Demolition Permit — Polson, Montana · Requirements sheet
Verified 2026-07-04 · Source: https://www.cityofpolson.com/media/10606
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Demolition Permit in Polson, Montana
Required for demolition of buildings within Polson city limits, following the City's published Guidelines for Demolition. Includes a mandatory EPA federal notification step in addition to the City permit.
Verified 2026-07-04 · Source
When you need this permit
- Submit the City's 1-page Application for Demolition Permit
- Submit a 2-page Federal Notification form to the U.S. EPA; the EPA must receive notification at least ten working days prior to the start of demolition, since federal notification is required for demolition activities in this area
- Projects over 5,000 square feet carry a 30-day completion time limit; larger projects may be granted up to six months with City Council approval, decided on an individual basis
- Projects over 5,000 square feet should post a performance bond (fee decided by City Council)
- All debris and related salvage must be stacked and promptly removed from the demo area within 48 hours
- Signage of hazard must be conspicuously posted around the perimeter of the demolition project
- Fireguards must be on-site when deemed necessary by the Fire Chief
- If requirements are not met, the City may take appropriate corrective action after the permit holder is notified and fails to remedy the problem within 3 days
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
See the full Polson inspection guide — scheduling & re-inspection fees →
Tips
- The EPA federal notification requirement (10 working days advance notice) is separate from and in addition to the City's own Demolition Permit Application — both must be filed.
- Debris and salvage must be removed from the site within 48 hours of demolition, and hazard signage must be posted around the project perimeter for the duration of work.
- For asbestos removal/disposal questions, contact Montana DEQ's Asbestos Control Program (406-444-2690) or the EPA Region VIII Asbestos Enforcement Coordinator (303-312-6126).
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-04.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Polson building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Polson
Demolition Permit in other cities
Compare demolition permit fees across Montana →
Look up this fee in a different city →