Skip to main content
PermitBase

Nibley building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Nibley, Utah.

Verified 2026-08-16 · Source

How to schedule

Inspections are requested through the building department below.

Address
455 W 3200 S, Nibley, UT 84321-6337
Phone
(435) 752-0431
Office hours
Mon–Fri 9:00 AM – 5:00 PM

Inspection sequence

Applies to: Commercial Building Permit

  1. 1

    Building, Electrical, Mechanical & Plumbing (project-specific)

    Per Nibley's official Building Department page: 'Inspections will vary depending on the project. A list of required inspections will be included upon issuance of building permit.'

  2. 2

    Fire Marshal Inspection

    Inferred from the Consolidated Fee Schedule's published 'Fire Marshall Inspection Fee (Rate set by the County)' ($65.00 in the FY2026-27 edition) in the Business Licenses & Fees section; no separate narrative description of when this inspection occurs was found on Nibley's official pages.

  3. 3

    Final / Certificate of Occupancy

    Final inspection prior to Certificate of Occupancy issuance; specific commercial CO process not separately detailed on Nibley's official Building Department page.

Applies to: Commercial Tenant Improvement / Tenant Finish Permit

  1. 1

    Building, Electrical, Mechanical & Plumbing (project-specific)

    Per Nibley's official Building Department page: 'Inspections will vary depending on the project. A list of required inspections will be included upon issuance of building permit.'

  2. 2

    Fire Marshal Inspection

    Inferred from the Consolidated Fee Schedule's published 'Fire Marshall Inspection Fee (Rate set by the County)' ($65.00 in the FY2026-27 edition) in the Business Licenses & Fees section; particularly relevant to tenant finish work affecting occupancy/egress or fire suppression systems.

  3. 3

    Final / Certificate of Occupancy

    Final inspection prior to Certificate of Occupancy or Certificate of Completion for the tenant space; specific commercial TI closeout process not separately detailed on Nibley's official Building Department page.

Applies to: Change of Use / Change of Occupancy Permit

  1. 1

    Building Final / Occupancy Verification

    Where a change of use involves physical alteration, the Building Official verifies occupancy classification as part of the Building Permit / Commercial Tenant Improvement Permit final inspection process (see the commercial-tenant-improvement-permit entry); no separately named Change of Use inspection is published.

  2. 2

    Fire Marshal Inspection

    Inferred from the Consolidated Fee Schedule's published 'Fire Marshall Inspection Fee (Rate set by the County)' ($65.00 in the FY2026-27 edition, up from $45.00) in the Business Licenses & Fees section, applicable when a new business license accompanies the change of use.

Applies to: Residential Building Permit

  1. 1

    Building, Electrical, Mechanical & Plumbing (project-specific)

    Per Nibley's official Building Department page: 'Inspections will vary depending on the project. A list of required inspections will be included upon issuance of building permit.'

  2. 2

    Finished Floor Elevation Certification

    Prior to issuance of a Certificate of Occupancy, final floor and/or crawl space elevations constructed under NCC 17.10.010 must be certified by a licensed Professional Engineer or Surveyor to ensure compliance, per Nibley's official Building Department page.

Applies to: Solar / Solar PV Installation Permit

  1. 1

    Electrical / Rough-In Inspection

    Inspection of PV wiring, disconnects, and interconnection equipment against the adopted 2023 NEC. Required inspections vary by project and are listed upon permit issuance per Nibley's official Building Department page.

  2. 2

    Final Inspection

    Final inspection of the completed solar PV installation prior to permit close-out; specific solar-PV final inspection process not separately detailed on Nibley's official Building Department page.

Re-inspection fees

Commercial Building PermitReinspection Fee · UNCHANGED. FY2026-27 Consolidated Fee Schedule, page 8 (read from render), 'Miscellaneous Items' section, row: 'Reinspection Fee — $50.00.'
$50.00
Commercial Tenant Improvement / Tenant Finish PermitReinspection Fee · UNCHANGED. FY2026-27 Consolidated Fee Schedule, page 8 (read from render), 'Miscellaneous Items' section, row: 'Reinspection Fee — $50.00.'
$50.00
EV Charger / EVSE PermitReinspection Fee · UNCHANGED. FY2026-27 Consolidated Fee Schedule, page 8 (read from render), 'Miscellaneous Items' section, row: 'Reinspection Fee — $50.00.'
$50.00
Solar / Solar PV Installation PermitReinspection Fee · UNCHANGED. FY2026-27 Consolidated Fee Schedule, page 8 (read from render), 'Miscellaneous Items' section, row: 'Reinspection Fee — $50.00.'
$50.00
Fire Sprinkler System Permit
Cache County Fire District inspection fee (county schedule now retrieved; Show full citationCache County Fire District inspection fee (county schedule now retrieved; applicability to a standalone Nibley permit still unconfirmed) · Read from the Cache County Fire District's own Fee Schedule page (cachecounty.gov/fire/cachecounty.org/firefeeschedule.html), heading 'Cache County Fire District — Fee Schedule (Effective 2026)', section 'Inspections & Permits'. IMPORTANT RETRIEVAL NOTE: this schedule is published as a single inline base64-encoded PNG image embedded directly in the page HTML, with no table markup and no linked PDF. Any text-based fetch of the page therefore returns only the words 'Fee Schedule' and no figures — which is exactly what a prior note in this record recorded as evidence that the district published no fee content. That conclusion was wrong. The figures here were obtained by decoding the inline base64 image out of the page HTML and reading the rendered image on 2026-08-16. The prior note in this record recorded these fees as unverifiable on that false basis and additionally discounted a local-newspaper report of county fire construction-permit fees 'differentiated by the presence of a sprinkler system' as describing only a proposed increase; the district's own published schedule now confirms that differentiation is adopted and in force — New Construction without Sprinklers or Fire Alarm $130, with Sprinklers and Fire Alarm $390. Cross-check: the district's $65 New Business License Inspection exactly matches the $65.00 'Fire Marshall Inspection Fee (Rate set by the County)' that Nibley added to its FY2026-27 schedule, which corroborates that Nibley passes county fire rates through at face value. WHAT IS STILL NOT ESTABLISHED, and why this permit type stays partial: neither Nibley nor the district publishes anything stating that a standalone sprinkler installation in Nibley is routed through the district's New Construction inspection fee, or which of the two tiers would apply to sprinkler-only work on an existing building. These amounts are recorded as the county's published rates, not as a determination that they attach to this permit.
New Construction (without Sprinklers or Fire Alarm) $130; New Construction (with Sprinklers and Fire Alarm) $390; New Business License Inspection $65; Cooking Hood Inspection $65; First Re-inspection $65; Second Re-inspection $100; unlisted services $65.00/hour (1-hour minimum, quarter-hour increments thereafter, 1.5× after hours/weekends/county holidays)
Fire Alarm System Permit
Cache County Fire District inspection fee (county schedule now retrieved; Show full citationCache County Fire District inspection fee (county schedule now retrieved; applicability to a standalone Nibley permit still unconfirmed) · Read from the Cache County Fire District's own Fee Schedule page (cachecounty.gov/fire/cachecounty.org/firefeeschedule.html), heading 'Cache County Fire District — Fee Schedule (Effective 2026)', section 'Inspections & Permits'. IMPORTANT RETRIEVAL NOTE: this schedule is published as a single inline base64-encoded PNG image embedded directly in the page HTML, with no table markup and no linked PDF. Any text-based fetch of the page therefore returns only the words 'Fee Schedule' and no figures — which is exactly what a prior note in this record recorded as evidence that the district published no fee content. That conclusion was wrong. The figures here were obtained by decoding the inline base64 image out of the page HTML and reading the rendered image on 2026-08-16. The prior note in this record recorded these fees as unverifiable on that false basis and additionally discounted a local-newspaper report of county fire construction-permit fees 'differentiated by the presence of a alarm system' as describing only a proposed increase; the district's own published schedule now confirms that differentiation is adopted and in force — New Construction without Sprinklers or Fire Alarm $130, with Sprinklers and Fire Alarm $390. Cross-check: the district's $65 New Business License Inspection exactly matches the $65.00 'Fire Marshall Inspection Fee (Rate set by the County)' that Nibley added to its FY2026-27 schedule, which corroborates that Nibley passes county fire rates through at face value. WHAT IS STILL NOT ESTABLISHED, and why this permit type stays partial: neither Nibley nor the district publishes anything stating that a standalone alarm installation in Nibley is routed through the district's New Construction inspection fee, or which of the two tiers would apply to alarm-only work on an existing building. These amounts are recorded as the county's published rates, not as a determination that they attach to this permit.
New Construction (without Sprinklers or Fire Alarm) $130; New Construction (with Sprinklers and Fire Alarm) $390; New Business License Inspection $65; Cooking Hood Inspection $65; First Re-inspection $65; Second Re-inspection $100; unlisted services $65.00/hour (1-hour minimum, quarter-hour increments thereafter, 1.5× after hours/weekends/county holidays)

Nibley building permits

Get alerts for Nibley

We'll email you when Nibley's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.