Residential Solar Photovoltaic (PV) Permit — State-Issued Electrical Permit Add-On — East Helena, Montana · Requirements sheet
Verified 2026-07-20 · Source: https://bsd.dli.mt.gov/building-codes-permits/permit-applications/electrical-permits/
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Solar Photovoltaic (PV) Permit — State-Issued Electrical Permit Add-On in East Helena, Montana
Rooftop or ground-mount residential solar photovoltaic installation within East Helena city limits is not a separate stand-alone permit type — it is billed and processed as an Alternative Energy Source add-on to the state-issued Residential Electrical Permit, since East Helena is not DLI-certified for Electrical and all electrical permitting for East Helena addresses is issued directly by the Montana Department of Labor & Industry Building Codes Bureau (Helena) under the 2020 NEC. The Bureau's own Application for Residential Electrical Permit form itemizes 'Alternative Energy Source (solar/wind/hydro)' as a fixed $65 fee added on top of whichever base electrical work-type fee applies (e.g., service upgrade, change of service), and requires the applicant to specify the system type (Micro Inverter/AC Module System or PV String System).
Verified 2026-07-20 · Source
When you need this permit
- Apply using the same statewide Application for Residential Electrical Permit used for all East Helena electrical work, since the state DLI Building Codes Bureau (not the city) issues electrical permits for East Helena addresses
- Select the applicable base work-type fee (e.g., service, change of service, accessory building panel) and add the Alternative Energy Source line item
- Specify system type: Micro Inverter/AC Module System or PV String System
- Application must be signed and dated by the licensed electrical contractor's person in charge; payment must be submitted with the application
- Apply in accordance with Title 50, Chapter 60, Section 604, MCA and ARM 24.301.431
- Governed by the 2020 NEC as statewide-adopted (effective June 11, 2022)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
State electrical inspection
Requested per-hour from the DLI Building Codes Bureau ($60/hr, plus travel), covering PV interconnection, disconnect placement, and wiring per the 2020 NEC
See the full East Helena inspection guide — scheduling & re-inspection fees →
Tips
- There is no separate 'solar permit' form or city process in East Helena — solar PV is a $65 line-item add-on on the same statewide Residential Electrical Permit application used for any other electrical work, filed with the state DLI Building Codes Bureau (not the city), because East Helena holds no local electrical certification.
- Budget the $65 Alternative Energy Source fee ON TOP OF whichever base electrical fee applies to the underlying work (e.g., a new service upgrade tied to the PV installation).
- Mail the application and payment to PO Box 200517, Helena, MT 59620-0517, or apply online at ebiz.mt.gov — not to East Helena City Hall.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the East Helena building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in East Helena
Residential Solar Photovoltaic (PV) Permit — State-Issued Electrical Permit Add-On in other cities
Look up this fee in a different city →
Now live
Build your East Helena project checklist
Describe your project once and get every permit, document, and fee it triggers in East Helena — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.