Required for new commercial construction, building additions, and shell buildings in Twin Falls, reviewed against the 2018 IBC with Idaho amendments and City of Twin Falls Design Criteria: Commercial. Applied for via the New Commercial Building Permit Application (Application Subtype: New, Addition, or Shell Building), which shares the City's general commercial submittal standards published in the Commercial Development Guide. Commercial multi-family (3+ unit) buildings use a separate, related New Commercial Multi-Family Building Permit Application rather than this one.

Verified 2026-08-02 · Source

When you need this permit

  • Building permit required for any new commercial construction, building addition, or shell building; select the New, Addition, or Shell Building subtype on the New Commercial Building Permit Application
  • Plans reviewed against the 2018 IBC with Idaho amendments and City of Twin Falls Design Criteria: Commercial (Wind Exposure B, minimum 25 psf uniformly distributed roof design load, 24-inch frost depth, 1,500 psf presumed soil bearing pressure, Climate Zone 5B)
  • Required submittal items due at time of application: Completed & Signed Application, Construction Plan Sheets (Sheet Prefix G/Contact-Cover-General Notes, C/Civil, D/Demolition, A/Architectural, E/Electrical, M/Mechanical, P/Plumbing, S/Structural, L/Landscape; PH/Phasing Plan if phasing multiple structures on one lot), Calculations, and Supplemental Information; FP/Fire Protection and I/Site Lighting are preferred standalone sheets
  • Signed Affidavit of Legal Interest required if the property owner is not the applicant; Development Agreement required for any project needing public infrastructure; Wastewater Discharge Survey required for industrial projects only; Sewer Capacity Fee Worksheet required
  • Fire Sprinkler, Fire Alarm, and Elevator plans must be submitted to the State of Idaho for review (not the City of Twin Falls), per IBC Section 105.3 as noted on the application
  • Applications for any proposed work are deemed abandoned after 180 days from the date of filing unless pursued in good faith or a permit has been issued; a written extension of up to 90 additional days may be granted upon a showing of justifiable cause
  • Commercial multi-family (3+ unit) buildings use the separate New Commercial Multi-Family Building Permit Application; each structure on a lot requires its own separate permit and full discipline-specific document set, and combined submittal packages for multiple buildings are not accepted
  • Registered contractor registration number and expiration must be provided; a primary licensed design professional (and, where applicable, a separate structural licensed design professional) must be identified on the application Contractor

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — valuation $1 to $500Per application; same valuation-based table used for residential permits. City of Twin Falls Master City-Wide Fee Schedule (2024), Exhibit B, footnote Building #1
$22.00
Building Permit Fee — valuation $501 to $2,000City of Twin Falls Master City-Wide Fee Schedule (2024)
$22.00 for the first $500, plus $2.75 for each additional $100 or fraction thereof
Building Permit Fee — valuation $2,001 to $25,000City of Twin Falls Master City-Wide Fee Schedule (2024)
$63.00 for the first $2,000, plus $12.50 for each additional $1,000 or fraction thereof
Building Permit Fee — valuation $25,001 to $50,000City of Twin Falls Master City-Wide Fee Schedule (2024)
$352.00 for the first $25,000, plus $9.00 for each additional $1,000 or fraction thereof
Building Permit Fee — valuation $50,001 to $100,000City of Twin Falls Master City-Wide Fee Schedule (2024)
$580.00 for the first $50,000, plus $6.25 for each additional $1,000 or fraction thereof
Building Permit Fee — valuation $100,001 to $500,000City of Twin Falls Master City-Wide Fee Schedule (2024)
$895.00 for the first $100,000, plus $5.00 for each additional $1,000 or fraction thereof
Building Permit Fee — valuation $500,001 to $1,000,000City of Twin Falls Master City-Wide Fee Schedule (2024)
$2,855.00 for the first $500,000, plus $4.25 for each additional $1,000 or fraction thereof
Building Permit Fee — valuation $1,000,001 and upCity of Twin Falls Master City-Wide Fee Schedule (2024)
$4,955.00 for the first $1,000,000, plus $2.75 for each additional $1,000 or fraction thereof
Commercial Plan Review FeeCity of Twin Falls Master City-Wide Fee Schedule (2024); higher than the 30% Residential Plan Review Fee charged on this file's residential entries
65% of the building permit fee
Additional Plan Review FeeCharged for all changes, additions, or revisions requiring review after initial submittal. City of Twin Falls Master City-Wide Fee Schedule (2024)
$50.00
Re-inspection FeeCity of Twin Falls Master City-Wide Fee Schedule (2024)
$50.00
Temporary Certificate of Occupancy application (non-single-family & duplex permits)Per application and extension, non-refundable. City of Twin Falls Master City-Wide Fee Schedule (2024)
$1,200.00
Temporary Certificate of Occupancy retainer (non-single-family & duplex permits)Refundable retainer. City of Twin Falls Master City-Wide Fee Schedule (2024)
1.50% of project value ($5,000 minimum; $75,000 maximum)

Review timeline

Plan reviewTwin Falls’s published plan-review target
25–25 business days

How long did your Commercial Building Permit (New Construction / Addition / Shell Building) permit actually take in Twin Falls?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Footing/Foundation

    All re-bar tied in place and hold-down anchors installed properly at time of inspection, per City of Twin Falls commercial inspection checklist

  2. 2

    Shear

    All hold-downs installed per approved plans and manufacturer installation guide; fasteners not overdriven, correct fastener type and spacing used

  3. 3

    Framing

    Accessibility standards (ICC A117.1-2009) verified, required load paths to footing installed for all load points, stair rise/tread dimensions and truss uplift protection confirmed

  4. 4

    Fire (Alarm / Sprinkler / Kitchen Hood, as applicable)

    Fire alarm and fire sprinkler plans must be pre-approved by the State Fire Marshal; underground fire sprinkler line must be inspected by the Twin Falls Fire Department before covering; kitchen hood suppression system trip test required where applicable. Call the Fire Marshal at (208) 735-7232

  5. 5

    Engineering (Storm Water / Site / Right-of-Way / Flood Plain)

    Required before Certificate of Occupancy: 3-phase storm water facility inspection (excavation, pipe placement, completed cover), parking lot/ADA site inspections, right-of-way (driveway approach, curb/gutter/sidewalk ADA compliance) inspections, and flood plain elevation verification where applicable. Call the Engineering inspection line at (208) 735-3446, before 7:30 AM for same-day service

  6. 6

    Planning & Zoning (Landscaping / Trash Enclosures)

    Landscaping and trash enclosures (including the enclosure's front gate) must be complete before a final inspection/TCO can be issued; landscaping completion may be deferred to the end of the current planting season (typically not more than 2-3 months) by agreement with the Planner at (208) 735-7270

  7. 7

    Final (Building) / Certificate of Occupancy

    All plumbing, electrical, and mechanical final inspections must pass before requesting the building final; landings, egress signage, door hardware, and handrails verified; all City departments (Building, Fire, Engineering, Planning & Zoning) must sign off before the Building Official signs the Certificate of Occupancy

See the full Twin Falls inspection guide — scheduling & re-inspection fees →

Tips

  • New complete commercial buildings, additions, and shell buildings are published at 5 weeks to first review (subject to workload/complexity), per the City of Twin Falls Building Applications & Forms plan review timelines table.
  • Fire Sprinkler, Fire Alarm, and Elevator plans are reviewed by the State of Idaho, not the City of Twin Falls — submit those through the state process separately, even though the City issues the building permit itself.
  • The Commercial Plan Review Fee is 65% of the building permit fee, versus 30% for residential permits documented elsewhere in this file, per the Master City-Wide Fee Schedule.
  • Commercial multi-family (3+ unit) buildings use a separate New Commercial Multi-Family Building Permit Application; each structure needs its own full document set and combined packages for multiple buildings are not accepted.
  • Initial plan review fees are assessed and invoiced at intake (after the application package is confirmed complete); final fees are invoiced once all departments have completed and passed their reviews, and approved plans are released on the portal only after those fees are paid, per the Commercial Development Guide's General Permitting Process.
  • All documents must be submitted as searchable, unlocked, vector-only PDFs (no scanned/raster content) with properly labeled sheet bookmarks; non-compliant electronic submittals are rejected per the Commercial Development Guide's Electronic Submittal Format Requirements.

Frequently asked questions

Twin Falls requires a commercial building permit (new construction / addition / shell building) for: Building permit required for any new commercial construction, building addition, or shell building; select the New, Addition, or Shell Building subtype on the New Commercial Building Permit Application; Plans reviewed against the 2018 IBC with Idaho amendments and City of Twin Falls Design Criteria: Commercial (Wind Exposure B, minimum 25 psf uniformly distributed roof design load, 24-inch frost depth, 1,500 psf presumed soil bearing pressure, Climate Zone 5B); Required submittal items due at time of application: Completed & Signed Application, Construction Plan Sheets (Sheet Prefix G/Contact-Cover-General Notes, C/Civil, D/Demolition, A/Architectural, E/Electrical, M/Mechanical, P/Plumbing, S/Structural, L/Landscape; PH/Phasing Plan if phasing multiple structures on one lot), Calculations, and Supplemental Information; FP/Fire Protection and I/Site Lighting are preferred standalone sheets; Signed Affidavit of Legal Interest required if the property owner is not the applicant; Development Agreement required for any project needing public infrastructure; Wastewater Discharge Survey required for industrial projects only; Sewer Capacity Fee Worksheet required; Fire Sprinkler, Fire Alarm, and Elevator plans must be submitted to the State of Idaho for review (not the City of Twin Falls), per IBC Section 105.3 as noted on the application; Applications for any proposed work are deemed abandoned after 180 days from the date of filing unless pursued in good faith or a permit has been issued; a written extension of up to 90 additional days may be granted upon a showing of justifiable cause; Commercial multi-family (3+ unit) buildings use the separate New Commercial Multi-Family Building Permit Application; each structure on a lot requires its own separate permit and full discipline-specific document set, and combined submittal packages for multiple buildings are not accepted; Registered contractor registration number and expiration must be provided; a primary licensed design professional (and, where applicable, a separate structural licensed design professional) must be identified on the application. If your project isn't listed, confirm with City of Twin Falls Building Safety Department at (208) 735-7238 before starting work.

In Twin Falls, the published Building Permit Fee — valuation $1 to $500 is: $22.00. Additional published fees: Building Permit Fee — valuation $501 to $2,000 — $22.00 for the first $500, plus $2.75 for each additional $100 or fraction thereof; Building Permit Fee — valuation $2,001 to $25,000 — $63.00 for the first $2,000, plus $12.50 for each additional $1,000 or fraction thereof; Building Permit Fee — valuation $25,001 to $50,000 — $352.00 for the first $25,000, plus $9.00 for each additional $1,000 or fraction thereof; Building Permit Fee — valuation $50,001 to $100,000 — $580.00 for the first $50,000, plus $6.25 for each additional $1,000 or fraction thereof; Building Permit Fee — valuation $100,001 to $500,000 — $895.00 for the first $100,000, plus $5.00 for each additional $1,000 or fraction thereof; Building Permit Fee — valuation $500,001 to $1,000,000 — $2,855.00 for the first $500,000, plus $4.25 for each additional $1,000 or fraction thereof; Building Permit Fee — valuation $1,000,001 and up — $4,955.00 for the first $1,000,000, plus $2.75 for each additional $1,000 or fraction thereof; Commercial Plan Review Fee — 65% of the building permit fee; Additional Plan Review Fee — $50.00; Re-inspection Fee — $50.00; Temporary Certificate of Occupancy application (non-single-family & duplex permits) — $1,200.00; Temporary Certificate of Occupancy retainer (non-single-family & duplex permits) — 1.50% of project value ($5,000 minimum; $75,000 maximum). These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

New complete commercial buildings and additions are published at 5 weeks to first review, subject to current workload and project complexity. This is the time to first review comments, not a guarantee of total time to permit issuance, since that also depends on revision cycles. Source: City of Twin Falls Building Applications & Forms page (Commercial plan review timelines table).

You'll need: New Commercial Building Permit Application; Construction Plan Sheets; Calculations; Supplemental Information. Depending on your project, Twin Falls may also ask for: Commercial Development Guide. See the required-documents checklist on this page for details on each.

Twin Falls requires 7 inspection(s) for a commercial building permit (new construction / addition / shell building), in order: Footing/Foundation, Shear, Framing, Fire (Alarm / Sprinkler / Kitchen Hood, as applicable), Engineering (Storm Water / Site / Right-of-Way / Flood Plain), Planning & Zoning (Landscaping / Trash Enclosures), Final (Building) / Certificate of Occupancy. Schedule each through City of Twin Falls Building Safety Department ((208) 735-7238).

Apply through City of Twin Falls Building Safety Department at 203 Main Avenue East, 2nd Floor of City Hall, Twin Falls, ID 83301 (P.O. Box 1907, Twin Falls, ID 83303-1907). Phone: (208) 735-7238, email: bsdpermits@tfid.org. Office hours: Building Safety Department, 2nd Floor of City Hall, 203 Main Avenue East, Twin Falls, ID 83301. Dedicated inspection request lines: Building Inspection (208) 735-7333, Plumbing Inspection (208) 735-7299, Mechanical Inspection (208) 735-7289, Electrical Inspection (208) 735-7235.. Official information: https://www.tfid.org/141/Building-Safety-Department.

Twin Falls, Idaho has adopted: Idaho Building Code Act (Idaho Code Title 39, Chapter 41) makes building code standards a matter of statewide concern; local governments that issue building permits and perform code enforcement must adopt the International Building Code and Idaho Residential Code (Parts I-III and IX) and the Idaho Energy Conservation Code as amended by the Idaho Building Code Board through negotiated rulemaking, and may not adopt subsequent IRC/IECC residential provisions not yet adopted by the Board. Source: Idaho Legislature, Idaho Code Title 39 Chapter 41 (39-4116, Local Government Adoption and Enforcement of Building Codes), https://legislature.idaho.gov/statutesrules/idstat/title39/t39ch41/; 2018 International Building Code (IBC), including accessibility appendices, adopted and incorporated by reference statewide with Idaho amendments; locally administered and enforced by the City of Twin Falls Building Safety Department for commercial construction within city limits. Source: City of Twin Falls Design Criteria: Commercial page and Idaho Building Code Act (Title 39 Ch. 41); 2018 International Residential Code (IRC), Parts I-VI and IX, Appendices A, B and G, with Idaho State amendments, adopted and locally administered by the City of Twin Falls for one- and two-family dwellings and townhouses within city limits. Source: City of Twin Falls Design Criteria: Residential page; 2018 International Energy Conservation Code (IECC), with Idaho State amendments, locally administered by the City of Twin Falls for residential construction. Source: City of Twin Falls Design Criteria: Residential page; 2023 National Electrical Code (NEC), per Idaho Rules and Amendments, locally administered and inspected by the City of Twin Falls Building Safety Department (dedicated Electrical Inspection line). Source: City of Twin Falls Design Criteria: Residential page and Inspections page; 2017 Idaho State Plumbing Code, locally administered and inspected by the City of Twin Falls Building Safety Department (dedicated Plumbing Inspection line). Source: City of Twin Falls Design Criteria: Residential page; City of Twin Falls has assumed local jurisdiction for issuing and inspecting building, electrical, plumbing, and mechanical permits within city limits (dedicated Building, Plumbing, Mechanical, and Electrical inspection phone lines are all City of Twin Falls Building Safety Department lines). The Idaho Division of Occupational and Professional Licenses (DOPL) separately registers/licenses electrical, plumbing, and HVAC contractors statewide (a distinct function from the City's permit issuance and inspection authority); DOPL's own Permits and Inspections program applies only in jurisdictions that have NOT assumed local authority, and DOPL confirms permit/inspection jurisdiction 'varies widely' by city/county assumption of authority. Source: DOPL Permits and Inspections page, https://dopl.idaho.gov/plb/plb-permits-and-inspections/, cross-checked against City of Twin Falls Inspections page listing City-run Building/Plumbing/Mechanical/Electrical inspection lines. Local amendments apply — see the Twin Falls overview page for the full list.

No. Fire Sprinkler, Fire Alarm, and Elevator plans must be submitted to the State of Idaho for review, separate from the City of Twin Falls building permit process, per IBC Section 105.3 as noted on the New Commercial Building Permit Application.

Sources & verification

Verified against official sources. Last reviewed 2026-08-02.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Twin Falls building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Twin Falls.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.