Commercial Building Permit in Nibley, Utah

Required for new commercial and industrial construction in Nibley, regulated by the adopted 2024 International Building Code (per Utah Code § 15A-2-103(1)(a), effective July 1, 2026). Nibley's official Building Department page states general submittal requirements without a residential/commercial distinction, and the Nibley City Consolidated Fee Schedule uses a single generic 'Building Permit Fee' valuation table (unlike some cities, this table is not separately labeled 'Commercial/Residential,' but nothing on the fee schedule or Building Department page restricts it to residential use). Commercial projects additionally trigger Development Services fees not applicable to single-family residential permits: a Commercial Site Plan Review Fee, a Public Works Inspection Fee for Commercial Development, a commercial-rate Stormwater Inspection Fee, use-specific Transportation Impact Fees, and a Commercial & Industrial Business License.

Verified 2026-08-16 · Source

When you need this permit

  • New commercial or industrial construction regulated by the adopted 2024 IBC
  • Two copies of engineered, stamped (if applicable), to-scale plans; electronic plans may be submitted with the application, per Nibley's official Building Department page general submittal requirements (no separate commercial-specific submittal checklist is published)
  • To-scale plot plan / commercial site plan showing setbacks and location of project/building as well as intended location of utility services
  • Commercial Site Plan Review through Nibley City Planning & Zoning, per the Consolidated Fee Schedule's 'Charges for Development Services' section
  • Compliance with the Nibley City Design Standards for Commercial and Institutional Uses (adopted design-standards document linked from the Planning & Zoning page)
  • Commercial & Industrial Business License from Nibley City for the business/use occupying the building, per the Consolidated Fee Schedule's 'Business Licenses & Fees' section
  • Conditional Use Permit for uses listed as conditional in Nibley City Code Title 19 zoning standards, where applicable (a 'Conditional Use Permit (No Business License)' fee line is separately published in the Fee Schedule's Development Services section)
  • SWPPP compliance documentation (if necessary), using Nibley's Common Plan SWPPP Template and the State of Utah Notice of Intent (NOI)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Building Permit Fee — valuation-based (Nibley City Consolidated Fee Schedule)
UNCHANGED. All eight valuation tiers compared line by line against 200-dpi renders of pages 7-8 of the FY2026-27 Consolidated Fee Schedule and found identical. Show full citationUNCHANGED. All eight valuation tiers compared line by line against 200-dpi renders of pages 7-8 of the FY2026-27 Consolidated Fee Schedule and found identical. The table is still titled generically 'Building Permit' with valuation 'according to building inspector's review' — the same table cited for the Residential Building Permit entry; the FY2026-27 schedule still publishes no separate commercial-only valuation table.
$1–$500: $24.00 flat. $501–$2,000: $24 for the first $500 plus $3 for each additional $1,000 (or fraction thereof). $2,001–$40,000: $69 for the first $2,000 plus $11 for each additional $1,000 (or fraction thereof). $40,001–$100,000: $487 for the first $40,000 plus $9 for each additional $1,000 (or fraction thereof). $100,001–$500,000: $1,027 for the first $100,000 plus $7 for each additional $1,000 (or fraction thereof). $500,001–$1,000,000: $3,827 for the first $500,000 plus $5 for each additional $1,000 (or fraction thereof). $1,000,001–$5,000,000: $6,327 for the first $1,000,000 plus $3 for each additional $1,000 (or fraction thereof). $5,000,001 and over: $18,327 for the first $5,000,000 plus $1 for each additional $1,000 (or fraction thereof).
Plan Review FeeNibley City Consolidated Fee Schedule, 'Building Permits & Impact Fees' section: 'Plan Review Fee — 0.1% of valuation of the improvement. Additional fees for inspections outside of normal business hours may be charged according to IRC fee schedule.'
0.1% of valuation of the improvement
Commercial Site Plan Review Fee
$100/1,000 sq. ft. with a $2,500 maximum → $150/1,000 sq. Show full citation$100/1,000 sq. ft. with a $2,500 maximum → $150/1,000 sq. ft. with a $900 minimum and a $3,600 maximum, both per building. Read from a 200-dpi render of page 6 of the FY2026-27 Consolidated Fee Schedule, 'Charges for Development Services' → 'Planning Review Fees' table, row 'Commercial Site Plan Review Fee': '$150/1000 Bldg. Sq. Ft., minimum $900 per building, maximum $3600 per building.' The identical wording also appears on page 6 of the intervening 2025-2026 edition (approved 1-30-2026), so the increase predates FY2026-27 and the figure we published had been stale since at least January 2026. A new per-building minimum of $900 has also been added, which our previous entry did not carry at all.
$150 per 1,000 building sq. ft., minimum $900 per building, maximum $3,600 per building
Public Works Inspection Fee for Commercial DevelopmentUNCHANGED. FY2026-27 Consolidated Fee Schedule, page 6 (read from render), 'Charges for Development Services' → 'Planning Review Fees' table, row: 'Public Works Inspection Fee for Commercial Development — .0075 x Bond Summary.'
0.0075 × Bond Summary
Stormwater Inspection Fee (Commercial)
UNCHANGED. FY2026-27 Consolidated Fee Schedule, page 8 (read from render), row: 'Stormwater Inspection Fee Commercial — $1500/acre with minimum of $500.' Do not confuse this with the separate… Show full citationUNCHANGED. FY2026-27 Consolidated Fee Schedule, page 8 (read from render), row: 'Stormwater Inspection Fee Commercial — $1500/acre with minimum of $500.' Do not confuse this with the separate 'Stormwater Development Inspection — $750.00 per acre of development' line on page 6 of the same schedule; they are two distinct charges. The residential companion line on page 8 now reads '$350 Per Year' (previously described here as $150/year), so that parenthetical has been corrected.
$1,500 per acre, minimum $500
Conditional Use Permit (No Business License)
$50.00 → $100.00. Read from a 200-dpi render of page 6 of the FY2026-27 Consolidated Fee Schedule, 'Charges for Development Services' → 'Planning Review Fees' table, row: 'Conditional Use Permit (No… Show full citation$50.00 → $100.00. Read from a 200-dpi render of page 6 of the FY2026-27 Consolidated Fee Schedule, 'Charges for Development Services' → 'Planning Review Fees' table, row: 'Conditional Use Permit (No Business License) — $100.00.' The 2025-2026 edition (page 6, also rendered) already listed $100.00; the $50.00 we published came from the superseded FY2024-2025 edition and was already inconsistent with the change-of-use-permit entry. Applicable when the proposed commercial use is listed as a conditional use under Nibley City Code Title 19 zoning standards.
$100.00
Commercial & Industrial Business License Fee
FY2026-27 Consolidated Fee Schedule, page 1, 'Business Licenses & Fees' table: 'Commercial & Industrial Business License Initial Fee (Jan-Dec) — $250.00,' 'Commercial & Industrial Business License… Show full citationFY2026-27 Consolidated Fee Schedule, page 1, 'Business Licenses & Fees' table: 'Commercial & Industrial Business License Initial Fee (Jan-Dec) — $250.00,' 'Commercial & Industrial Business License Initial Fee (July-Dec) — $125.00,' and 'Commercial & Industrial Business License Renewal Fee (Jan-Dec) — $150.00.' Copied text scrambles this block badly — it pairs the Jan-Dec initial fee with 'Late Fee after February 1 — 10% or $10.00, whichever is greater' and shifts the other two rows down one — so read all three values from the page as published.
Initial (Jan–Dec): $250.00. Initial (July–Dec): $125.00. Renewal (Jan–Dec): $150.00.
Fire Marshall Inspection Fee
$45.00 → $65.00. Read from a 200-dpi render of page 1 of the FY2026-27 Consolidated Fee Schedule, 'Business Licenses & Fees' table, row: 'Fire Marshall Inspection Fee (Rate set by the County) —… Show full citation$45.00 → $65.00. Read from a 200-dpi render of page 1 of the FY2026-27 Consolidated Fee Schedule, 'Business Licenses & Fees' table, row: 'Fire Marshall Inspection Fee (Rate set by the County) — $65.00.' The 2025-2026 edition (page 3, also rendered) still listed $45.00 with no parenthetical, so this is a genuine FY2026-27 increase; it corresponds to the 'County Fire Inspections' element of Resolution 26-09 (City Council agenda item 16, 2026-08-06). The new '(Rate set by the County)' qualifier confirms Cache County, not Nibley, sets this rate.
$65.00
Transportation Impact Fee (commercial, per 1,000 sq. ft., by use)
UNCHANGED. FY2026-27 Consolidated Fee Schedule, page 7 (read from render), 'Building Permits & Impact Fees' → 'Impact Fees' table. Show full citationUNCHANGED. FY2026-27 Consolidated Fee Schedule, page 7 (read from render), 'Building Permits & Impact Fees' → 'Impact Fees' table. All eight commercial land-use rates compared individually and found identical: Shopping Center $2342.00, Office $1522.00, Light Industrial $466.00, Warehouse $164.00, Institutional $1426.00, Hotel $786.00, Food/Fast Food $11,257.00, Gas Station/Conv $46,015.00, each per 1000 Sq Ft. (Single Family/Multifamily/Mobile Home rates are per-unit and apply to residential only.)
Shopping Center $2,342.00; Office $1,522.00; Light Industrial $466.00; Warehouse $164.00; Institutional $1,426.00; Hotel $786.00; Food/Fast Food $11,257.00; Gas Station/Convenience $46,015.00 — all per 1,000 sq. ft.
Water Impact Fee (by meter size)
UNCHANGED. FY2026-27 Consolidated Fee Schedule, page 7 (read from render), 'Impact Fees' table — all four service-size tiers identical to what we publish. Show full citationUNCHANGED. FY2026-27 Consolidated Fee Schedule, page 7 (read from render), 'Impact Fees' table — all four service-size tiers identical to what we publish. Same tiered water impact fee schedule cited in the Residential Building Permit entry; charged upon issuance of a building permit for new commercial or industrial construction per Nibley's Planning & Zoning FAQ (see reviewTimelineNote / tips).
1" Service $3,363.00; 2" Service $10,733.00; 3" Service $20,137.00; 4" Service $33,568.00
Sewer Impact Fee (by service size)UNCHANGED. FY2026-27 Consolidated Fee Schedule, page 7 (read from render), 'Impact Fees' table — all four service-size tiers identical to what we publish. Same tiered sewer impact fee schedule cited in the Residential Building Permit entry.
1" Service $1,425.00; 2" Service $4,629.00; 3" Service $8,685.00; 4" Service $14,478.00
State Collected 1% FeeUNCHANGED. FY2026-27 Consolidated Fee Schedule, page 7 (read from render): 'State Collected 1% Fee — 1% of Building Permit Fees.'
1% of Building Permit Fees
Reinspection FeeUNCHANGED. FY2026-27 Consolidated Fee Schedule, page 8 (read from render), 'Miscellaneous Items' section, row: 'Reinspection Fee — $50.00.'
$50.00
After Hours Inspection Fee
UNCHANGED. FY2026-27 Consolidated Fee Schedule, page 8 (read from render), 'Miscellaneous Items' section, row: 'After Hours Inspection Fee upon availability and approval of Building Inspector —… Show full citationUNCHANGED. FY2026-27 Consolidated Fee Schedule, page 8 (read from render), 'Miscellaneous Items' section, row: 'After Hours Inspection Fee upon availability and approval of Building Inspector — $200.00 Per Hour, 4 hour minimum.' A parallel Public Works after-hours line on page 6 reads '$200/hr with 4 hr minimum', also unchanged.
$200.00 per hour, 4-hour minimum

Review timeline

Plan reviewNibley’s published plan-review target
10–14 business days

How long did your Commercial Building Permit permit actually take in Nibley?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Building, Electrical, Mechanical & Plumbing (project-specific)

    Per Nibley's official Building Department page: 'Inspections will vary depending on the project. A list of required inspections will be included upon issuance of building permit.'

  2. 2

    Fire Marshal Inspection

    Inferred from the Consolidated Fee Schedule's published 'Fire Marshall Inspection Fee (Rate set by the County)' ($65.00 in the FY2026-27 edition) in the Business Licenses & Fees section; no separate narrative description of when this inspection occurs was found on Nibley's official pages.

  3. 3

    Final / Certificate of Occupancy

    Final inspection prior to Certificate of Occupancy issuance; specific commercial CO process not separately detailed on Nibley's official Building Department page.

See the full Nibley inspection guide — scheduling & re-inspection fees →

Tips

  • Nibley does not publish a separate 'commercial' building permit fee table — the same generic valuation-based Building Permit Fee table used for residential construction applies to commercial and industrial construction.
  • Commercial projects trigger fees that residential single-family permits do not: a Commercial Site Plan Review Fee ($150/1,000 building sq. ft., min $900 and max $3,600 per building), a Public Works Inspection Fee for Commercial Development (0.0075 × Bond Summary), a commercial-rate Stormwater Inspection Fee ($1,500/acre, min $500 — vs. $350/year for residential), and use-specific Transportation Impact Fees that vary enormously by use (e.g., $164 per 1,000 sq. ft. for warehouse vs. $46,015 per 1,000 sq. ft. for a gas station/convenience store).
  • A Commercial & Industrial Business License is required in addition to the building permit — the fee schedule labels these 'Initial Fee (Jan-Dec)' $250.00, 'Initial Fee (July-Dec)' $125.00 (the half-year rate for licenses taken out in the second half of the calendar year), and 'Renewal Fee (Jan-Dec)' $150.00.
  • Compliance with the separately published 'Nibley City Design Standards for Commercial and Institutional Uses' document is required for commercial and institutional construction, per the Planning & Zoning page.
  • Park Impact Fees in Nibley's fee schedule are specified 'per Single Family Home/ADU' or 'per Multifamily Unit' — no commercial Park Impact Fee line is published, so it is omitted here rather than assumed.

Frequently asked questions

Nibley requires a commercial building permit for: New commercial or industrial construction regulated by the adopted 2024 IBC; Two copies of engineered, stamped (if applicable), to-scale plans; electronic plans may be submitted with the application, per Nibley's official Building Department page general submittal requirements (no separate commercial-specific submittal checklist is published); To-scale plot plan / commercial site plan showing setbacks and location of project/building as well as intended location of utility services; Commercial Site Plan Review through Nibley City Planning & Zoning, per the Consolidated Fee Schedule's 'Charges for Development Services' section; Compliance with the Nibley City Design Standards for Commercial and Institutional Uses (adopted design-standards document linked from the Planning & Zoning page); Commercial & Industrial Business License from Nibley City for the business/use occupying the building, per the Consolidated Fee Schedule's 'Business Licenses & Fees' section; Conditional Use Permit for uses listed as conditional in Nibley City Code Title 19 zoning standards, where applicable (a 'Conditional Use Permit (No Business License)' fee line is separately published in the Fee Schedule's Development Services section); SWPPP compliance documentation (if necessary), using Nibley's Common Plan SWPPP Template and the State of Utah Notice of Intent (NOI). If your project isn't listed, confirm with Nibley City Building Department (Public Works) at (435) 752-0431 before starting work.

No. Nibley's Consolidated Fee Schedule uses one generic valuation-based 'Building Permit Fee' table for all construction, plus the 0.1% Plan Review Fee. Commercial projects additionally owe a Commercial Site Plan Review Fee, a Public Works Inspection Fee for Commercial Development, a commercial-rate Stormwater Inspection Fee, use-specific Transportation Impact Fees, and Commercial & Industrial Business License fees that residential single-family permits do not.

No commercial-specific timeline is separately published. Nibley's Building Department page states a general 'up to two weeks from the date of submittal' processing guideline for building permits generally; Utah's statutory backstop for expedited plan review (Utah Code § 10-20-909) applies only to one- and two-family dwellings, not commercial construction.

You'll need: Building Permit Application; Engineered/Stamped Plans (two copies, to-scale); Commercial Site Plan; Commercial & Industrial Business License Application. Depending on your project, Nibley may also ask for: SWPPP Compliance Documentation. See the required-documents checklist on this page for details on each.

Nibley requires 3 inspection(s) for a commercial building permit, in order: Building, Electrical, Mechanical & Plumbing (project-specific), Fire Marshal Inspection, Final / Certificate of Occupancy. Schedule each through Nibley City Building Department (Public Works) ((435) 752-0431).

Apply through Nibley City Building Department (Public Works) at 455 W 3200 S, Nibley, UT 84321-6337. Phone: (435) 752-0431. Office hours: Mon–Fri 9:00 AM – 5:00 PM. Official information: https://nibleycity.gov/building-department/.

Nibley, Utah has adopted: 2021 International Residential Code (IRC) — Nibley City Building Department page states: 'Nibley is currently using the ICC Codes as amended by the state of Utah'; per Utah Code § 15A-2-103(1)(b), the 2021 IRC continues in force statewide, unchanged by the July 1, 2026 update.; 2024 International Building Code (IBC), including Appendices C and J — current statewide edition per Utah Code § 15A-2-103(1)(a), effective July 1, 2026.; 2024 International Plumbing Code (IPC) — current statewide edition per Utah Code § 15A-2-103(1)(d), effective July 1, 2026; per Nibley's own 'ICC Codes as amended by the state of Utah' statement.; 2024 International Mechanical Code (IMC) — current statewide edition per Utah Code § 15A-2-103(1)(e), effective July 1, 2026; per Nibley's own 'ICC Codes as amended by the state of Utah' statement.; 2024 International Fuel Gas Code (IFGC) — current statewide edition per Utah Code § 15A-2-103(1)(f), effective July 1, 2026; per Nibley's own 'ICC Codes as amended by the state of Utah' statement.; 2024 International Energy Conservation Code (IECC) — current statewide edition per Utah Code § 15A-2-103(1)(h), effective July 1, 2026; per Nibley's own 'ICC Codes as amended by the state of Utah' statement.; 2024 International Existing Building Code (IEBC) — current statewide edition per Utah Code § 15A-2-103(1)(i), effective July 1, 2026; per Nibley's own 'ICC Codes as amended by the state of Utah' statement.; Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — current statewide edition per Utah Code § 15A-2-103(1)(n), effective July 1, 2026; per Nibley's own 'ICC Codes as amended by the state of Utah' statement.; 2023 National Electrical Code (NEC) — current statewide edition per Utah Code § 15A-2-103(1)(g); unchanged by the July 1, 2026 statewide update.; Modular Building Institute Standards 1200 and 1205 — adopted statewide per Utah Code § 15A-2-103(1)(o); not separately itemized on Nibley's own page, but applies statewide.. Local amendments apply — see the Nibley overview page for the full list.

Yes. Nibley's FY2026-27 Consolidated Fee Schedule lists a Commercial & Industrial Business License Initial Fee of $250.00 (labelled Jan-Dec) or $125.00 (labelled July-Dec, the half-year rate), with a $150.00 annual renewal fee.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Nibley.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.

Nibley's permit history isn't searchable here yet

This page covers what the permit requires. What we don't have for Nibley yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.

Your email, and the place — never an address. We only use it to tell you when Nibley lands. Privacy.