Demolition Permit in Livingston, Montana

Required for demolition of any building within Livingston city limits. Uses the same Building Permit Application form as new construction, with 'Demolition' as a distinct work-type checkbox alongside Residential, Commercial, Sign, and Well.

Verified 2026-07-03 · Source

When you need this permit

  • Building Permit Application must be completed with the 'Demolition' box checked, including project cost, site address, legal description, and property owner information
  • Application must be signed; unsigned applications are not accepted
  • Reviewed and approved by the appropriate City departments prior to permit issuance, per the standard Building Permit Application process
  • No separate, dedicated demolition-specific checklist, bond requirement, or fee line distinct from the standard valuation-based Building Permit Fee was found published by the City of Livingston (unlike Billings, which publishes a distinct Demolition Permit Requirements/Checklist with an explicit $10,000 site bond)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Building Permit Fee — valuation-based (same schedule as new construction)City of Livingston Fee Schedule (Resolution 5181, approved 2/03/2026); no separate demolition fee line or bond amount was found published by the City
$23.50 minimum ($1.00-$500.00 valuation), scaling per the City of Livingston Fee Schedule Building Fees table

Review timeline

Plan reviewLivingston’s published plan-review target
1–10 business days

How long did your Demolition Permit permit actually take in Livingston?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final

    Site verified as cleared/restored per approved demolition permit

See the full Livingston inspection guide — scheduling & re-inspection fees →

Tips

  • Livingston's Building Permit Application form itself lists 'Demolition' as one of five work-type checkboxes (Residential, Commercial, Sign, Well, Demolition) — there is no separate demolition-only application form.
  • Unlike Billings (which requires a $10,000 site bond filed with the City Clerk for demolition), no published bond requirement for demolition was found on the City of Livingston's site; contact the Building Department at (406) 222-0083 to confirm current bonding/insurance requirements before applying.

Frequently asked questions

Livingston requires a demolition permit for: Building Permit Application must be completed with the 'Demolition' box checked, including project cost, site address, legal description, and property owner information; Application must be signed; unsigned applications are not accepted; Reviewed and approved by the appropriate City departments prior to permit issuance, per the standard Building Permit Application process; No separate, dedicated demolition-specific checklist, bond requirement, or fee line distinct from the standard valuation-based Building Permit Fee was found published by the City of Livingston (unlike Billings, which publishes a distinct Demolition Permit Requirements/Checklist with an explicit $10,000 site bond). If your project isn't listed, confirm with City of Livingston Building & Planning Department (Building Division) — city-certified for Building and Swimming Pool permits only; Electrical, Plumbing, and Mechanical/HVAC permits are issued directly by the Montana Department of Labor & Industry Building Codes Bureau at (406) 222-4903 (Building & Planning); (406) 222-0083 (Interim Building Director Brad Haefs, Building Division) before starting work.

In Livingston, the published Building Permit Fee — valuation-based (same schedule as new construction) is: $23.50 minimum ($1.00-$500.00 valuation), scaling per the City of Livingston Fee Schedule Building Fees table. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Livingston's published plan-review target for a demolition permit is 1–10 business days.

You'll need: Building Permit Application (Demolition). See the required-documents checklist on this page for details on each.

Livingston requires 1 inspection(s) for a demolition permit, in order: Final. Schedule each through City of Livingston Building & Planning Department (Building Division) — city-certified for Building and Swimming Pool permits only; Electrical, Plumbing, and Mechanical/HVAC permits are issued directly by the Montana Department of Labor & Industry Building Codes Bureau ((406) 222-4903 (Building & Planning); (406) 222-0083 (Interim Building Director Brad Haefs, Building Division)).

Use the standard City of Livingston Building Permit Application and check the 'Demolition' work-type box. The fee is calculated from the same valuation-based Building Permit Fee schedule used for new construction.

Livingston, Montana has adopted: Montana has a mandatory statewide building code administered by the Montana Department of Labor & Industry (DLI) Building Codes Bureau, amended by the Administrative Rules of Montana (ARM) Title 24, Chapter 301. Cities, counties, and towns may become 'certified' to locally administer permitting and inspection for all or part of the code (building, plumbing, electrical, mechanical, swimming pool, etc.); non-certified areas/trades fall under direct state administration by the DLI Building Codes Bureau. Source: Montana DLI Building Codes Bureau, Certified City, County and Town Programs and Current Codes pages (bsd.dli.mt.gov/building-codes-permits).; Livingston is a Montana DLI-certified jurisdiction for Building (B) and Swimming Pool (SP) ONLY within Livingston city limits; certified building official on file with DLI: Jim Woodhull, (406) 222-0083. Source: Montana DLI Building Codes Bureau, Certified City, County and Town Programs / Current Codes page, bsd.dli.mt.gov/building-codes-permits/certified-government; Livingston is NOT certified for Electrical (E), Plumbing/Mechanical-Gas (P(M/G)), or Mechanical (M). Per the City of Livingston Building Department page: 'The City of Livingston does not issue permits or conduct inspections for electrical, plumbing, or HVAC work. These services are regulated at the state level.' Source: City of Livingston Building Department page, https://www.livingstonmontana.org/buildingplanning/page/building-department; Park County (unincorporated, outside Livingston city limits) does not appear on the Montana DLI Building Codes Bureau's certified local government list at all — unincorporated Park County is entirely state-enforced for Building, Electrical, Plumbing, and Mechanical permitting. Source: Montana DLI Building Codes Bureau, Certified City, County and Town Programs list, bsd.dli.mt.gov/building-codes-permits/certified-government; 2021 International Building Code (IBC) — statewide effective June 11, 2022; per the City of Livingston Building Department, new 2021-edition building codes took effect locally September 23, 2022 ('NEW BUILDING CODES (2021) TAKE EFFECT SEPTEMBER 23, 2022'). Source: City of Livingston Building Department page; 2021 International Residential Code (IRC) — statewide effective June 11, 2022; adopted locally effective September 23, 2022 per City of Livingston Building Department page; 2021 International Existing Building Code (IEBC) — statewide effective June 11, 2022; 2021 International Swimming Pool and Spa Code (ISPSC) — statewide effective June 11, 2022; Livingston is DLI-certified for swimming pool (SP) permitting; 2021 International Mechanical Code (IMC) and 2021 International Fuel Gas Code (IFGC) — statewide editions; state-administered permits in Livingston (city is not Mechanical-certified); 2021 Uniform Plumbing Code (UPC) — statewide edition; state-administered permits in Livingston (city is not Plumbing-certified) — Montana uses the Uniform Plumbing Code, not the International Plumbing Code; 2020 National Electrical Code (NEC) — statewide edition; state-administered permits in Livingston (city is not Electrical-certified); 2021 International Energy Conservation Code (IECC) — statewide effective June 11, 2022; All codes amended by the Administrative Rules of Montana (ARM) Title 24, Chapter 301. Source: Montana DLI Building Codes Bureau, Current Codes page, bsd.dli.mt.gov/building-codes-permits/current-codes; The Livingston Building Department reviews plans and performs inspections using the ICC's IBC and IRC; codes are 're-adopted approximately every three years' per the City of Livingston Building Department page. No Livingston-specific Municode text of Chapter 6 (Uniform Building Code) confirming a distinct local amendment ordinance number could be retrieved (Municode's dynamic content did not resolve via direct fetch or Wayback Machine snapshot); the City's own Building Department page is used as the authoritative statement of adopted-code editions and effective date.. Local amendments apply — see the Livingston overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-03.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Livingston building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.