Inspection sequence, scheduling, and re-inspection fees for building permits in Livingston, Montana.

Verified 2026-07-03 · Source

How to schedule

Inspections are requested through the building department below.

Address
220 E. Park Street, Livingston, MT 59047 (Building Division field office: 330 Bennett Street)
Phone
(406) 222-4903 (Building & Planning); (406) 222-0083 (Interim Building Director Brad Haefs, Building Division)
Office hours
City Hall, 220 E. Park Street, Livingston, MT 59047

Inspection sequence

Applies to: Accessory Dwelling Unit (ADU)

  1. 1

    Footing/Foundation

    Required before concrete pour for detached ADU construction

  2. 2

    Framing

    Structural framing verified before walls are closed

  3. 3

    Final

    Completed ADU verified against approved plans

Applies to: Residential Addition / Remodel / Alteration Permit

  1. 1

    Footing/Foundation

    Required before concrete pour for additions, deck posts, or foundation work

  2. 2

    Framing

    Structural framing and connections to the existing structure verified before walls are closed

  3. 3

    Final

    Completed work verified against approved plans

Applies to: Residential Building Permit (New Construction)

  1. 1

    Footing/Foundation

    Required before concrete pour; verified against the approved foundation plan per the adopted 2021 IBC/IRC. A list of required inspections is provided to the permit holder at issuance per the City's FAQ.

  2. 2

    Framing

    Structural framing verified against approved plans before walls are closed

  3. 3

    Final

    Completed work verified against approved plans prior to occupancy

Applies to: Electrical Permit (State-Issued)

  1. 1

    Rough-In

    Wiring, box placement, and service connections before walls are closed

  2. 2

    Final

    Devices installed, panel labeled, protections verified per 2020 NEC

Applies to: Fire Sprinkler & Fire Alarm System Permit

  1. 1

    Rough-In / Underground

    Underground and rough-in sprinkler piping or fire alarm wiring verified before concealment, consistent with the NFPA 13/NFPA 72 provisions incorporated by reference into the locally adopted 2021 IBC Chapter 9 (Fire Protection Systems)

  2. 2

    Final Acceptance Test

    Final witnessed acceptance test of the installed fire suppression and/or fire alarm system performed by Livingston Fire & Rescue prior to occupancy; billed per the Additional Occupancy Inspection Fees table (Fire Sprinkler Systems $30 + $10/floor; Fire Alarm/Smoke Detector Systems $30 + $10/floor; Standpipe Systems $30/standpipe; Fire Pumps $30/fire pump)

Applies to: Mechanical / HVAC Permit (State-Issued)

  1. 1

    Rough-In

    Ductwork and mechanical equipment rough-in before walls closed; gas piping pressure test before concealment

  2. 2

    Final

    Equipment operational; combustion air and clearances verified

Applies to: Plumbing Permit (State-Issued, including Water Heater)

  1. 1

    Rough-In

    After pipes installed, before walls closed

  2. 2

    Final

    All fixtures connected, water heater T&P and expansion tank verified, cleanouts exposed, no leaks

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    Final (Building)

    Panel mounting, racking attachment, and roof penetration sealing verified by the City of Livingston Building Division

  2. 2

    Rough/Final (Electrical)

    Conduit runs, wire sizing, disconnect placement, and interconnection point verified by the state Building Codes Bureau

Re-inspection fees

Fire Sprinkler & Fire Alarm System PermitUnsatisfactory re-inspection · City of Livingston Fee Schedule (Resolution 5181, approved 2/03/2026), Fire Inspection Fees -- Violations and Re-inspections table
Double the amount of the initial inspection fee (fourth re-inspection doubles the prior re-inspection fee and is referred to the Code Review Board)

Sources & verification

Verified against official sources. Last reviewed 2026-07-03.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Livingston building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Livingston building permits

Get alerts for Livingston

We'll email you when Livingston's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.