How to schedule

Inspections are requested through the building department below.

Address
100 N Frederick Ave, P.O. Box 73, Harrison, ID 83833
Phone
(208) 689-3212
Office hours
Monday–Thursday 8:30 AM – 4:00 PM; Friday 9:00 AM – 3:00 PM (per City Hall Staff page); City's homepage hours widget separately lists Fri as closed — confirm same-day with City Hall at (208) 689-3212 before a Friday visit

Published scheduling rules

  • Harrison's Building Permit application form states '24 hour notice should be given for inspections' — schedule inspections at least a day ahead by calling (208) 689-3212 or emailing CityClerk@CityofHarrison.org. (Residential Building Permit (New Construction))

Inspection sequence

Applies to: Commercial Building Permit (New Construction, Additions & Remodels)

  1. 1

    Foundation / Footings

    Before concrete pour -- verify forms, rebar, and 24-inch minimum frost depth per City Code 8-1-2-1(A)(2)

  2. 2

    Framing

    After framing and rough-in trades, before insulation or wall cover

  3. 3

    Final

    All work complete per approved plans; required before Certificate of Occupancy is issued (City Code 8-1-5; 9-13-2(C))

Applies to: Residential Building Permit (New Construction)

  1. 1

    Foundation / Footings

    Before concrete pour — verify forms, rebar, and 24-inch minimum frost depth per City Code 8-1-2-1(A)(2)

  2. 2

    Framing

    After framing and rough-in trades, before insulation or wall cover

  3. 3

    Final

    All work complete per approved plans; required before Certificate of Occupancy is issued (City Code 8-1-5; 9-13-2(C))

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    State Electrical Inspection

    Performed by an Idaho DOPL inspector; wiring, disconnect placement, and interconnection point verified before energizing; renewable energy installations require a plan check prior to this final inspection

  2. 2

    City Final Inspection (Building)

    Racking/roof-penetration attachment and structural compliance verified by the City Building Official

Final inspection only: EV Charger / EVSE Permit

Sources & verification

Verified against official sources. Last reviewed 2026-08-02.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Harrison building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Harrison building permits

Get alerts for Harrison

We'll email you when Harrison's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.