EV Charger / EVSE Permit in South Weber, Utah

South Weber does not publish a distinct EV-charger/EVSE fee category. Installing electric vehicle charging equipment (a new circuit/wiring for the EVSE) is electrical work covered by the city's combined Electrical/Mechanical permit, billed at the single flat fee on the Consolidated Fee Schedule FY2026-2027. This is confirmed directly by South Weber's own electrical-mechanical-permit entry, which explicitly states EV charger/EVSE installation falls under the combined Electrical/Mechanical permit and that the fee schedule carries no EV-specific line item.

Verified 2026-07-20 · Source

When you need this permit

  • Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property
  • New electrical circuit/wiring or service capacity to serve the charger
  • Falls under South Weber's 'Requires Permits — Inside' checklist item for electrical work

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Electrical/Mechanical FeeSouth Weber City Consolidated Fee Schedule FY2026-2027, Chapter 6, Item 38: 'Electrical/Mechanical — 151.00 includes $50 refundable completion bond & 1% state fee.' No separate EV Charger line item exists in this schedule; EV/EVSE work is billed under this combined flat fee.
$151.00 (includes $50 refundable completion bond and 1% state fee)

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / EVSE Permit permit actually take in South Weber?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Electrical/Mechanical Inspection

    Scheduled through South Weber City Building Department (801-479-3177).

See the full South Weber inspection guide — scheduling & re-inspection fees →

Tips

  • South Weber has no separate EV-charger fee category — file EV/EVSE installations under the combined Electrical/Mechanical permit ($151.00 flat fee), not as a standalone permit type.
  • The $151 fee already bundles a $50 refundable completion bond and the statewide 1% state fee — no additional line items apply for a standard EV charger circuit.

Frequently asked questions

The combined Electrical/Mechanical permit, applied for through the South Weber City Building Department's Forms page.

No. South Weber's Consolidated Fee Schedule does not list a distinct EV-charger fee category. EV charger/EVSE installations are billed under the combined Electrical/Mechanical permit fee of $151.00.

South Weber does not publish a plan-review timeline for this permit. Contact South Weber City Building Department (Public Works) at (801) 479-3177 for current turnaround.

You'll need: Building Permit Application. See the required-documents checklist on this page for details on each.

South Weber requires 1 inspection(s) for an ev charger / evse permit, in order: Electrical/Mechanical Inspection. Schedule each through South Weber City Building Department (Public Works) ((801) 479-3177).

Apply through South Weber City Building Department (Public Works) at 1600 E South Weber Drive, South Weber, UT 84405. Phone: (801) 479-3177, email: mlarsen@southwebercity.com. Office hours: Mon–Thu 8:30 AM – 5:30 PM, Fri 8:00 AM – 12:00 PM. Official information: https://southwebercity.gov/i-want-to/forms/.

South Weber, Utah has adopted: South Weber City is subject to the Utah State Construction Code (Utah Code § 15A-2-103), which as of 7/1/2026 CURRENTLY adopts: the 2024 International Building Code (IBC), including Appendices C and J, § 15A-2-103(1)(a); the 2021 International Residential Code (IRC), § 15A-2-103(1)(b), UNCHANGED by the 7/1/2026 amendment, plus Appendix AQ of the 2021 IRC, § 15A-2-103(1)(c); the 2024 International Plumbing Code (IPC), § 15A-2-103(1)(d); the 2024 International Mechanical Code (IMC), § 15A-2-103(1)(e); the 2024 International Fuel Gas Code (IFGC), § 15A-2-103(1)(f); the 2024 International Energy Conservation Code (IECC), single unsplit statewide edition, § 15A-2-103(1)(h); the 2024 International Existing Building Code (IEBC), § 15A-2-103(1)(i); and the residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC), § 15A-2-103(1)(n). South Weber's own Building Department page and forms (live-checked 2026-07-16) do not publish a city-specific code-edition statement beyond referencing 'building codes' generally, so the applicable edition is the statewide-adopted edition rather than a city-specific amendment — this could not be independently confirmed on a South Weber-specific ordinance page beyond the code index (see localAmendments note on codelibrary.amlegal.com access). No city-page conflict to record since South Weber publishes no edition statement of its own to contradict the statute.; 2023 National Electrical Code (NEC) — statewide-adopted edition per Utah Code § 15A-2-103(1)(g); UNCHANGED by the 7/1/2026 amendment; no South Weber-specific amendment to the NEC edition was found.; NOTE (2026-07-16 re-verification): The Utah Code § 15A-2-103 version effective 7/1/2026 (superseded 1/1/2027) took effect 15 days before this re-verification; this entry previously described the 2024-cycle codes in future tense ('scheduled to take effect July 1, 2026') and as a single undifferentiated '2021 I-Codes' set. That date has now passed, so IBC/IPC/IMC/IFGC/IECC/IEBC/residential ISPSC are now individually itemized above and stated as CURRENT (2024 editions), while IRC (2021) and NEC (2023) are explicitly flagged as unchanged. Utah's statewide-mandatory code regime (Utah Code § 15A-1-204) binds South Weber directly since it publishes no city-specific edition page of its own.. Local amendments apply — see the South Weber overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the South Weber building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.