Solar Photovoltaic (PV) Permit in Harrison, Idaho
Required for installation of rooftop or ground-mount solar photovoltaic systems within Harrison city limits. Requires a City Building Permit (structural/racking, valuation-based per 1997 UBC Table 1-A as adopted by City Code 8-1-4) plus a State of Idaho electrical permit (wiring/interconnection) issued by the Division of Occupational and Professional Licenses (DOPL) -- Harrison has no electrical-permit program of its own. The state's Contractor Electrical Permit Worksheet has a dedicated checkbox and valuation-based fee formula for 'Solar, Renewable Energy, power generation, power production, or energy storage systems.'
Verified 2026-07-20 · Source
When you need this permit
- City Application for Building Permit submitted to City Hall for the structural/racking scope, with fee calculated per 1997 UBC Table 1-A (City Code 8-1-4)
- Electrical wiring/interconnection scope requires a State of Idaho DOPL Contractor Electrical Permit (or Homeowner Electrical Permit if self-installed) -- not a City permit, since Harrison has no electrical-permit program of its own
- On the DOPL Electrical Permit Worksheet, check the 'Solar, Renewable Energy, power generation, power production, or energy storage systems' box under 'Other Installations including Commercial/Industrial/Solar/Renewable Energy' and enter the total cost of the electrical system
- Renewable energy installations require a plan check prior to final inspection, per the DOPL Electrical Permit Worksheet
- Working without a permit triggers a 100% investigation fee (equal to the actual permit fee) under City Code 8-1-8(C)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
State Electrical Inspection
Performed by an Idaho DOPL inspector; wiring, disconnect placement, and interconnection point verified before energizing; renewable energy installations require a plan check prior to this final inspection
- 2
City Final Inspection (Building)
Racking/roof-penetration attachment and structural compliance verified by the City Building Official
See the full Harrison inspection guide — scheduling & re-inspection fees →
Tips
- Harrison splits solar permitting across two agencies: the City issues the structural Building Permit, but the State of Idaho (DOPL, dbs.idaho.gov) issues the electrical permit, since Harrison has no electrical permitting program of its own.
- Harrison's building-permit fee is calculated per-project by the Building Official using the 1997 UBC Table 1-A valuation formula -- no dedicated flat fee schedule is published online, so get a written estimate before budgeting.
- On the state electrical permit worksheet, be sure to check the dedicated 'Solar, Renewable Energy, power generation, power production, or energy storage systems' box -- this routes the project to the correct valuation-based fee formula.
- Working without a permit in Harrison triggers a 100% investigation fee on top of the actual permit fee, per City Code 8-1-8(C) -- don't skip the paperwork even for a straightforward rooftop install.
- Re-chase pass (2026-07-20): downloaded and read the current State of Idaho DOPL Application for Contractor Permit / Electrical Permit Worksheet (Fee Schedule) PDF directly from dopl.idaho.gov — live today, and its 'OTHER INSTALLATIONS including COMMERCIAL/INDUSTRIAL/SOLAR/RENEWABLE ENERGY' section matches this entry's tiered formula verbatim: (system cost x 0.02) + $60 up to $10,000; ((system cost - $10,000) x 0.01) + $260 for $10,001-$100,000; ((system cost - $100,000) x 0.005) + $1,160 over $100,001. This DOPL fee schedule is the explicit, statewide, currently-in-force state mechanism for the PV/renewable-energy electrical scope in any Idaho city (including this one) that has not independently certified its own electrical inspection program.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Harrison building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Harrison
Solar Photovoltaic (PV) Permit in other cities
Compare solar photovoltaic (pv) permit fees across Idaho →
Look up this fee in a different city →