How to schedule

Inspections are requested through the building department below.

Address
1600 E South Weber Drive, South Weber, UT 84405
Phone
(801) 479-3177
Office hours
Mon–Thu 8:30 AM – 5:30 PM, Fri 8:00 AM – 12:00 PM

Inspection sequence

Applies to: Commercial Building Permit

  1. 1

    Foundation/Footing

    Initial structural inspection scheduled through South Weber City Building Department (801-479-3177) prior to concrete pour.

  2. 2

    Framing

    Framing and rough mechanical/electrical/plumbing inspection prior to insulation and wall cover.

  3. 3

    Final Inspection

    Final building inspection required before Certificate of Occupancy; the applicable Completion Bond ($1,500 or $500 depending on valuation) is refunded following successful completion.

Applies to: Residential Building Permit (New Construction)

  1. 1

    Footing/Foundation

    Initial structural inspection scheduled through South Weber City Building Department (801-479-3177) prior to concrete pour.

  2. 2

    Framing

    Framing, fire-blocking, and rough mechanical/electrical/plumbing inspection prior to insulation and drywall.

  3. 3

    Final Inspection

    Final building inspection required before Certificate of Occupancy; South Weber's Completion Bond (residential new construction: $500) is refunded following successful completion per the Consolidated Fee Schedule.

Applies to: Commercial Tenant Improvement / Tenant Finish Permit

  1. 1

    Framing / Rough-In

    Wall construction and MEP rough-in inspection scheduled through South Weber City Building Department (801-479-3177).

  2. 2

    Final Inspection

    Final inspection required before the applicable Completion Bond is refunded.

Applies to: Remodeling / Finish Basement Permit

  1. 1

    Framing

    Wall framing, fire-blocking, and rough MEP inspection for remodel or basement-finish scope.

  2. 2

    Final Inspection

    Final inspection required before completion bond ($200 or $100 depending on permit type) is refunded.

Applies to: Sign Permit (Temporary)

  1. 1

    Completion Inspection

    Inspection confirming sign installation compliance.

  2. 2

    Planning Commission Requirements

    Second required inspection/sign-off tied to Planning Commission requirements for temporary signage.

Re-inspection fees

Fire Sprinkler & Fire Alarm System ReviewFire Inspection (Business License) — Light/Medium Commercial or Large Commercial/Mining/Gravel Pits · South Weber City Consolidated Fee Schedule FY2026-2027, Chapter 5, Item 36: 'Fire Inspection — Light/Medium Commercial: 100.00 each year' and 'Large Commercial/Mining/Gravel Pits: 100.00 each year.' Per the Business License Application form, the re-inspection cycle after the initial inspection is Annually or Every 3 years, checked at issuance.
$100.00 per year

Sources & verification

Verified against official sources. Last reviewed 2026-07-08.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the South Weber building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

South Weber building permits

Get alerts for South Weber

We'll email you when South Weber's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.