Contractor Permit / Electrical Permit Worksheet (Fee Schedule) PDF directly from dopl.idaho.gov — live today, and its 'OTHER INSTALLATIONS including COMMERCIAL/INDUSTRIAL/SOLAR/RENEWABLE ENERGY' section matches this entry's tiered formula verbatim: (system cost x 0.02) + $60 up to $10,000; ((system cost - $10,000) x 0.01) + $260 for $10,001-$100,000; ((system cost - $100,000) x 0.005) + $1,160 over $100,001. This DOPL fee schedule is the explicit, statewide, currently-in-force state mechanism for the PV/renewable-energy electrical scope in any Idaho city (including this one) that has not independently certified its own electrical inspection program.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Grangeville building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Grangeville
Solar Photovoltaic (PV) Permit in other cities
Compare solar photovoltaic (pv) permit fees across Idaho →
Look up this fee in a different city →