Residential Building Permit (New Construction) in South Weber, Utah

Required for new single-family and two-family residential construction, room additions, detached/attached garages, and any structural work regulated by the Utah State Construction Code in South Weber City. Fee is calculated using the ICC Building Valuation Data formula per South Weber's official Consolidated Fee Schedule.

Verified 2026-07-08 · Source

When you need this permit

  • New single-family or two-family residential construction
  • Room additions, detached or attached garages, patio enclosures
  • Any structural modification or replacement/repair of a structural component
  • Site plan and building plans submitted for review by the Building Official
  • New residential construction is subject to Parks & Trails, Public Safety Fire Station, Recreation Building, Water, Sewer (City + Central Weber Sewer), Storm Sewer, and Transportation impact fees per South Weber's Consolidated Fee Schedule Chapter 7

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee (valuation-based, ICC formula)South Weber City Consolidated Fee Schedule, Fiscal Year 2026-2027, Chapter 6 'Building Permit Fees', Item 38: 'Building Permit Fee — ICC Formula: Gross Area x Sq Ft x Constr. Cost x Permit Fee Multiplier.' Retrieved from southwebercity.gov/wp-content/uploads/2027-CFS.pdf.
Gross Area x Square Foot Construction Cost x Permit Fee Multiplier, per the 2025 ICC Building Code Valuation Data
Plan Check FeeSouth Weber Consolidated Fee Schedule FY2026-2027, Chapter 6, Item 38.
30% of the building permit fee, or $100 minimum, plus any professional services
State FeeSouth Weber Consolidated Fee Schedule FY2026-2027, Chapter 6, Item 38: 'State Fee — 1% of building fee for all building permits.'
1% of the building permit fee
Residential New Construction Completion BondSouth Weber Consolidated Fee Schedule FY2026-2027, Chapter 6, Item 39 'Completion Bonds': 'Residential- New Construction: 500.00.'
$500.00 (refundable)
Parks & Trails Impact Fee (Single Family Residential)South Weber Consolidated Fee Schedule FY2026-2027, Chapter 7, Item 40.
$2,096.00 per dwelling unit
Public Safety Fire Station Impact Fee (Single Family Residential)South Weber Consolidated Fee Schedule FY2026-2027, Chapter 7, Item 41.
$126.00 per dwelling unit
Recreation Building Impact Fee (Single Family Residential)South Weber Consolidated Fee Schedule FY2026-2027, Chapter 7, Item 42.
$834.00 per dwelling unit
Water Impact Fee (Residential, 1-inch meter)South Weber Consolidated Fee Schedule FY2026-2027, Chapter 7, Item 43.
$1,463.00
Transportation Impact Fee (Single Family Detached Housing)South Weber Consolidated Fee Schedule FY2026-2027, Chapter 7, Item 45, ITE 210 category.
$3,597.00 per dwelling unit
Storm Sewer Impact FeeSouth Weber Consolidated Fee Schedule FY2026-2027, Chapter 7, Item 47.
$1,281.00 per ERU (1.0 ERU per lot for single-family)

Review timeline

Plan reviewSouth Weber’s published plan-review target
17–17 business days

How long did your Residential Building Permit (New Construction) permit actually take in South Weber?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Footing/Foundation

    Initial structural inspection scheduled through South Weber City Building Department (801-479-3177) prior to concrete pour.

  2. 2

    Framing

    Framing, fire-blocking, and rough mechanical/electrical/plumbing inspection prior to insulation and drywall.

  3. 3

    Final Inspection

    Final building inspection required before Certificate of Occupancy; South Weber's Completion Bond (residential new construction: $500) is refunded following successful completion per the Consolidated Fee Schedule.

See the full South Weber inspection guide — scheduling & re-inspection fees →

Tips

  • South Weber's Building Permit Fee uses the ICC Building Valuation Data formula (2025 edition per the FY2026-2027 fee schedule) rather than a flat table — request the current Square Foot Construction Cost table from the Building Department to estimate fees before applying.
  • New residential construction in South Weber is subject to six separate impact fees (Parks & Trails, Public Safety Fire Station, Recreation Building, Water, Storm Sewer, Transportation) plus Central Weber Sewer District fees — budget for these in addition to the building permit and plan check fees.
  • A $500 refundable completion bond is required for new residential construction, separate from the building permit fee itself.
  • City Office Hours are Mon-Thu 8:30 AM-5:30 PM and Friday 8:00 AM-12:00 PM only — South Weber closes early on Fridays and is closed Friday afternoons, unlike many neighboring Davis County cities.

Frequently asked questions

South Weber requires a residential building permit (new construction) for: New single-family or two-family residential construction; Room additions, detached or attached garages, patio enclosures; Any structural modification or replacement/repair of a structural component; Site plan and building plans submitted for review by the Building Official; New residential construction is subject to Parks & Trails, Public Safety Fire Station, Recreation Building, Water, Sewer (City + Central Weber Sewer), Storm Sewer, and Transportation impact fees per South Weber's Consolidated Fee Schedule Chapter 7. If your project isn't listed, confirm with South Weber City Building Department (Public Works) at (801) 479-3177 before starting work.

South Weber uses the ICC Building Valuation Data formula: Gross Area x Square Foot Construction Cost x Permit Fee Multiplier, per the city's official Consolidated Fee Schedule (FY2026-2027). A Plan Check Fee of 30% of the building permit fee (or $100 minimum) and a State Fee of 1% of the building fee also apply.

South Weber does not publish its own plan-review turnaround time. Utah Code § 10-20-909 requires all Utah municipalities, including South Weber, to complete plan review of a one- or two-family dwelling or townhome within 14 business days after a mandatory 3-business-day application completeness screening period — 17 business days total from submission — as a statutory floor.

You'll need: Building Permit Application; Site Plan. Depending on your project, South Weber may also ask for: When Do I Need a Building Permit? Checklist. See the required-documents checklist on this page for details on each.

South Weber requires 3 inspection(s) for a residential building permit (new construction), in order: Footing/Foundation, Framing, Final Inspection. Schedule each through South Weber City Building Department (Public Works) ((801) 479-3177).

Apply through South Weber City Building Department (Public Works) at 1600 E South Weber Drive, South Weber, UT 84405. Phone: (801) 479-3177, email: mlarsen@southwebercity.com. Office hours: Mon–Thu 8:30 AM – 5:30 PM, Fri 8:00 AM – 12:00 PM. Official information: https://southwebercity.gov/i-want-to/forms/.

South Weber, Utah has adopted: South Weber City is subject to the Utah State Construction Code (Utah Code § 15A-2-103), which as of 7/1/2026 CURRENTLY adopts: the 2024 International Building Code (IBC), including Appendices C and J, § 15A-2-103(1)(a); the 2021 International Residential Code (IRC), § 15A-2-103(1)(b), UNCHANGED by the 7/1/2026 amendment, plus Appendix AQ of the 2021 IRC, § 15A-2-103(1)(c); the 2024 International Plumbing Code (IPC), § 15A-2-103(1)(d); the 2024 International Mechanical Code (IMC), § 15A-2-103(1)(e); the 2024 International Fuel Gas Code (IFGC), § 15A-2-103(1)(f); the 2024 International Energy Conservation Code (IECC), single unsplit statewide edition, § 15A-2-103(1)(h); the 2024 International Existing Building Code (IEBC), § 15A-2-103(1)(i); and the residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC), § 15A-2-103(1)(n). South Weber's own Building Department page and forms (live-checked 2026-07-16) do not publish a city-specific code-edition statement beyond referencing 'building codes' generally, so the applicable edition is the statewide-adopted edition rather than a city-specific amendment — this could not be independently confirmed on a South Weber-specific ordinance page beyond the code index (see localAmendments note on codelibrary.amlegal.com access). No city-page conflict to record since South Weber publishes no edition statement of its own to contradict the statute.; 2023 National Electrical Code (NEC) — statewide-adopted edition per Utah Code § 15A-2-103(1)(g); UNCHANGED by the 7/1/2026 amendment; no South Weber-specific amendment to the NEC edition was found.; NOTE (2026-07-16 re-verification): The Utah Code § 15A-2-103 version effective 7/1/2026 (superseded 1/1/2027) took effect 15 days before this re-verification; this entry previously described the 2024-cycle codes in future tense ('scheduled to take effect July 1, 2026') and as a single undifferentiated '2021 I-Codes' set. That date has now passed, so IBC/IPC/IMC/IFGC/IECC/IEBC/residential ISPSC are now individually itemized above and stated as CURRENT (2024 editions), while IRC (2021) and NEC (2023) are explicitly flagged as unchanged. Utah's statewide-mandatory code regime (Utah Code § 15A-1-204) binds South Weber directly since it publishes no city-specific edition page of its own.. Local amendments apply — see the South Weber overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-08.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the South Weber building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.