Certificate of Occupancy / Change of Use — Unincorporated Washoe County, Nevada · Requirements sheet
Reviewed 2026-07-22 · Source: https://www.washoecounty.gov/building/Files/Files/Certificate%20of%20Occupancy%20Commercial%20Handout-Final.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Certificate of Occupancy / Change of Use in Unincorporated Washoe County, Nevada
Washoe County requires a Certificate of Occupancy (CO) before any building or structure is used or occupied, and before any change in the existing occupancy classification is made (WCC §100.110.1). There is no standalone 'change of use permit' product — a change of use is processed through the applicable building or commercial tenant-improvement permit that brings the space up to current code, culminating in issuance of a new Certificate of Occupancy. A Temporary Certificate of Occupancy (TCO) is available for up to 90 days.
Reviewed 2026-07-22 · Source
When you need this permit
- No building or structure may be used or occupied, and no change in the existing occupancy classification may be made, until the Building Division issues a Certificate of Occupancy (WCC §100.110.1)
- A change of use (e.g., an office/Business occupancy converting to retail/Mercantile occupancy) triggers upgrade to current codes covering zoning use compatibility, parking, accessibility (IBC/ANSI A117.1), fire alarm/sprinkler (IFC/NEC/IBC), plumbing fixture counts, lighting/HVAC/electrical, and building envelope — processed via the standard commercial building or tenant-improvement permit, not a separate 'change of use' permit
- Final inspection requires all work under the approved permit to be complete (WCC §100.109.3.12) before a CO is issued
- Commercial CO requires sign-off from: Nevada State Office (elevators, boilers/pressure vessels over 200,000 Btu/h), County Road Department, District Health Department (well/septic, food service licensing), Community Development (landscaping, parking striping, zoning), and the Fire Department (fire alarm/sprinkler test, seismic bracing, standpipes, Fire Department Connection)
- Residential CO requires completed life-safety systems (smoke/CO detectors, GFCI/AFCI), a final gas manometer test, blower-door and duct-testing certification, an insulation certificate, and a completed grading/drainage letter
- A Temporary Certificate of Occupancy (TCO) may be issued for up to 90 days (WCC §100.110.3) if incomplete work does not block access or create a hazard, and only OSHA-trained construction/stocking staff — not the general public — may occupy the space under a TCO
- A residential TCO additionally requires a Special Inspection Permit ('Trip Permit') before the Final Certificate of Occupancy can be issued
- A Pre-Development meeting with the Community Services Department is recommended for any change-of-use project before design begins
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Final Building Inspection
All work required by the building permit is completed (WCC §100.109.3.12)
- 2
Other-Agency Sign-Offs
Road, Health (well/septic), Community Development (parking/zoning/landscaping), Fire Department, and Nevada State Office inspections as applicable, verified on the permit card in Accela
- 3
Certificate of Occupancy Issuance
Building Division issues the CO (or TCO, up to 90 days) once all required sign-offs are complete
See the full Unincorporated Washoe County inspection guide — scheduling & re-inspection fees →
Tips
- Washoe County does not have a standalone 'change of use permit' — a change of use is processed through the normal building or commercial tenant-improvement permit for the space, which must bring the space up to current code before a new Certificate of Occupancy is issued.
- Under a Temporary Certificate of Occupancy, no access to the general public is allowed — only OSHA-trained construction or stocking staff may occupy the space, and a TCO cannot exceed 90 days.
- A residential TCO requires an additional Special Inspection Permit ('Trip Permit') before the Final Certificate of Occupancy can be issued.
- Request a Pre-Development meeting with the Community Services Department before designing a change-of-use project — parking, accessibility, and fire sprinkler/alarm upgrades are common triggers that are easy to miss.
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-07-22.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Washoe County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Washoe County
Certificate of Occupancy / Change of Use in other cities
Compare certificate of occupancy / change of use fees across Nevada →
Look up this fee in a different city →
Now live
Build your Unincorporated Washoe County project checklist
Describe your project once and get every permit, document, and fee it triggers in Unincorporated Washoe County — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →