Residential Building Permit (One- and Two-Family Dwelling — New Construction) in Helena, Montana

Verified

Required for construction of new single-family and two-family (duplex) dwellings within Helena city limits. Reviewed against the 2021 International Residential Code (IRC) as adopted statewide by Montana and enforced locally by the City of Helena Building Division, a DLI-certified building code enforcement program.

Verified 2026-07-02 · Source

From$22.00Building Permit Fee — valuation $0–$500 — see all 9 fees below

When you need this permit

Required documents

Fee schedule

Fee typeAmountNotes
Building Permit Fee — valuation $0–$500$22.00Building Permit Fee Tabulation, Figure 1 (Appendix A), Ordinance 3134 — City of Helena Building Permit Valuation Table
Building Permit Fee — valuation $2,001–$3,000$75.50Building Permit Fee Tabulation, Figure 1 (Appendix A), Ordinance 3134
Building Permit Fee — valuation $9,001–$10,000$163.00Building Permit Fee Tabulation, Figure 1 (Appendix A), Ordinance 3134
Building Permit Fee — valuation $99,001–$100,000$892.50Building Permit Fee Tabulation, Figure 1 (Appendix A), Ordinance 3134
Building Permit Fee — valuation $100,001–$500,000$895.00 for the first $100,000 plus $5.00 for each additional $1,000 or fraction thereof (max example: $500,000 = $2,895.00)Building Permit Fee Tabulation, Figure 1 (Appendix A), Ordinance 3134
Building Permit Fee — valuation $500,001–$1,000,000$2,855.00 for the first $500,000 plus $4.25 for each additional $1,000 or fraction thereof (max example: $1,000,000 = $4,980.00)Building Permit Fee Tabulation, Figure 1 (Appendix A), Ordinance 3134
Building Permit Fee — valuation $1,000,001 and over$4,955.00 for the first $1,000,000 plus $2.75 for each additional $1,000 or fraction thereofBuilding Permit Fee Tabulation, Figure 1 (Appendix A), Ordinance 3134
Plan Review (Plan Check) Fee65% of the calculated Building Permit FeeVerified from the City's own worked example (November 2022 Building Permit Valuation Fee Calculation Example): $2,140.00 building permit fee produced a $1,391.00 plan check fee = 65.00%
Valuation BasisGreater of the applicant's stated construction contract dollar amount, or the square-foot valuation from the ICC Building Valuation Data table as regionally modified by the CityOrdinance 3134, item #25; e.g. for a 2,000 sq ft R-3 (Type VB) home, Helena's Feb-2022 Square Foot Valuation Data table used $150.87/sq ft for finished floor area and $60.43/sq ft for garage/deck (U occupancy)

Review timeline

~1015 business days

Typical estimate — confirm current times with the Helena building department

Inspection process

  1. 1

    Foundation / Footings

    Before concrete pour; footings minimum 42 inches below grade or otherwise frost-protected

  2. 2

    Framing

    After framing complete, before insulation or wall cover; verifies wall bracing per 105 mph wind speed and Seismic Design Category D0

  3. 3

    Insulation / Energy

    Insulation and IECC Climate Zone 6 compliance before drywall

  4. 4

    Final

    Required approved final inspection prior to moving in and occupying the dwelling

Tips

Frequently asked questions

What building code does Helena use for new homes?
The 2021 International Residential Code (IRC), adopted statewide by Montana effective June 11, 2022 and enforced locally by the City of Helena Building Division, which is certified by the Montana DLI Building Codes Program to enforce Building, Plumbing, Electrical, and Mechanical codes within Helena city limits.
How is my building permit fee calculated in Helena?
Per City Ordinance 3134, your fee is based on the GREATER of your stated construction contract value or the City's ICC-based square-foot valuation table, run through the Building Permit Fee Tabulation table (Appendix A). A plan review fee equal to 65% of the building permit fee is added.

Sources & verification

Verified against official sources. Last reviewed 2026-07-02.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Helena building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Other permits in Helena

Residential Building Permit (One- and Two-Family Dwelling — New Construction) in other cities

Compare residential building permit (one- and two-family dwelling — new construction) fees across Montana

Project checklist — coming soon

Describe your project once and get every permit, document, and fee it triggers in Helena — in one checklist. Leave your email and we'll tell you when it's ready.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.