Skip to main content
PermitBase

Belgrade building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Belgrade, Montana.

Verified 2026-07-03 · Source

How to schedule

Inspections are requested through the building department below.

Address
91 East Central Avenue, Belgrade, MT 59714
Phone
(406) 388-3564
Office hours
Community & Economic Development public counter, 91 E. Central Ave., Monday-Friday 9:00 AM - 3:00 PM (Permits and Licensing Division: 406-388-3560). Building Department general line: 406-388-3760. Chief Building Official Lucas Sobeck: 406-388-3564.

Published scheduling rules

  • Inspections must be scheduled by phone (406-388-3560) or email (mjohnson@belgrademt.gov) only, by 3:00 PM for next-day service; inspectors will not pre-schedule future inspections. (Residential Building Permit (New Construction, ADU, Addition, Remodel))
  • Inspections must be scheduled by phone (406-388-3560) or email (mjohnson@belgrademt.gov) only, with a 3:00 PM cutoff for next-day service; inspectors do not pre-schedule future inspections, and photographs are never accepted in lieu of a re-inspection. (General)

Inspection sequence

Applies to: Commercial Building Permit & Fire Plan Review

  1. 1

    Concrete (Footings, Foundation Walls, Slabs, Columns, CMU, Elevator Shaft)

    Before concrete pour — includes elevator shaft footings and walls for commercial projects

  2. 2

    Building (Shear Walls, Rough Framing, Roof Dry-In, Insulation, Suspended Ceiling Grid, Above-Ceiling MEPF, Anchoring)

    Structural and above-ceiling mechanical/electrical/plumbing/fire rough-in

  3. 3

    Fire (Fire Walls, Draft Stopping, Penetrations, Alarms/Detectors, Sprinkler Piping/Heads, Fire Riser Flow Test)

    Fire-rated construction and fire suppression/detection systems, now inspected directly by the City's Building Department

  4. 4

    Swimming Pool (if applicable): Pool Structure, Bonding/Grounding, Equipment Room, Lighting Wiring, Pool Plumbing, Main Drain Grate

    For commercial pools — Belgrade is DLI-certified for swimming pool (SP) permitting

  5. 5

    Final (Building, Plumbing, Electrical, Mechanical, Fire)

    All systems complete and signed off before Certificate of Occupancy is issued

Applies to: Residential Building Permit (New Construction, ADU, Addition, Remodel)

  1. 1

    Concrete (Footings, Foundation Walls, Damp Proofing, Slabs, CMU)

    Before concrete pour — footings, foundation walls, damp proofing, structural slabs, structural CMU

  2. 2

    Building (Shear Walls, Rough Framing, Roof Dry-In, Insulation, Sheet Rock Screws)

    Structural framing, shear walls, roof dry-in, insulation, and sheet rock screw pattern

  3. 3

    Plumbing, Electrical, Mechanical Rough-In

    Underground/building waste/vent/water piping; temporary meter pole and building electrical rough-in; ductwork, exhaust fans, building gas lines, and gas meter bar

  4. 4

    Final (Building, Plumbing, Electrical, Mechanical)

    All systems complete; Air Test (blower door) results and Energy Sticker submitted before occupancy is granted

Applies to: Plumbing Permit

  1. 1

    Underground Piping

    Before concrete pour or backfill — verify pipe slope, materials, and cleanouts

  2. 2

    Building Waste, Vent, and Water Lines Piping

    Rough-in inspection after pipes installed, before walls closed

  3. 3

    Plumbing Final

    All fixtures connected, water heater and expansion tank verified, cleanouts exposed, no leaks

Applies to: Change of Use / Change of Occupancy Permit

  1. 1

    Final Occupancy Inspection

    Building Department verification that life-safety, egress, and use-specific code requirements for the new occupancy classification are met before a Certificate of Occupancy is issued

  2. 2

    Site Improvements Verification (Public Works)

    Public Works confirms required site improvements (utilities, drainage, parking, ADA access, etc.) are complete; required before the City issues a Certificate of Occupancy, per the City's Master Fee Schedule

Applies to: Electrical Permit

  1. 1

    Rough-In (Temporary Meter Pole, Building Rough-In, Early Permanent Service)

    Wiring, box placement, and service connections before walls are closed

  2. 2

    Electrical Final

    Devices installed, panel labeled, protections verified per 2020 NEC

Applies to: Fire Sprinkler & Fire Alarm Permit

  1. 1

    Required Inspections

    CVFD-conducted inspection(s) during installation; billed as part of the flat or hourly system fee ('plan review, required inspections, and acceptance testing') rather than itemized as separate named stages on CVFD's published fee schedule

  2. 2

    Final Acceptance Testing

    Final acceptance test of the completed sprinkler or alarm system, verified by Central Valley Fire District before the system is approved for service; a failed test triggers a $100 re-inspection fee

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In (Ductwork, Exhaust Fans, Building Gas Lines, Gas Meter Bar)

    Ductwork and mechanical equipment rough-in before walls closed; gas piping verified before concealment

  2. 2

    Mechanical Final

    Equipment operational; exhaust vents, combustion air, and clearances verified

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    Electrical Rough-In

    Conduit runs, wire sizing, neutral-ground bonding, and disconnect placement before energizing

  2. 2

    Electrical Final

    Panel mounting, racking attachment, roof penetration sealing, production meter, and interconnection point verified

Re-inspection fees

Fire Sprinkler & Fire Alarm PermitRe-Inspection for Failed Final Inspection/Acceptance Testing · Central Valley Fire District Fee Schedule
$100

Sources & verification

Verified against official sources. Last reviewed 2026-07-03.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Belgrade building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Belgrade building permits

Get alerts for Belgrade

We'll email you when Belgrade's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.