Unincorporated Utah County building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Unincorporated Utah County, Utah.

Verified 2026-07-16 · Source

How to schedule

Inspections are requested through the building department below.

Address
51 South University Avenue, Suite 117, Provo, UT 84601
Phone
(801) 851-8342
Office hours
Mon–Fri 8:00 AM – 4:30 PM (inspection scheduling: ShaunaL@utahcounty.gov)

Published scheduling rules

  • Schedule inspections with at least 3 days advance notice via email to ShaunaL@utahcounty.gov or call (801) 851-8342. (Residential Building Permit)
  • Schedule inspections with at least 3 business days advance notice. Contact: ShaunaL@utahcounty.gov or (801) 851-8342. (General)

Inspection sequence

Applies to: Accessory Dwelling Unit (ADU)

  1. 1

    Foundation

    Footings, forms, rebar — before concrete pour

  2. 2

    Framing

    Structure, fire separation between units, egress windows

  3. 3

    MEP Rough-In

    Mechanical, electrical, plumbing rough-ins before walls closed

  4. 4

    Insulation

    Insulation and vapor barrier before drywall

  5. 5

    Final

    All work complete, smoke/CO detectors installed, address posted, ready for occupancy

Applies to: Basement Finish Permit

  1. 1

    Framing

    Wall framing, fire blocking, and egress window openings

  2. 2

    MEP Rough-In

    Electrical, plumbing, and HVAC rough-ins before walls closed

  3. 3

    Insulation

    Insulation on exterior walls before drywall

  4. 4

    Final

    Drywall, fixtures, smoke/CO detectors, and all finishes complete

Applies to: Residential Building Permit

  1. 1

    Foundation / Footings

    Before concrete pour — forms, rebar, anchor bolts; provide up to 3 days advance notice for inspection scheduling

  2. 2

    Framing

    After framing, sheathing, and roof — before insulation or wall cover

  3. 3

    Insulation

    After insulation installed, before drywall

  4. 4

    Final

    All work complete — Certificate of Occupancy issued upon passing. Occupancy prohibited until final inspection approved.

Applies to: Swimming Pool Permit

  1. 1

    Excavation / Steel

    Pool shell excavation, rebar, and plumbing before gunite/shotcrete

  2. 2

    Electrical / Bonding

    Pool bonding grid, equipment connections, GFCI protection

  3. 3

    Barrier

    Pool fence / barrier — 48-inch minimum height, self-closing / self-latching gates

  4. 4

    Final

    Pool complete, filled, equipment operational, all barriers in place

Applies to: Commercial Building Permit

  1. 1

    Foundation / Footing

    Before concrete pour. Utah County's own materials do not publish a commercial-specific inspection checklist distinct from the general building inspection sequence used for the residential-building-permit entry in this file.

  2. 2

    Framing

    After framing, sheathing, and roof — before insulation or wall cover.

  3. 3

    Final

    All work complete — Certificate of Occupancy issued upon passing.

Applies to: Deck Permit

  1. 1

    Footings

    Verify footing depth (below frost line at 30 inches minimum), diameter, and rebar before concrete pour

  2. 2

    Framing

    Posts, beams, joists, ledger connection, and hardware

  3. 3

    Final

    Decking, stairs, guards, and railings complete — 36-inch guard height required per IRC

Applies to: Electrical Permit

  1. 1

    Rough-In

    After wiring installed, before walls closed — verify box placement, wire sizing, proper support

  2. 2

    Service / Panel

    Panel installation, grounding electrode system, service entrance conductors

  3. 3

    Final

    All devices installed, GFCI/AFCI protection verified, panel labeled

Applies to: Grading & Excavation Permit

  1. 1

    Erosion Control

    Silt fence, inlet protection, and stabilization measures in place before work begins

  2. 2

    Rough Grade

    Cut/fill completed, verify elevations match approved plan

  3. 3

    Final Grade

    Drainage verified, slopes stabilized, permanent landscaping or erosion control in place

Applies to: Plumbing Permit

  1. 1

    Underground / Slab

    Before concrete pour — verify pipe slope, materials, and cleanouts

  2. 2

    Rough-In

    After pipes installed, before walls closed — pressure test required

  3. 3

    Final

    All fixtures connected, water flowing, no leaks, proper venting verified

Applies to: Commercial Tenant Improvement / Tenant Finish Permit

  1. 1

    Framing / Structural

    Where structural or MEP changes are part of the tenant-improvement scope, before close-in.

  2. 2

    Final

    All work complete — Certificate of Occupancy issued upon passing.

Applies to: Demolition Permit

  1. 1

    Pre-Demolition

    Verify utility disconnects are complete and any required asbestos clearance is obtained before work begins

  2. 2

    Final / Site Clear

    Site cleared, foundation removed or capped, site conditions verified

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough-In

    After wiring installed, before walls closed — verify box placement, wire sizing, proper support

  2. 2

    Final

    Charger installed and operational, GFCI/AFCI protection verified, panel labeled

Applies to: Fire Alarm System Permit

  1. 1

    Rough-In

    Visual site inspection of alarm wiring/devices before concealment, included in the base permit fee.

  2. 2

    Final Test

    Final functional test of the alarm system, included in the base permit fee.

Applies to: Fire Sprinkler Permit

  1. 1

    Rough-In

    Site inspection of sprinkler piping/heads before concealment, included in the base permit fee per the Fire Marshal's fee schedule.

  2. 2

    Final

    Final site inspection and test, included in the base permit fee.

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In

    Ductwork and gas piping installed, before walls closed — verify clearances, support, and combustion air

  2. 2

    Final

    Equipment operational, combustion air verified, gas pressure tested, thermostat functional

Applies to: Roofing Permit

  1. 1

    Deck / Substrate

    After tear-off — verify sheathing condition, replace damaged decking before proceeding

  2. 2

    Final

    Completed roof — verify ice and water shield, flashing, drip edge, and nailing pattern

Applies to: Solar Panel Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before energizing

  2. 2

    Final / Structural

    Panel mounting, racking attachment, roof penetration sealing, and electrical connections verified

Re-inspection fees

Electrical PermitRe-Inspection Fee (Normal Business Hours) · Utah County Code, Fee Schedule — Building Permits, Exhibit A (effective 4/3/2012).
$101.00
EV Charger / EVSE PermitRe-Inspection Fee (Normal Business Hours) · Utah County Code, Fee Schedule — Building Permits, Exhibit A (effective 4/3/2012).
$101.00
Mechanical / HVAC PermitRe-Inspection Fee (Normal Business Hours) · Utah County Code, Fee Schedule — Building Permits, Exhibit A (effective 4/3/2012).
$101.00
Fire Sprinkler PermitRe-inspection after non-compliance of initial inspection · Utah County Fire Marshal Permit Fee Schedule, Miscellaneous Permits and Fees, item 2. Plus applicable Zone Fee.
$70.00
Fire Alarm System PermitRe-inspection after non-compliance of initial inspection · Utah County Fire Marshal Permit Fee Schedule, Miscellaneous Permits and Fees, item 2. Plus applicable Zone Fee.
$70.00

Unincorporated Utah County building permits

Get alerts for Unincorporated Utah County

We'll email you when Unincorporated Utah County's fees, documents, or codes change — not often.