Unincorporated Clark County building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Unincorporated Clark County, Nevada.
Verified 2026-07-16 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 4701 West Russell Road, Las Vegas, NV 89118
- Phone
- (702) 455-3000
- Office hours
- Mon–Thu 7:30 AM – 5:30 PM (closed Fri, Sat, Sun)
- Website
- Official site
Inspection sequence
Applies to: Residential Building Permit (New Construction)
- 1
Foundation / Footings
Before concrete pour — forms, rebar, anchor bolts, and soil preparation verified per IRC Table R401.4.1
- 2
Underground Plumbing / Slab Rough-In
Underground piping and under-slab rough-in before concrete pour — pressure test required
- 3
Framing / Structural
After framing, sheathing, roof, and rough-in trades complete — before insulation or wall cover
- 4
MEP Rough-In
Electrical, plumbing, and mechanical rough-in before walls are covered — may be combined with framing inspection
- 5
Insulation / Energy
Insulation and energy compliance items verified before drywall — 2024 IECC compliance
- 6
Final
All work complete, certificate of occupancy issued — all trades, site grading, address signage, smoke/CO detectors verified
Applies to: Residential Addition / Remodel Permit
- 1
Foundation / Footings
Before concrete pour for any new footings associated with addition
- 2
Framing / Structural
After framing complete, before insulation or wall cover
- 3
MEP Rough-In
Electrical, plumbing, mechanical rough-ins before walls closed
- 4
Insulation / Energy
Insulation and energy compliance before drywall — 2024 IECC
- 5
Final
All work complete per approved plans
Applies to: Swimming Pool / Spa Permit
- 1
Pre-Gunite / Steel / Excavation
Before gunite or shotcrete application — verify steel reinforcement, layout, and dimensions per §22.02.470
- 2
Plumbing Rough-In
Pool plumbing lines installed, pressure test before backfill
- 3
Electrical Bonding
Bonding conductors connected to all metal components — verified before plaster or decking
- 4
Barrier / Fencing
Pool barrier installed and compliant (minimum 48-inch height, self-closing/latching gate) before water is introduced
- 5
Final
All work complete — pool filled, equipment operational, safety features verified, electrical final
Applies to: Accessory Dwelling Unit (ADU) Permit
- 1
Foundation
Footings and foundation before concrete pour
- 2
Framing
Structural framing, egress, and fire separation
- 3
MEP Rough-In
Mechanical, electrical, plumbing rough-ins before walls closed
- 4
Final
All work complete, smoke/CO detectors installed, address posted
Applies to: Commercial Tenant Improvement Permit
- 1
Framing / Structural
Before concealment of structural elements
- 2
MEP Rough-In
Electrical, plumbing, and mechanical rough-ins before walls are closed
- 3
Above-Ceiling
All above-ceiling work inspected before tile/ceiling is installed
- 4
Final / Certificate of Occupancy
All work complete, fire alarm, sprinkler, and exit sign testing completed — Certificate of Occupancy or TCO issued
Applies to: Block Wall / Screen Wall Permit
- 1
Footing / Foundation
Before concrete pour — trench depth, width, rebar placement verified
- 2
Block / Grout
At intermediate block heights (for taller walls) — verify rebar placement and grout consistency before filling cells
- 3
Final
Wall complete — verify height, cap, and any required steel dowels to adjacent structures
Applies to: Fire Sprinkler System Permit (NFPA 13 / NFPA 13R)
- 1
Underground / Mains
Underground fire sprinkler piping and mains inspected before backfill
- 2
Rough-In / Hydrostatic Test
Overhead piping rough-in and hydrostatic pressure test before concealment
- 3
Final / Acceptance Test
Full system flow test, alarm/flow-switch verification, and fire department connection check before system acceptance
Applies to: Solar Photovoltaic (PV) Permit
- 1
Rough Electrical
Conduit runs, wire sizing, and disconnect placement before energizing
- 2
Final — Building / Structural
Panel mounting, racking attachment, and roof penetration sealing verified
- 3
Final — Electrical
Electrical connections, inverter installation, and interconnection point verified per 2023 NEC
Applies to: Change of Use / Certificate of Occupancy Permit
- 1
Life-Safety / Final Inspection
Verifies the space meets code requirements for the proposed occupancy classification — egress, fire separation, occupant load, and accessibility
- 2
Fire Department Final
Verifies fire and life-safety systems are appropriate to the new occupancy classification, where applicable
Applies to: Electrical Permit
- 1
Rough-In / Service
After wiring installed and before walls closed — conductor sizing, panel connections, and service entrance verified
- 2
Final
All devices installed, panel labeled, GFCI/AFCI protection verified per 2023 NEC
Applies to: EV Charger / EVSE Permit
- 1
Rough-In / Service
New circuit wiring or service/panel work verified before closing walls, if applicable
- 2
Final
EVSE equipment connection, breaker sizing, and GFCI protection (where required) verified per 2023 NEC
Applies to: Fire Alarm System Permit (NFPA 72)
- 1
Rough-In / Wiring
Initiating and notification device wiring inspected before concealment
- 2
Final / Acceptance Test
Functional test of all initiating and notification devices, battery calculations verification, and central-station monitoring connection check
Applies to: Mechanical / HVAC Permit
- 1
Mechanical Rough-In
Ductwork and equipment rough-in before wall cover — clearances and support verified per UMC
- 2
Final
Equipment operational, combustion air verified, refrigerant charge complete, thermostat functional
Applies to: Plumbing Permit
- 1
Underground / Rough-In
Underground plumbing and rough-in before concealment — pressure test required per UPC
- 2
Final
All fixtures connected, no leaks, proper venting verified per UPC
Applies to: Sign Permit (Sign Design Review)
- 1
Electrical (illuminated signs only)
Wiring and connections for internally illuminated or electronic message signs, inspected under the associated electrical permit
- 2
Final
Sign built and located per the approved Sign Design Review/Administrative Sign Design Review plans and construction permit
Final inspection only: Demolition Permit, Re-Roofing Permit
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-16.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Clark County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Unincorporated Clark County building permits
Get alerts for Unincorporated Clark County
We'll email you when Unincorporated Clark County's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.