Rathdrum building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Rathdrum, Idaho.
Verified 2026-08-21 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 8047 W Main Street #2, Rathdrum, ID 83858
- Phone
- (208) 687-7242 (Building Department)
- Office hours
- Monday through Friday, 8:00 a.m. to 5:00 p.m. (published on the Community Development contact block). Applications are submitted electronically through the BS&A Online portal (bsaonline.com/?uid=2897); the City's own checklists state no hard copy or emailed submittals are accepted.
- Website
- Official site
Inspection sequence
Applies to: Change of Occupancy / Tenant Improvement Permit
- 1
Building Department Courtesy Site Visit
Pre-application visit to classify the project as Same Occupancy, Minor Change, or Major Change; determines the remainder of the review/permit path
- 2
Construction Inspections (as applicable)
Required inspections and approvals for any permitted building/mechanical/sign work performed under a Minor or Major Change permit
- 3
Final / Certificate of Occupancy
Certificate of Occupancy issued once required inspections and approvals are complete and, for Same Occupancy/Minor Change, the permit invoice is paid; for Major Change, any finalizations are also submitted on the Regulatory Compliance Form
Applies to: Commercial Building Permit (New Construction / Addition or Alteration)
- 1
Foundation/Footing
Before concrete pour, per 2018 IBC and City Design Criteria (24-inch minimum frost depth); new construction only
- 2
Framing
Structural framing per approved plans
- 3
Final
All work complete per approved plans; requires signed Owner/Lessee Consent for Required Permit Inspections
Applies to: Residential Addition or Alteration Permit
- 1
Footing/Foundation
Required before concrete pour for new footings
- 2
Framing
Structural framing and connection to the existing structure
- 3
Final
All work complete per approved plans
Applies to: Residential Single Family Building Permit (New Construction)
- 1
Foundation/Footing
Before concrete pour, per 2018 IRC and City Design Criteria (24-inch minimum frost depth)
- 2
Framing
Structural framing per approved plans
- 3
Final
All work complete per approved plans; requires signed Owner/Lessee Consent for Required Permit Inspections
Applies to: Solar PV Permit (City Building Permit + State-Issued Electrical)
- 1
Electrical Rough-In (DOPL-inspected)
Grounding and listing of all components verified before the system is covered or energized
- 2
Electrical Final (DOPL-inspected)
Wiring methods, labeling at the shut-off, working clearances, and system operation verified
- 3
Building Final (City-inspected)
Roof-mounting and structural attachment verified against approved plans; requires signed Owner/Lessee Consent for Required Permit Inspections
Applies to: Electrical Permit (State-Issued — Idaho DOPL, not the City)
- 1
Rough-In (DOPL-inspected)
Wiring and box placement before walls are closed, performed by a State of Idaho DOPL inspector
- 2
Final (DOPL-inspected)
Devices installed, panel labeled, protections verified per NEC
Applies to: EV Charging Station Permit (State-Issued Electrical Permit)
- 1
Electrical Rough-In (if applicable)
Required only if new circuit wiring is enclosed before final; conduit runs, wire sizing, and grounding verified (DOPL electrical inspection)
- 2
Electrical Final
EVSE circuit breaker sizing, GFCI protection (where applicable), working clearances, and charger mounting verified against NEC Article 625 (DOPL electrical inspection)
Applies to: Plumbing Permit (State-Issued — Idaho DOPL, not the City)
- 1
Rough-In (DOPL-inspected)
Pipe placement and slope verification before walls/slab are closed, performed by a State of Idaho DOPL inspector
- 2
Final (DOPL-inspected)
Fixtures connected, no leaks
Applies to: Residential Mechanical / HVAC Permit
- 1
Rough-In
Ductwork and mechanical equipment rough-in before walls closed
- 2
Final
Equipment operational per approved plans; requires signed Owner/Lessee Consent for Required Permit Inspections
Final inspection only: Demolition Permit
Sources & verification
Verified against official sources. Last reviewed 2026-08-21.
Fee schedules
Applications & forms
Checklists & handouts
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Rathdrum building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Rathdrum building permits
Get alerts for Rathdrum
We'll email you when Rathdrum's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.