How to schedule

Inspections are requested through the building department below.

Address
8047 W Main Street #2, Rathdrum, ID 83858
Phone
(208) 687-7242 (Building Department)
Office hours
Monday through Friday, 8:00 a.m. to 5:00 p.m. (published on the Community Development contact block). Applications are submitted electronically through the BS&A Online portal (bsaonline.com/?uid=2897); the City's own checklists state no hard copy or emailed submittals are accepted.

Inspection sequence

Applies to: Residential Addition or Alteration Permit

  1. 1

    Footing/Foundation

    Required before concrete pour for new footings

  2. 2

    Framing

    Structural framing and connection to the existing structure

  3. 3

    Final

    All work complete per approved plans

Applies to: Residential Single Family Building Permit (New Construction)

  1. 1

    Foundation/Footing

    Before concrete pour, per 2018 IRC and City Design Criteria (24-inch minimum frost depth)

  2. 2

    Framing

    Structural framing per approved plans

  3. 3

    Final

    All work complete per approved plans; requires signed Owner/Lessee Consent for Required Permit Inspections

Applies to: Solar PV Permit (City Building Permit + State-Issued Electrical)

  1. 1

    Electrical Rough-In (DOPL-inspected)

    Grounding and listing of all components verified before the system is covered or energized

  2. 2

    Electrical Final (DOPL-inspected)

    Wiring methods, labeling at the shut-off, working clearances, and system operation verified

  3. 3

    Building Final (City-inspected)

    Roof-mounting and structural attachment verified against approved plans; requires signed Owner/Lessee Consent for Required Permit Inspections

Applies to: Electrical Permit (State-Issued — Idaho DOPL, not the City)

  1. 1

    Rough-In (DOPL-inspected)

    Wiring and box placement before walls are closed, performed by a State of Idaho DOPL inspector

  2. 2

    Final (DOPL-inspected)

    Devices installed, panel labeled, protections verified per NEC

Applies to: EV Charging Station Permit (State-Issued Electrical Permit)

  1. 1

    Electrical Rough-In (if applicable)

    Required only if new circuit wiring is enclosed before final; conduit runs, wire sizing, and grounding verified (DOPL electrical inspection)

  2. 2

    Electrical Final

    EVSE circuit breaker sizing, GFCI protection (where applicable), working clearances, and charger mounting verified against NEC Article 625 (DOPL electrical inspection)

Applies to: Plumbing Permit (State-Issued — Idaho DOPL, not the City)

  1. 1

    Rough-In (DOPL-inspected)

    Pipe placement and slope verification before walls/slab are closed, performed by a State of Idaho DOPL inspector

  2. 2

    Final (DOPL-inspected)

    Fixtures connected, no leaks

Applies to: Residential Mechanical / HVAC Permit

  1. 1

    Rough-In

    Ductwork and mechanical equipment rough-in before walls closed

  2. 2

    Final

    Equipment operational per approved plans; requires signed Owner/Lessee Consent for Required Permit Inspections

Final inspection only: Demolition Permit

Sources & verification

Verified against official sources. Last reviewed 2026-07-04.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Rathdrum building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Rathdrum building permits

Get alerts for Rathdrum

We'll email you when Rathdrum's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.