Livingston building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Livingston, Montana.
Verified 2026-07-03 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 220 E. Park Street, Livingston, MT 59047 (Building Division field office: 330 Bennett Street)
- Phone
- (406) 222-4903 (Building & Planning); (406) 222-0083 (Interim Building Director Brad Haefs, Building Division)
- Office hours
- City Hall, 220 E. Park Street, Livingston, MT 59047
- Website
- Official site
Inspection sequence
Applies to: Accessory Dwelling Unit (ADU)
- 1
Footing/Foundation
Required before concrete pour for detached ADU construction
- 2
Framing
Structural framing verified before walls are closed
- 3
Final
Completed ADU verified against approved plans
Applies to: Residential Addition / Remodel / Alteration Permit
- 1
Footing/Foundation
Required before concrete pour for additions, deck posts, or foundation work
- 2
Framing
Structural framing and connections to the existing structure verified before walls are closed
- 3
Final
Completed work verified against approved plans
Applies to: Residential Building Permit (New Construction)
- 1
Footing/Foundation
Required before concrete pour; verified against the approved foundation plan per the adopted 2021 IBC/IRC. A list of required inspections is provided to the permit holder at issuance per the City's FAQ.
- 2
Framing
Structural framing verified against approved plans before walls are closed
- 3
Final
Completed work verified against approved plans prior to occupancy
Applies to: Electrical Permit (State-Issued)
- 1
Rough-In
Wiring, box placement, and service connections before walls are closed
- 2
Final
Devices installed, panel labeled, protections verified per 2020 NEC
Applies to: Fire Sprinkler & Fire Alarm System Permit
- 1
Rough-In / Underground
Underground and rough-in sprinkler piping or fire alarm wiring verified before concealment, consistent with the NFPA 13/NFPA 72 provisions incorporated by reference into the locally adopted 2021 IBC Chapter 9 (Fire Protection Systems)
- 2
Final Acceptance Test
Final witnessed acceptance test of the installed fire suppression and/or fire alarm system performed by Livingston Fire & Rescue prior to occupancy; billed per the Additional Occupancy Inspection Fees table (Fire Sprinkler Systems $30 + $10/floor; Fire Alarm/Smoke Detector Systems $30 + $10/floor; Standpipe Systems $30/standpipe; Fire Pumps $30/fire pump)
Applies to: Mechanical / HVAC Permit (State-Issued)
- 1
Rough-In
Ductwork and mechanical equipment rough-in before walls closed; gas piping pressure test before concealment
- 2
Final
Equipment operational; combustion air and clearances verified
Applies to: Plumbing Permit (State-Issued, including Water Heater)
- 1
Rough-In
After pipes installed, before walls closed
- 2
Final
All fixtures connected, water heater T&P and expansion tank verified, cleanouts exposed, no leaks
Applies to: Solar Photovoltaic (PV) Permit
- 1
Final (Building)
Panel mounting, racking attachment, and roof penetration sealing verified by the City of Livingston Building Division
- 2
Rough/Final (Electrical)
Conduit runs, wire sizing, disconnect placement, and interconnection point verified by the state Building Codes Bureau
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-03.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Livingston building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Livingston building permits
Get alerts for Livingston
We'll email you when Livingston's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.