Inspection sequence, scheduling, and re-inspection fees for building permits in Unincorporated Latah County, Idaho.

Verified 2026-07-04 · Source

How to schedule

Inspections are requested through the building department below.

Address
200 S Almon Street, Ste 102 (Annex Building), Moscow, ID 83843
Phone
(208) 883-7220
Office hours
Monday - Friday, 8 AM - 5 PM. Per the Latah County government contact directory (api.latah.id.us), the department's authoritative current record is: Planning, Building and GIS — Latah County Planning & Building, 200 S Almon Street, Ste 102, Annex Building, Moscow, Idaho 83843; phone (208) 883-7220; Monday - Friday, 8 am - 5 pm. (A City of Moscow homeowner's-guide directory listing shows an older '522 South Adams Street' address and '(208) 882-8580' phone; the county's own current record uses the Annex Building address with phone (208) 883-7220 only.) The email PB@LatahCountyID.gov is confirmed on the county's own Zoning Placement Permit application form (Application for Zoning Placement, revised 6/5/2026) and Building Permit Application Requirements handout.

Published scheduling rules

  • Schedule inspection through the DOPL electrical inspection request line/portal; Latah County unincorporated is served by a state-assigned electrical inspector, not a county inspector (EV Charger / EVSE Permit)

Inspection sequence

Applies to: Commercial Building Permit

  1. 1

    Foundation/Footing

    Before concrete pour, per the same requirements as any other structure under the adopted IBC/IRC.

  2. 2

    Framing

    After framing, sheathing, and MEP rough-in; will not be scheduled until electrical and plumbing permit numbers (issued by Idaho DOPL) have been submitted to the county.

  3. 3

    Final / Certificate of Occupancy

    Final inspection required before occupancy. No commercial-specific inspection sequence (e.g., a distinct fire-marshal sign-off inspection) is documented in any county source reviewed — the county's own materials list only the same general inspection framework used for all structures.

Applies to: Residential/General Building Permit

  1. 1

    Foundation/Footing

    Before concrete pour; footings must be placed 30 in. below grade on undisturbed soil per the county's Wall Section Detail handout.

  2. 2

    Framing

    After framing, sheathing, and MEP rough-in; will not be scheduled until electrical and plumbing permit numbers (issued by the Idaho Division of Occupational and Professional Licenses (DOPL)) have been submitted to the county.

  3. 3

    Final / Certificate of Occupancy

    Final inspection required before occupancy; a Temporary Certificate of Occupancy may be issued for partial occupancy before all permitted elements are complete, per Section 7-1-3(D) of the Code of Latah County.

Applies to: Solar PV Permit

  1. 1

    Zoning Inspection (if a Zoning Placement Permit applies)

    Confirms setback and zoning compliance before/after placement, per Section 7-1-3(A)(3)

  2. 2

    State Rough-In / Final Electrical Inspection

    Performed by Idaho DOPL, not the county — verifies wiring, combiners, disconnects, and point of connection

  3. 3

    County Final Inspection

    Confirms mounting/structural work complete per approved plans, where a full Building Permit was required

Applies to: Commercial Tenant Improvement / Alteration Permit

  1. 1

    Rough-In (framing/MEP, if scope-applicable)

    Required if the TI scope involves framing changes or mechanical/electrical/plumbing rough-in work; will not be scheduled until electrical and plumbing permit numbers (issued by Idaho DOPL) have been submitted to the county.

  2. 2

    Final / Certificate of Occupancy

    Final inspection required before occupying the improved space; a new or amended Certificate of Occupancy is required if the change-of-use/occupancy process applies.

Applies to: Manufactured/Modular/Mobile Home Installation Permit

  1. 1

    Installation Inspection

    Required to confirm compliance with the state-approved installation instructions or Idaho Manufactured Home Installation Standard.

  2. 2

    Final / Certificate of Occupancy

    Required under the same standards as any other single-family dwelling before occupancy.

Re-inspection fees

Residential/General Building PermitReinspection Fee · Other Inspections and Fees, Fee Schedule.
$75.00 per hour

Unincorporated Latah County building permits

Get alerts for Unincorporated Latah County

We'll email you when Unincorporated Latah County's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.