Unincorporated Clark County building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Unincorporated Clark County, Nevada.

Verified 2026-07-16 · Source

How to schedule

Inspections are requested through the building department below.

Address
4701 West Russell Road, Las Vegas, NV 89118
Phone
(702) 455-3000
Office hours
Mon–Thu 7:30 AM – 5:30 PM (closed Fri, Sat, Sun)

Inspection sequence

Applies to: Residential Building Permit (New Construction)

  1. 1

    Foundation / Footings

    Before concrete pour — forms, rebar, anchor bolts, and soil preparation verified per IRC Table R401.4.1

  2. 2

    Underground Plumbing / Slab Rough-In

    Underground piping and under-slab rough-in before concrete pour — pressure test required

  3. 3

    Framing / Structural

    After framing, sheathing, roof, and rough-in trades complete — before insulation or wall cover

  4. 4

    MEP Rough-In

    Electrical, plumbing, and mechanical rough-in before walls are covered — may be combined with framing inspection

  5. 5

    Insulation / Energy

    Insulation and energy compliance items verified before drywall — 2024 IECC compliance

  6. 6

    Final

    All work complete, certificate of occupancy issued — all trades, site grading, address signage, smoke/CO detectors verified

Applies to: Residential Addition / Remodel Permit

  1. 1

    Foundation / Footings

    Before concrete pour for any new footings associated with addition

  2. 2

    Framing / Structural

    After framing complete, before insulation or wall cover

  3. 3

    MEP Rough-In

    Electrical, plumbing, mechanical rough-ins before walls closed

  4. 4

    Insulation / Energy

    Insulation and energy compliance before drywall — 2024 IECC

  5. 5

    Final

    All work complete per approved plans

Applies to: Swimming Pool / Spa Permit

  1. 1

    Pre-Gunite / Steel / Excavation

    Before gunite or shotcrete application — verify steel reinforcement, layout, and dimensions per §22.02.470

  2. 2

    Plumbing Rough-In

    Pool plumbing lines installed, pressure test before backfill

  3. 3

    Electrical Bonding

    Bonding conductors connected to all metal components — verified before plaster or decking

  4. 4

    Barrier / Fencing

    Pool barrier installed and compliant (minimum 48-inch height, self-closing/latching gate) before water is introduced

  5. 5

    Final

    All work complete — pool filled, equipment operational, safety features verified, electrical final

Applies to: Accessory Dwelling Unit (ADU) Permit

  1. 1

    Foundation

    Footings and foundation before concrete pour

  2. 2

    Framing

    Structural framing, egress, and fire separation

  3. 3

    MEP Rough-In

    Mechanical, electrical, plumbing rough-ins before walls closed

  4. 4

    Final

    All work complete, smoke/CO detectors installed, address posted

Applies to: Commercial Tenant Improvement Permit

  1. 1

    Framing / Structural

    Before concealment of structural elements

  2. 2

    MEP Rough-In

    Electrical, plumbing, and mechanical rough-ins before walls are closed

  3. 3

    Above-Ceiling

    All above-ceiling work inspected before tile/ceiling is installed

  4. 4

    Final / Certificate of Occupancy

    All work complete, fire alarm, sprinkler, and exit sign testing completed — Certificate of Occupancy or TCO issued

Applies to: Block Wall / Screen Wall Permit

  1. 1

    Footing / Foundation

    Before concrete pour — trench depth, width, rebar placement verified

  2. 2

    Block / Grout

    At intermediate block heights (for taller walls) — verify rebar placement and grout consistency before filling cells

  3. 3

    Final

    Wall complete — verify height, cap, and any required steel dowels to adjacent structures

Applies to: Fire Sprinkler System Permit (NFPA 13 / NFPA 13R)

  1. 1

    Underground / Mains

    Underground fire sprinkler piping and mains inspected before backfill

  2. 2

    Rough-In / Hydrostatic Test

    Overhead piping rough-in and hydrostatic pressure test before concealment

  3. 3

    Final / Acceptance Test

    Full system flow test, alarm/flow-switch verification, and fire department connection check before system acceptance

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before energizing

  2. 2

    Final — Building / Structural

    Panel mounting, racking attachment, and roof penetration sealing verified

  3. 3

    Final — Electrical

    Electrical connections, inverter installation, and interconnection point verified per 2023 NEC

Applies to: Change of Use / Certificate of Occupancy Permit

  1. 1

    Life-Safety / Final Inspection

    Verifies the space meets code requirements for the proposed occupancy classification — egress, fire separation, occupant load, and accessibility

  2. 2

    Fire Department Final

    Verifies fire and life-safety systems are appropriate to the new occupancy classification, where applicable

Applies to: Electrical Permit

  1. 1

    Rough-In / Service

    After wiring installed and before walls closed — conductor sizing, panel connections, and service entrance verified

  2. 2

    Final

    All devices installed, panel labeled, GFCI/AFCI protection verified per 2023 NEC

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough-In / Service

    New circuit wiring or service/panel work verified before closing walls, if applicable

  2. 2

    Final

    EVSE equipment connection, breaker sizing, and GFCI protection (where required) verified per 2023 NEC

Applies to: Fire Alarm System Permit (NFPA 72)

  1. 1

    Rough-In / Wiring

    Initiating and notification device wiring inspected before concealment

  2. 2

    Final / Acceptance Test

    Functional test of all initiating and notification devices, battery calculations verification, and central-station monitoring connection check

Applies to: Mechanical / HVAC Permit

  1. 1

    Mechanical Rough-In

    Ductwork and equipment rough-in before wall cover — clearances and support verified per UMC

  2. 2

    Final

    Equipment operational, combustion air verified, refrigerant charge complete, thermostat functional

Applies to: Plumbing Permit

  1. 1

    Underground / Rough-In

    Underground plumbing and rough-in before concealment — pressure test required per UPC

  2. 2

    Final

    All fixtures connected, no leaks, proper venting verified per UPC

Applies to: Sign Permit (Sign Design Review)

  1. 1

    Electrical (illuminated signs only)

    Wiring and connections for internally illuminated or electronic message signs, inspected under the associated electrical permit

  2. 2

    Final

    Sign built and located per the approved Sign Design Review/Administrative Sign Design Review plans and construction permit

Final inspection only: Demolition Permit, Re-Roofing Permit

Re-inspection fees

Residential Building Permit (New Construction)Re-inspection Fee · Table 3-I, Clark County Code §22.02.430
$110.00 each
Residential Addition / Remodel PermitRe-inspection Fee · Table 3-I, Clark County Code §22.02.430
$110.00 each
Electrical PermitRe-inspection Fee · Table 3-I, Clark County Code §22.02.430
$110.00 each
Plumbing PermitRe-inspection Fee · Table 3-I, Clark County Code §22.02.430
$110.00 each
Mechanical / HVAC PermitRe-inspection Fee · Table 3-I, Clark County Code §22.02.430
$110.00 each
Re-Roofing PermitRe-inspection Fee · Table 3-I, Clark County Code §22.02.430
$110.00 each
Solar Photovoltaic (PV) PermitRe-inspection Fee · Table 3-I, Clark County Code §22.02.430
$110.00 each
EV Charger / EVSE PermitRe-inspection Fee · Table 3-I, Clark County Code §22.02.430
$110.00 each
Accessory Dwelling Unit (ADU) PermitRe-inspection Fee · Table 3-I, Clark County Code §22.02.430
$110.00 each
Demolition PermitRe-inspection Fee · Table 3-I, Clark County Code §22.02.430
$110.00 each
Commercial Tenant Improvement PermitRe-inspection Fee · Table 3-I, Clark County Code §22.02.430
$110.00 each
Swimming Pool / Spa PermitRe-inspection Fee · Table 3-I, Clark County Code §22.02.430
$110.00 each
Block Wall / Screen Wall PermitRe-inspection Fee · Table 3-I, Clark County Code §22.02.430
$110.00 each

Sources & verification

Verified against official sources. Last reviewed 2026-07-16.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Clark County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Unincorporated Clark County building permits

Get alerts for Unincorporated Clark County

We'll email you when Unincorporated Clark County's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.