EV Charger Installation Permit in Unincorporated White Pine County, Nevada

Required for installation of Level 2 or DC fast electric vehicle charging equipment on residential or commercial properties in unincorporated White Pine County. EV charging is not a separately defined permit type in the White Pine County Code; it is administered as an electrical permit (circuit/wiring/interconnection) under the county's adopted 2011 NEC, plus a building permit if a new support structure or canopy is added, mirroring the same treatment documented in the solar-pv-permit entry. No dedicated EV-charger fee line item, valuation table, or charging-infrastructure code chapter is published on the county website: the county's Fee Schedule page links only to the County Clerk's NRS Chapter 19 fee schedule (marriage licenses, document copies, candidate filing — unrelated to building/electrical permits), and the Building Permit Procedures page links to the County's shared City of Ely/White Pine County Building Permit Application form. That application form itself has blank 'Total Valuation of Work', 'Building Permit', 'Plan Check', and 'Fuel Surcharge' fields filled in manually per-project by Building Department staff rather than a published fee table — the fee-setting mechanism is genuinely case-by-case and unpublished, not merely undiscovered.

Reviewed 2026-07-20 · Source

When you need this permit

  • Electrical permit required for the charger circuit, wiring, and interconnection, enforced under the 2011 NEC per White Pine County Code §14.12.010, administered under the 2011 Uniform Administrative Code (§14.12.020)
  • Building permit additionally required if a new canopy, carport, or structural mounting component is added, per the county's adopted 2018 IBC/IRC
  • Submit a Building Permit Application (the county's single application form covers electrical work) describing the scope
  • Plot plan may be required showing the charger/structure location relative to the building and property lines if new construction is involved

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Electrical Permit Fee — EV charger circuit/wiringSame gap documented in the electrical-permit entry — White Pine County Code §14.12 (Electrical Code) contains no dollar-figure fee schedule. Contact the Building Department at (775) 289-6500 for current fee information.
Valuation/fee schedule not published on the county website

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger Installation Permit permit actually take in Unincorporated White Pine County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before cover, per the 2011 NEC as adopted

  2. 2

    Final

    Charger installed and electrical connections verified

See the full Unincorporated White Pine County inspection guide — scheduling & re-inspection fees →

Tips

  • White Pine County has no dedicated EV-charger permit category, fee line item, or charging-infrastructure code chapter published — an installation is treated as a standard electrical permit (plus a building permit if a new structure is added), following the county's general, unpublished valuation-based fee approach, the same treatment documented for the solar-pv-permit entry.
  • Because no numeric fee table is published for any permit type in White Pine County, call the Building Department directly at (775) 289-6500 for a project-specific cost estimate before applying.
  • The county enforces the 2011 NEC edition (not a more recent cycle) for the electrical portion of an EV charger installation.

Frequently asked questions

Unincorporated White Pine County requires an ev charger installation permit for: Electrical permit required for the charger circuit, wiring, and interconnection, enforced under the 2011 NEC per White Pine County Code §14.12.010, administered under the 2011 Uniform Administrative Code (§14.12.020); Building permit additionally required if a new canopy, carport, or structural mounting component is added, per the county's adopted 2018 IBC/IRC; Submit a Building Permit Application (the county's single application form covers electrical work) describing the scope; Plot plan may be required showing the charger/structure location relative to the building and property lines if new construction is involved. If your project isn't listed, confirm with White Pine County Building Department at (775) 289-6500 before starting work.

In Unincorporated White Pine County, the published Electrical Permit Fee — EV charger circuit/wiring is: Valuation/fee schedule not published on the county website. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Unincorporated White Pine County does not publish a plan-review timeline for this permit. Contact White Pine County Building Department at (775) 289-6500 for current turnaround.

You'll need: Building Permit Application. See the required-documents checklist on this page for details on each.

Unincorporated White Pine County requires 2 inspection(s) for an ev charger installation permit, in order: Rough Electrical, Final. Schedule each through White Pine County Building Department ((775) 289-6500).

Apply through White Pine County Building Department at 501 Mill Street, Ely, NV 89301. Phone: (775) 289-6500, email: BuildingPlanning@whitepinecountynv.gov. Office hours: Monday–Friday 8:00 AM – 5:00 PM. Official information: https://www.whitepinecounty.net/132/Building.

Unincorporated White Pine County, Nevada has adopted: Nevada is a home-rule state for building codes: there is no single mandatory statewide building-code edition — each city and county adopts and amends its own code. The only genuine statewide floor is the energy code: pursuant to NRS 701.220, the Governor's Office of Energy adopts the most recently published IECC edition on a triennial basis (2024 IECC effective statewide August 18, 2024, with revisions effective March 12, 2025). Always confirm the specific adopted edition for the city or county in question. Source: NRS Chapter 701 and Nevada Governor's Office of Energy, Building Energy Codes program.; 2018 International Building Code (IBC), including all appendices, adopted per White Pine County Code Title 14, Chapter 14.04, Section 14.04.010 (Ord. 527 §1, 2022, tracing back to Ord. 15 §1, 1959). Source: White Pine County Code, amlegal.com.; 2018 International Residential Code (IRC), including Appendix G (Swimming Pools, Spas and Hot Tubs) and Appendix H (Patio Covers), adopted per White Pine County Code §14.06.010 (Ord. 579 §1, 2022: Ord. 418 §1, 2008). Applies to detached one- and two-family dwellings and townhouses up to three stories with separate means of egress. Source: White Pine County Code, amlegal.com.; 2018 International Plumbing Code (IPC), adopted per White Pine County Code §14.08.010 (Ord. 579 §1, 2022: Ord. 242 §1, 1989, tracing back to Ord. 17 §1, 1959). Source: White Pine County Code, amlegal.com.; 2011 National Electrical Code (NEC), enforced pursuant to Nevada Revised Statutes 278.583, adopted per White Pine County Code §14.12.010 and §14.12.020 (Ord. 579 §1, 2022: Ord. 208 §1, 1987), administered via the Uniform Administrative Code (2011 edition) promulgated by the International Conference of Building Officials. Source: White Pine County Code, amlegal.com.; State of Nevada Fire Code — the county adopts the State Fire Marshal's most recently adopted fire code (currently the International Fire Code (IFC), including Appendices B, C, F and H), per White Pine County Code §14.20.010 (Ord. 579 §1, 2022: Ord. 286 §1(part), 1993: Ord. 92 §1(part), 1980). Source: White Pine County Code, amlegal.com.; 1997 Uniform Code for the Abatement of Dangerous Buildings, adopted per White Pine County Code Chapter 14.05. Source: White Pine County Code, amlegal.com.; Permit and plan review fees are governed by White Pine County Code §14.04.080, which states that all such fees 'shall conform to the 1997 Uniform Administrative Code (UAC)'; the county does not publish a standalone dollar-figure valuation table on its website — applicants must contact the Building Department directly at (775) 289-6500 for current fee calculation. Source: White Pine County Code §14.04.080, amlegal.com.. Local amendments apply — see the Unincorporated White Pine County overview page for the full list.

No. EV charging station installations in unincorporated White Pine County are permitted as a standard electrical permit (circuit/wiring/interconnection), plus a building permit if a new structure or canopy is added, under the county's adopted 2011 NEC and 2018 IBC/IRC. There is no dedicated EV-charger permit type, fee schedule line item, or charging-infrastructure code chapter published by the county.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated White Pine County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Unincorporated White Pine County's permit history isn't searchable here yet

This page covers what the permit requires. What we don't have for Unincorporated White Pine County yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.

Your email, and the place — never an address. We only use it to tell you when Unincorporated White Pine County lands. Privacy.