How to schedule
Inspections are requested through the building department below.
- Address
- 91 East Central Avenue, Belgrade, MT 59714
- Phone
- (406) 388-3564
- Office hours
- Community & Economic Development public counter, 91 E. Central Ave., Monday-Friday 9:00 AM - 3:00 PM (Permits and Licensing Division: 406-388-3560). Building Department general line: 406-388-3760. Chief Building Official Lucas Sobeck: 406-388-3564.
- Website
- Official site
Published scheduling rules
- Inspections must be scheduled by phone (406-388-3560) or email (mjohnson@belgrademt.gov) only, by 3:00 PM for next-day service; inspectors will not pre-schedule future inspections. (Residential Building Permit (New Construction, ADU, Addition, Remodel))
- Inspections must be scheduled by phone (406-388-3560) or email (mjohnson@belgrademt.gov) only, with a 3:00 PM cutoff for next-day service; inspectors do not pre-schedule future inspections, and photographs are never accepted in lieu of a re-inspection. (General)
Inspection sequence
Applies to: Commercial Building Permit & Fire Plan Review
- 1
Concrete (Footings, Foundation Walls, Slabs, Columns, CMU, Elevator Shaft)
Before concrete pour — includes elevator shaft footings and walls for commercial projects
- 2
Building (Shear Walls, Rough Framing, Roof Dry-In, Insulation, Suspended Ceiling Grid, Above-Ceiling MEPF, Anchoring)
Structural and above-ceiling mechanical/electrical/plumbing/fire rough-in
- 3
Fire (Fire Walls, Draft Stopping, Penetrations, Alarms/Detectors, Sprinkler Piping/Heads, Fire Riser Flow Test)
Fire-rated construction and fire suppression/detection systems, now inspected directly by the City's Building Department
- 4
Swimming Pool (if applicable): Pool Structure, Bonding/Grounding, Equipment Room, Lighting Wiring, Pool Plumbing, Main Drain Grate
For commercial pools — Belgrade is DLI-certified for swimming pool (SP) permitting
- 5
Final (Building, Plumbing, Electrical, Mechanical, Fire)
All systems complete and signed off before Certificate of Occupancy is issued
Applies to: Residential Building Permit (New Construction, ADU, Addition, Remodel)
- 1
Concrete (Footings, Foundation Walls, Damp Proofing, Slabs, CMU)
Before concrete pour — footings, foundation walls, damp proofing, structural slabs, structural CMU
- 2
Building (Shear Walls, Rough Framing, Roof Dry-In, Insulation, Sheet Rock Screws)
Structural framing, shear walls, roof dry-in, insulation, and sheet rock screw pattern
- 3
Plumbing, Electrical, Mechanical Rough-In
Underground/building waste/vent/water piping; temporary meter pole and building electrical rough-in; ductwork, exhaust fans, building gas lines, and gas meter bar
- 4
Final (Building, Plumbing, Electrical, Mechanical)
All systems complete; Air Test (blower door) results and Energy Sticker submitted before occupancy is granted
Applies to: Plumbing Permit
- 1
Underground Piping
Before concrete pour or backfill — verify pipe slope, materials, and cleanouts
- 2
Building Waste, Vent, and Water Lines Piping
Rough-in inspection after pipes installed, before walls closed
- 3
Plumbing Final
All fixtures connected, water heater and expansion tank verified, cleanouts exposed, no leaks
Applies to: Change of Use / Change of Occupancy Permit
- 1
Final Occupancy Inspection
Building Department verification that life-safety, egress, and use-specific code requirements for the new occupancy classification are met before a Certificate of Occupancy is issued
- 2
Site Improvements Verification (Public Works)
Public Works confirms required site improvements (utilities, drainage, parking, ADA access, etc.) are complete; required before the City issues a Certificate of Occupancy, per the City's Master Fee Schedule
Applies to: Electrical Permit
- 1
Rough-In (Temporary Meter Pole, Building Rough-In, Early Permanent Service)
Wiring, box placement, and service connections before walls are closed
- 2
Electrical Final
Devices installed, panel labeled, protections verified per 2020 NEC
Applies to: Fire Sprinkler & Fire Alarm Permit
- 1
Required Inspections
CVFD-conducted inspection(s) during installation; billed as part of the flat or hourly system fee ('plan review, required inspections, and acceptance testing') rather than itemized as separate named stages on CVFD's published fee schedule
- 2
Final Acceptance Testing
Final acceptance test of the completed sprinkler or alarm system, verified by Central Valley Fire District before the system is approved for service; a failed test triggers a $100 re-inspection fee
Applies to: Mechanical / HVAC Permit
- 1
Rough-In (Ductwork, Exhaust Fans, Building Gas Lines, Gas Meter Bar)
Ductwork and mechanical equipment rough-in before walls closed; gas piping verified before concealment
- 2
Mechanical Final
Equipment operational; exhaust vents, combustion air, and clearances verified
Applies to: Solar Photovoltaic (PV) Permit
- 1
Electrical Rough-In
Conduit runs, wire sizing, neutral-ground bonding, and disconnect placement before energizing
- 2
Electrical Final
Panel mounting, racking attachment, roof penetration sealing, production meter, and interconnection point verified
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-03.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Belgrade building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Belgrade building permits
Get alerts for Belgrade
We'll email you when Belgrade's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.