Construction Permit — Residential Building (New Construction / Addition / Remodel) — East Helena, Montana · Requirements sheet
Verified 2026-07-03 · Source: https://easthelenamt.us/coeh/planning-zoning-building/
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Construction Permit — Residential Building (New Construction / Addition / Remodel) in East Helena, Montana
Required for new one- and two-family residential construction, additions, remodels, and other structural building work within East Helena city limits, issued by the City of East Helena Department of Building & Safety under its DLI-certified local Building (B) program (2021 IBC/IRC). Must be preceded by an approved Zoning Application. Submitted at City Hall, 306 E. Main Street.
Verified 2026-07-03 · Source
When you need this permit
- Zoning Application must be approved before a Building Permit Application is submitted
- Construction Permit Application (Building & Safety) must be completed with project address, owner/architect/contractor information, description of project, and estimated valuation of work
- Owner-Builder & Worker's Compensation Declaration section must be completed (owner performing work vs. licensed contractor vs. Worker's Compensation Insurance certification) Owner-builderContractor
- For new construction, additions, and remodels: Residential One- and Two-Family Dwellings Plan Submittal Requirements apply — site plan, foundation plan, floor plans, floor framing plan, lateral bracing analysis, building section/framing details, roof framing, exterior elevations, and fireplace details (if applicable) as described in the city's published submittal checklist
- Engineered floor/roof truss data sheets required where applicable; calculations and drawings signed/sealed by a Montana-licensed design professional required for structural elements exceeding IRC Section R301 limits or otherwise non-conforming to the IRC
- Geotechnical report required where expansive, compressible, shifting, or otherwise questionable soil conditions are likely present
- Incomplete submittals are returned to the applicant un-reviewed
- Applicant must pay the plan-review portion of the fee within 30 days of notification that plan review is complete (even if not proceeding to construction), and 100% of the total permit fee before starting work
- Digital plans may be emailed to the Building Official at building@easthelenamt.us
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Footing Inspection
Made when forms and footing steel are in place, prior to any concrete being placed
- 2
Foundation Inspection
Made after forms are erected and foundation steel is in place, prior to any concrete being placed
- 3
Framing Inspection
Made after roof, all framing, sheathing, fireblocking, and bracing are in place and all rough electrical wiring, plumbing, chimneys, vents, and ducting are complete, and before thermal insulation is installed
- 4
Insulation Inspection
Not required for single-family dwellings as a called inspection; required for commercial/multi-family after exterior wall and ceiling insulation is installed and secured, before interior surface covering is applied
- 5
Wallboard Inspection
Made after all wallboard is in place, but before joints and fasteners are taped/finished
- 6
Final Inspection
Made after the building is completed and ready for occupancy and all special conditions required for permit issuance are completed; a completed 'Energy Efficient Components' label (per Sec. 50-60-803, MCA) must be affixed to the interior breaker panel first
See the full East Helena inspection guide — scheduling & re-inspection fees →
Tips
- A Zoning Application must be approved BEFORE the Building Permit Application is submitted — plan for both steps.
- No flat building-permit fee schedule is published; the city calculates fees by valuation formula after the application is submitted. Confirm the current calculation directly with the Department of Building & Safety, (406) 227-5321 / building@easthelenamt.us.
- reviewTimelineDays is encoded from MCA 50-60-106(2)(c): a Montana jurisdiction certified under 50-60-302 (East Helena is certified for Building) must issue the permit or a written notice of plan disapproval within 10 working days of the contractor's submission when the state's single-family-dwelling checklist (devised under 50-60-118) is attached to the plans. East Helena's own site and permit forms do not publish an independent turnaround figure, so this statutory floor is used as the governing timeline rather than an invented number.
- East Helena sits within the federal Superfund Institutional Control Program (ICP) administrative area (former ASARCO smelter site) — coordinate with the LEAP office (Room 201, City Hall, (406) 457-8583) to determine if soil/lead compliance measures apply to your project.
- This permit becomes null and void if work is not commenced within 180 days, or is suspended/abandoned for 180 days after starting; request a progress inspection before 180 days elapses between inspections to keep the permit active.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-03.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the East Helena building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in East Helena
Construction Permit — Residential Building (New Construction / Addition / Remodel) in other cities
Look up this fee in a different city →
Now live
Build your East Helena project checklist
Describe your project once and get every permit, document, and fee it triggers in East Helena — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →