Grading Permit in Sunland Park, New Mexico
VerifiedRequired for clearing/access, pre-final, and final grading on any site in Sunland Park; tiered by acreage. Issued by the Building Inspections Dept. within the Community Development Department using the City's own Grading Permit Application form.
Verified 2026-07-03 · Source
When you need this permit
- Prior to grading, notify the Community Development Department for a pre-inspection at (575) 589-3631
- Complete the Grading Permit Application specifying intended use of site, flood zone, legal description, owner/contractor info, estimated cut/fill (cubic yards), and acreage tier
- Select permit type: Clearing & Access (20% of total fee), Pre-Final Grading (40%), or Final Grading (100%), or Borrow/Waste
- $300,000 minimum combined single-limit liability insurance required for all permits on sites larger than one (1) acre
- A copy of the permit must be kept at the job site at all times
- No grading on weekends or holidays unless authorized in advance by the City Building Inspector (call (575) 589-3631 before 12:00 p.m. for weekend/holiday grading authorization)
- Permits (other than Borrow/Waste) are valid for one year from issuance; extensions must be requested one month prior to expiration, in writing
Required documents
- Required
Grading Permit Application
City of Sunland Park Community Development / Building Inspections Dept. form; requires legal description, cut/fill estimates, acreage tier selection, and liability insurance confirmation for sites over 1 acre
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Clearing and Access Grading Permit — Tier 1 (0-5 acres) | $74 | City of Sunland Park Development Fee Schedule / Grading Permit Application fee table |
| Clearing and Access Grading Permit — Tier 7 (50+ acres) | $162 | City of Sunland Park Development Fee Schedule / Grading Permit Application fee table |
| Pre-Final Grading Permit — Tier 1 (0-5 acres) | $148 | City of Sunland Park Development Fee Schedule / Grading Permit Application fee table |
| Pre-Final Grading Permit — Tier 7 (50+ acres) | $325 | City of Sunland Park Development Fee Schedule / Grading Permit Application fee table |
| Final Grading Permit — Tier 1 (0-5 acres) | $369 | City of Sunland Park Development Fee Schedule / Grading Permit Application fee table |
| Final Grading Permit — Tier 7 (50+ acres) | $812 | City of Sunland Park Development Fee Schedule / Grading Permit Application fee table |
| Grading First/Second Extension | 30% of Net Payment (each) | City of Sunland Park Development Fee Schedule |
| Illegal Grading | Double Fee | City of Sunland Park Development Fee Schedule |
Review timeline
7–10 business days
Sunland Park’s published plan-review target
Inspection process
- 1
Pre-Grading Inspection
Required notification/pre-inspection with Community Development Dept. prior to commencing grading
- 2
Final Grading Inspection
Upon completion of final grading phase
Tips
- Grading permits (except Borrow/Waste) are valid one year with up to two extensions at 30% of net payment each — plan ahead if your project phase will run long.
- Sites over one acre must carry a $300,000 minimum combined single-limit liability insurance policy before the permit will be approved.
- Weekend/holiday grading requires advance authorization from the City Building Inspector — call before noon the business day prior.
Sources & verification
Verified against official sources. Last reviewed 2026-07-03.
- City of Sunland Park Community Development Department — Building Inspections Division — official building department
- Grading Permit Application | City of Sunland Park Community Development Department
- City of Sunland Park Development Fee Schedule (effective July 1, 2024)
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Sunland Park building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Sunland Park
Grading Permit in other cities
Compare grading permit fees across New Mexico →
Project checklist — coming soon
Describe your project once and get every permit, document, and fee it triggers in Sunland Park — in one checklist. Leave your email and we'll tell you when it's ready.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.