Inspection sequence, scheduling, and re-inspection fees for building permits in Fernley, Nevada.

Verified 2026-07-03 · Source

How to schedule

Inspections are requested through the building department below.

Address
595 Silver Lace Blvd, Fernley, NV 89408
Phone
(775) 784-9900
Office hours
Monday-Friday 8:00 a.m.-5:00 p.m.; permit submittal counter closes at 4:00 p.m. daily; closed all observed holidays. Inspection requests must be received by phone (775-784-9829/775-784-9900) by 4:00 p.m. the business day before the requested inspection date.

Published scheduling rules

  • Inspections must be requested by phone by 4:00 p.m. the business day before the desired inspection date. (Residential Building Permit (New Construction / Single- and Two-Family Dwellings))
  • Inspections must be requested by phone by 4:00 p.m. the business day before the desired inspection date; the City does not offer same-day inspection requests. (General)

Inspection sequence

Applies to: Residential Building Permit (New Construction / Single- and Two-Family Dwellings)

  1. 1

    Foundation

    Footing, stem wall, and under-slab inspection required prior to placing concrete

  2. 2

    Underfloor

    Required prior to installing plywood subfloor

  3. 3

    Utilities (Trench)

    All trenches behind electrical and gas meters; testing of new lines

  4. 4

    Roof-Framing

    Required prior to covering the roof

  5. 5

    Shear Nailing

    Wall sheathing nailing including required structural hold-downs

  6. 6

    Stucco/Veneer Lath

    Lath inspection prior to applying stucco or veneer finish

  7. 7

    Rough Frame / Electric / Plumbing / HVAC

    Combined rough inspection including leak tests; building must be weathered-in (roofing and door/window weather protection complete)

  8. 8

    Insulation

    Building insulation, thermal wrap, ductwork leak test, and related energy-code certifications of compliance

  9. 9

    Wallboard / Shower Pan

    Wallboard nailing inspection and shower pan inspection

  10. 10

    Final Utilities

    Heat and permanent power release inspections

  11. 11

    Final / Certificate of Occupancy

    All permitted work complete; Building & Safety Division issues final approval and, if required, a Certificate of Occupancy and utility releases

Applies to: Plumbing Permit

  1. 1

    Underground/Slab

    Before concrete pour — verify pipe slope, materials, and cleanouts

  2. 2

    Rough-In

    After pipes installed, before walls closed; utility trench inspection and new-line testing

  3. 3

    Final

    All fixtures connected, no leaks, final utility release

Applies to: Residential Addition / Remodel / Repair Permit

  1. 1

    Foundation/Footing

    Required before concrete pour for any new footings (addition, deck posts requiring a permit, etc.)

  2. 2

    Rough Frame / Electric / Plumbing / HVAC

    Structural framing, connections to existing structure, and rough utility inspections combined

  3. 3

    Final

    Completed work verified against approved plans; final utility release and Certificate of Occupancy if applicable

Applies to: Sign Building Permit

  1. 1

    Footing

    Required before backfill/concrete placement, to verify footing size, location, materials, reinforcing, and embedded anchoring against the approved footing plan

  2. 2

    Electrical Rough-In

    For illuminated signs only: disconnect location, circuit sizing, and conduit verified before energizing

  3. 3

    Final

    Completed sign verified against approved elevations, height, and location; electrical connections and grounding verified if illuminated

Applies to: Demolition Permit

  1. 1

    Pre-Backfill / Utility Disconnect Verification

    Owner, Public Works, NV Energy, and Southwest Gas sign-off confirming water, sewer, gas, and electrical services are disconnected and capped/de-energized before demolition proceeds

  2. 2

    Final

    Site restoration verified: lot filled and maintained to existing grade, debris removed, drainage provisions in place

Applies to: Electrical Permit (Tag / Service Change / New Installation)

  1. 1

    Rough-In

    Wiring, box placement, and service connections before walls are closed

  2. 2

    Final

    Devices installed, panel labeled, protections verified per 2023 NEC; final utility (permanent power) release

Applies to: EV Charger / Electric Vehicle Charging Station Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement, and any panel/service upgrade verified before energizing

  2. 2

    Final

    Charger mounting, electrical connections, and interconnection point verified per adopted NEC

Applies to: Fence and Retaining Wall Permit

  1. 1

    Footing

    Required for permitted retaining walls before backfill, to verify footing depth and reinforcement

  2. 2

    Final

    Completed fence/wall verified against approved plans

Applies to: Fire Sprinkler & Fire Alarm System Permit (North Lyon County Fire Protection District)

  1. 1

    Underground/Rough-In

    Sprinkler underground supply piping and rough fire-alarm wiring inspected/tested per NFPA 13/25 and NFPA 72 before concealment

  2. 2

    Final Acceptance Test

    Hydrostatic/flow acceptance test of the sprinkler system (NFPA 13) and functional test of the fire alarm system (NFPA 72); a floor and site plan showing hydrant locations, gas/electrical shutoffs, lock box location, annunciator panel, and FDC/PIV location must be provided to NLCFPD at building final (8.5in x 11in, two copies)

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In

    Ductwork and mechanical equipment rough-in before walls closed; gas piping tested (manometer test) before concealment

  2. 2

    Final

    Equipment operational, clearances and combustion air verified, final utility (heat) release

Applies to: Solar Photovoltaic (PV) / EV Charging Station Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before energizing; roof retrofit verification if applicable

  2. 2

    Final

    Panel mounting, racking attachment, roof penetration sealing, electrical connections, inverter, and interconnection point verified per adopted NEC

Re-inspection fees

Electrical Permit (Tag / Service Change / New Installation)Re-Inspection Fee (third or subsequent inspection of same building element, each) · City of Fernley Resolution 20-009, Exhibit A
$207
Plumbing PermitRe-Inspection Fee (third or subsequent inspection of same building element, each) · City of Fernley Resolution 20-009, Exhibit A
$207
Re-Roofing PermitRe-Inspection Fee (third or subsequent inspection of same building element, each) · City of Fernley Resolution 20-009, Exhibit A
$207
Sign Building PermitRe-Inspection Fee (third or subsequent inspection of same building element, each) · City of Fernley Resolution 20-009, Exhibit A
$207

Sources & verification

Verified against official sources. Last reviewed 2026-07-03.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Fernley building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Fernley building permits

Get alerts for Fernley

We'll email you when Fernley's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.