Unincorporated Clark County building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Unincorporated Clark County, Nevada.

Verified 2026-07-16 · Source

How to schedule

Inspections are requested through the building department below.

Address
4701 West Russell Road, Las Vegas, NV 89118
Phone
(702) 455-3000
Office hours
Mon–Thu 7:30 AM – 5:30 PM (closed Fri, Sat, Sun)

Inspection sequence

Applies to: Residential Building Permit (New Construction)

  1. 1

    Foundation / Footings

    Before concrete pour — forms, rebar, anchor bolts, and soil preparation verified per IRC Table R401.4.1

  2. 2

    Underground Plumbing / Slab Rough-In

    Underground piping and under-slab rough-in before concrete pour — pressure test required

  3. 3

    Framing / Structural

    After framing, sheathing, roof, and rough-in trades complete — before insulation or wall cover

  4. 4

    MEP Rough-In

    Electrical, plumbing, and mechanical rough-in before walls are covered — may be combined with framing inspection

  5. 5

    Insulation / Energy

    Insulation and energy compliance items verified before drywall — 2024 IECC compliance

  6. 6

    Final

    All work complete, certificate of occupancy issued — all trades, site grading, address signage, smoke/CO detectors verified

Applies to: Residential Addition / Remodel Permit

  1. 1

    Foundation / Footings

    Before concrete pour for any new footings associated with addition

  2. 2

    Framing / Structural

    After framing complete, before insulation or wall cover

  3. 3

    MEP Rough-In

    Electrical, plumbing, mechanical rough-ins before walls closed

  4. 4

    Insulation / Energy

    Insulation and energy compliance before drywall — 2024 IECC

  5. 5

    Final

    All work complete per approved plans

Applies to: Swimming Pool / Spa Permit

  1. 1

    Pre-Gunite / Steel / Excavation

    Before gunite or shotcrete application — verify steel reinforcement, layout, and dimensions per §22.02.470

  2. 2

    Plumbing Rough-In

    Pool plumbing lines installed, pressure test before backfill

  3. 3

    Electrical Bonding

    Bonding conductors connected to all metal components — verified before plaster or decking

  4. 4

    Barrier / Fencing

    Pool barrier installed and compliant (minimum 48-inch height, self-closing/latching gate) before water is introduced

  5. 5

    Final

    All work complete — pool filled, equipment operational, safety features verified, electrical final

Applies to: Accessory Dwelling Unit (ADU) Permit

  1. 1

    Foundation

    Footings and foundation before concrete pour

  2. 2

    Framing

    Structural framing, egress, and fire separation

  3. 3

    MEP Rough-In

    Mechanical, electrical, plumbing rough-ins before walls closed

  4. 4

    Final

    All work complete, smoke/CO detectors installed, address posted

Applies to: Commercial Tenant Improvement Permit

  1. 1

    Framing / Structural

    Before concealment of structural elements

  2. 2

    MEP Rough-In

    Electrical, plumbing, and mechanical rough-ins before walls are closed

  3. 3

    Above-Ceiling

    All above-ceiling work inspected before tile/ceiling is installed

  4. 4

    Final / Certificate of Occupancy

    All work complete, fire alarm, sprinkler, and exit sign testing completed — Certificate of Occupancy or TCO issued

Applies to: Block Wall / Screen Wall Permit

  1. 1

    Footing / Foundation

    Before concrete pour — trench depth, width, rebar placement verified

  2. 2

    Block / Grout

    At intermediate block heights (for taller walls) — verify rebar placement and grout consistency before filling cells

  3. 3

    Final

    Wall complete — verify height, cap, and any required steel dowels to adjacent structures

Applies to: Fire Sprinkler System Permit (NFPA 13 / NFPA 13R)

  1. 1

    Underground / Mains

    Underground fire sprinkler piping and mains inspected before backfill

  2. 2

    Rough-In / Hydrostatic Test

    Overhead piping rough-in and hydrostatic pressure test before concealment

  3. 3

    Final / Acceptance Test

    Full system flow test, alarm/flow-switch verification, and fire department connection check before system acceptance

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before energizing

  2. 2

    Final — Building / Structural

    Panel mounting, racking attachment, and roof penetration sealing verified

  3. 3

    Final — Electrical

    Electrical connections, inverter installation, and interconnection point verified per 2023 NEC

Applies to: Change of Use / Certificate of Occupancy Permit

  1. 1

    Life-Safety / Final Inspection

    Verifies the space meets code requirements for the proposed occupancy classification — egress, fire separation, occupant load, and accessibility

  2. 2

    Fire Department Final

    Verifies fire and life-safety systems are appropriate to the new occupancy classification, where applicable

Applies to: Electrical Permit

  1. 1

    Rough-In / Service

    After wiring installed and before walls closed — conductor sizing, panel connections, and service entrance verified

  2. 2

    Final

    All devices installed, panel labeled, GFCI/AFCI protection verified per 2023 NEC

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough-In / Service

    New circuit wiring or service/panel work verified before closing walls, if applicable

  2. 2

    Final

    EVSE equipment connection, breaker sizing, and GFCI protection (where required) verified per 2023 NEC

Applies to: Fire Alarm System Permit (NFPA 72)

  1. 1

    Rough-In / Wiring

    Initiating and notification device wiring inspected before concealment

  2. 2

    Final / Acceptance Test

    Functional test of all initiating and notification devices, battery calculations verification, and central-station monitoring connection check

Applies to: Mechanical / HVAC Permit

  1. 1

    Mechanical Rough-In

    Ductwork and equipment rough-in before wall cover — clearances and support verified per UMC

  2. 2

    Final

    Equipment operational, combustion air verified, refrigerant charge complete, thermostat functional

Applies to: Plumbing Permit

  1. 1

    Underground / Rough-In

    Underground plumbing and rough-in before concealment — pressure test required per UPC

  2. 2

    Final

    All fixtures connected, no leaks, proper venting verified per UPC

Applies to: Sign Permit (Sign Design Review)

  1. 1

    Electrical (illuminated signs only)

    Wiring and connections for internally illuminated or electronic message signs, inspected under the associated electrical permit

  2. 2

    Final

    Sign built and located per the approved Sign Design Review/Administrative Sign Design Review plans and construction permit

Final inspection only: Demolition Permit, Re-Roofing Permit

Re-inspection fees

Residential Building Permit (New Construction)Re-inspection Fee · Table 3-I, Clark County Code §22.02.430
$110.00 each
Residential Addition / Remodel PermitRe-inspection Fee · Table 3-I, Clark County Code §22.02.430
$110.00 each
Electrical PermitRe-inspection Fee · Table 3-I, Clark County Code §22.02.430
$110.00 each
Plumbing PermitRe-inspection Fee · Table 3-I, Clark County Code §22.02.430
$110.00 each
Mechanical / HVAC PermitRe-inspection Fee · Table 3-I, Clark County Code §22.02.430
$110.00 each
Re-Roofing PermitRe-inspection Fee · Table 3-I, Clark County Code §22.02.430
$110.00 each
Solar Photovoltaic (PV) PermitRe-inspection Fee · Table 3-I, Clark County Code §22.02.430
$110.00 each
EV Charger / EVSE PermitRe-inspection Fee · Table 3-I, Clark County Code §22.02.430
$110.00 each
Accessory Dwelling Unit (ADU) PermitRe-inspection Fee · Table 3-I, Clark County Code §22.02.430
$110.00 each
Demolition PermitRe-inspection Fee · Table 3-I, Clark County Code §22.02.430
$110.00 each
Commercial Tenant Improvement PermitRe-inspection Fee · Table 3-I, Clark County Code §22.02.430
$110.00 each
Swimming Pool / Spa PermitRe-inspection Fee · Table 3-I, Clark County Code §22.02.430
$110.00 each
Block Wall / Screen Wall PermitRe-inspection Fee · Table 3-I, Clark County Code §22.02.430
$110.00 each

Unincorporated Clark County building permits

Get alerts for Unincorporated Clark County

We'll email you when Unincorporated Clark County's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.