Commercial Tenant Improvement / Tenant Finish Permit — Nibley, Utah · Requirements sheet
Verified 2026-08-16 · Source: https://nibleycity.gov/building-department/
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Tenant Improvement / Tenant Finish Permit in Nibley, Utah
Required for interior remodel/tenant finish work in an existing commercial building in Nibley — e.g., a new tenant finishing out shell space, or an existing tenant remodeling — regulated by the adopted 2024 IBC and, for existing buildings, the 2024 International Existing Building Code (per Utah Code § 15A-2-103(1)(i)). Nibley does not publish a standalone tenant-improvement fee schedule; the same generic valuation-based Building Permit Fee table used for new construction applies, based on the value of the tenant-improvement work. Nibley's Planning & Zoning page states directly that impact fees — which represent the largest cost component of a new commercial building permit — are 'not charged for remodels, accessory buildings or additions, unless the addition is large enough to necessitate changing the size of the water meter,' meaning most tenant-improvement projects owe only the building permit fee, plan review fee, and any required business license, not the full impact-fee stack.
Verified 2026-08-16 · Source
When you need this permit
- Interior tenant finish or remodel of existing commercial space regulated by the adopted 2024 IBC / 2024 IEBC
- Two copies of engineered, stamped (if applicable), to-scale plans; electronic plans may be submitted with the application, per Nibley's official Building Department page general submittal requirements
- Commercial & Industrial Business License for a new tenant or new use, per the Consolidated Fee Schedule's Business Licenses & Fees section
- Conditional Use Permit if the proposed tenant use is listed as a conditional use under Nibley City Code Title 19 zoning standards
- SWPPP compliance documentation only if the project disturbs qualifying ground area (uncommon for interior-only tenant finish work)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
UNCHANGED. FY2026-27 Consolidated Fee Schedule, pages 7-8 (read from renders), 'Building Permit Fees' → 'Total Valuation' table: valuation 'according to building inspector's review.' All tiers… Show full citationHide
UNCHANGED. FY2026-27 Consolidated Fee Schedule, pages 7-8 (read from renders), 'Building Permit Fees' → 'Total Valuation' table: valuation 'according to building inspector's review.' All tiers identical to the superseded edition; no separate, lower tenant-improvement-specific fee table is published in the FY2026-27 edition either, so valuation is based on the value of the TI work itself.Nibley City Planning & Zoning page, 'When does Nibley City charge impact fees?' FAQ, quoted directly: 'Nibley City charges impact fees upon issuance of a building permit for new residential,… Show full citationHide
Nibley City Planning & Zoning page, 'When does Nibley City charge impact fees?' FAQ, quoted directly: 'Nibley City charges impact fees upon issuance of a building permit for new residential, commercial or industrial construction. Impact fees are not charged for remodels, accessory buildings or additions, unless the addition is large enough to necessitate changing the size of the water meter.' A tenant improvement is a remodel of existing space, so impact fees generally do not apply unless the project requires a larger water meter, in which case the applicable Water Impact Fee tier (see Commercial Building Permit entry) would apply.UNCHANGED. FY2026-27 Consolidated Fee Schedule, page 1 (read from render), 'Business Licenses & Fees' table — all three rates identical ($250.00 initial Jan-Dec, $125.00 initial July-Dec, $150.00 renewal Jan-Dec). Show full citationHide
UNCHANGED. FY2026-27 Consolidated Fee Schedule, page 1 (read from render), 'Business Licenses & Fees' table — all three rates identical ($250.00 initial Jan-Dec, $125.00 initial July-Dec, $150.00 renewal Jan-Dec). Applies only if the tenant improvement involves a new tenant/new use requiring its own business license, not a like-for-like remodel by an already-licensed tenant.$45.00 → $65.00. Read from a 200-dpi render of page 1 of the FY2026-27 Consolidated Fee Schedule, 'Business Licenses & Fees' table, row: 'Fire Marshall Inspection Fee (Rate set by the County) —… Show full citationHide
$45.00 → $65.00. Read from a 200-dpi render of page 1 of the FY2026-27 Consolidated Fee Schedule, 'Business Licenses & Fees' table, row: 'Fire Marshall Inspection Fee (Rate set by the County) — $65.00.' The 2025-2026 edition (page 3, also rendered) still listed $45.00, so this is a genuine FY2026-27 increase corresponding to the 'County Fire Inspections' element of Resolution 26-09 (City Council, 2026-08-06).Review timeline
Inspection process
- 1
Building, Electrical, Mechanical & Plumbing (project-specific)
Per Nibley's official Building Department page: 'Inspections will vary depending on the project. A list of required inspections will be included upon issuance of building permit.'
- 2
Fire Marshal Inspection
Inferred from the Consolidated Fee Schedule's published 'Fire Marshall Inspection Fee (Rate set by the County)' ($65.00 in the FY2026-27 edition) in the Business Licenses & Fees section; particularly relevant to tenant finish work affecting occupancy/egress or fire suppression systems.
- 3
Final / Certificate of Occupancy
Final inspection prior to Certificate of Occupancy or Certificate of Completion for the tenant space; specific commercial TI closeout process not separately detailed on Nibley's official Building Department page.
See the full Nibley inspection guide — scheduling & re-inspection fees →
Tips
- Tenant improvements are generally exempt from Nibley's impact fees (water, sewer, park, transportation) because they are a remodel of existing space — per the city's own Planning & Zoning FAQ, the only exception is if the project requires upsizing the water meter.
- There is no separate, lower tenant-improvement fee table — the building permit fee is calculated from the same generic valuation-based table as new construction, just applied to the (typically much lower) value of the interior work.
- A new business license may be required if the tenant improvement involves a new tenant or new use, at $250.00 (fee schedule label: Initial Fee Jan-Dec) or $125.00 (Initial Fee July-Dec, the half-year rate) plus a $150.00/year renewal — confirm with Nibley City whether the existing tenant's license carries over.
- No tenant-improvement-specific submittal checklist or plan review timeline is published separately from the general Building Department page — call (435) 752-0431 or email the Building Department for project-specific scoping before submittal.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-16.
Fee schedules
Applications & forms
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Nibley building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Nibley.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Nibley's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Nibley yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Nibley lands. Privacy.
Other permits in Nibley
Commercial Tenant Improvement / Tenant Finish Permit in other cities
Compare commercial tenant improvement / tenant finish permit fees across Utah →