Unincorporated Utah County building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Unincorporated Utah County, Utah.
Verified 2026-07-16 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 51 South University Avenue, Suite 117, Provo, UT 84601
- Phone
- (801) 851-8342
- Office hours
- Mon–Fri 8:00 AM – 4:30 PM (inspection scheduling: ShaunaL@utahcounty.gov)
- Website
- Official site
Published scheduling rules
- Schedule inspections with at least 3 days advance notice via email to ShaunaL@utahcounty.gov or call (801) 851-8342. (Residential Building Permit)
- Schedule inspections with at least 3 business days advance notice. Contact: ShaunaL@utahcounty.gov or (801) 851-8342. (General)
Inspection sequence
Applies to: Accessory Dwelling Unit (ADU)
- 1
Foundation
Footings, forms, rebar — before concrete pour
- 2
Framing
Structure, fire separation between units, egress windows
- 3
MEP Rough-In
Mechanical, electrical, plumbing rough-ins before walls closed
- 4
Insulation
Insulation and vapor barrier before drywall
- 5
Final
All work complete, smoke/CO detectors installed, address posted, ready for occupancy
Applies to: Basement Finish Permit
- 1
Framing
Wall framing, fire blocking, and egress window openings
- 2
MEP Rough-In
Electrical, plumbing, and HVAC rough-ins before walls closed
- 3
Insulation
Insulation on exterior walls before drywall
- 4
Final
Drywall, fixtures, smoke/CO detectors, and all finishes complete
Applies to: Residential Building Permit
- 1
Foundation / Footings
Before concrete pour — forms, rebar, anchor bolts; provide up to 3 days advance notice for inspection scheduling
- 2
Framing
After framing, sheathing, and roof — before insulation or wall cover
- 3
Insulation
After insulation installed, before drywall
- 4
Final
All work complete — Certificate of Occupancy issued upon passing. Occupancy prohibited until final inspection approved.
Applies to: Swimming Pool Permit
- 1
Excavation / Steel
Pool shell excavation, rebar, and plumbing before gunite/shotcrete
- 2
Electrical / Bonding
Pool bonding grid, equipment connections, GFCI protection
- 3
Barrier
Pool fence / barrier — 48-inch minimum height, self-closing / self-latching gates
- 4
Final
Pool complete, filled, equipment operational, all barriers in place
Applies to: Commercial Building Permit
- 1
Foundation / Footing
Before concrete pour. Utah County's own materials do not publish a commercial-specific inspection checklist distinct from the general building inspection sequence used for the residential-building-permit entry in this file.
- 2
Framing
After framing, sheathing, and roof — before insulation or wall cover.
- 3
Final
All work complete — Certificate of Occupancy issued upon passing.
Applies to: Deck Permit
- 1
Footings
Verify footing depth (below frost line at 30 inches minimum), diameter, and rebar before concrete pour
- 2
Framing
Posts, beams, joists, ledger connection, and hardware
- 3
Final
Decking, stairs, guards, and railings complete — 36-inch guard height required per IRC
Applies to: Electrical Permit
- 1
Rough-In
After wiring installed, before walls closed — verify box placement, wire sizing, proper support
- 2
Service / Panel
Panel installation, grounding electrode system, service entrance conductors
- 3
Final
All devices installed, GFCI/AFCI protection verified, panel labeled
Applies to: Grading & Excavation Permit
- 1
Erosion Control
Silt fence, inlet protection, and stabilization measures in place before work begins
- 2
Rough Grade
Cut/fill completed, verify elevations match approved plan
- 3
Final Grade
Drainage verified, slopes stabilized, permanent landscaping or erosion control in place
Applies to: Plumbing Permit
- 1
Underground / Slab
Before concrete pour — verify pipe slope, materials, and cleanouts
- 2
Rough-In
After pipes installed, before walls closed — pressure test required
- 3
Final
All fixtures connected, water flowing, no leaks, proper venting verified
Applies to: Commercial Tenant Improvement / Tenant Finish Permit
- 1
Framing / Structural
Where structural or MEP changes are part of the tenant-improvement scope, before close-in.
- 2
Final
All work complete — Certificate of Occupancy issued upon passing.
Applies to: Demolition Permit
- 1
Pre-Demolition
Verify utility disconnects are complete and any required asbestos clearance is obtained before work begins
- 2
Final / Site Clear
Site cleared, foundation removed or capped, site conditions verified
Applies to: EV Charger / EVSE Permit
- 1
Rough-In
After wiring installed, before walls closed — verify box placement, wire sizing, proper support
- 2
Final
Charger installed and operational, GFCI/AFCI protection verified, panel labeled
Applies to: Fire Alarm System Permit
- 1
Rough-In
Visual site inspection of alarm wiring/devices before concealment, included in the base permit fee.
- 2
Final Test
Final functional test of the alarm system, included in the base permit fee.
Applies to: Fire Sprinkler Permit
- 1
Rough-In
Site inspection of sprinkler piping/heads before concealment, included in the base permit fee per the Fire Marshal's fee schedule.
- 2
Final
Final site inspection and test, included in the base permit fee.
Applies to: Mechanical / HVAC Permit
- 1
Rough-In
Ductwork and gas piping installed, before walls closed — verify clearances, support, and combustion air
- 2
Final
Equipment operational, combustion air verified, gas pressure tested, thermostat functional
Applies to: Roofing Permit
- 1
Deck / Substrate
After tear-off — verify sheathing condition, replace damaged decking before proceeding
- 2
Final
Completed roof — verify ice and water shield, flashing, drip edge, and nailing pattern
Applies to: Solar Panel Permit
- 1
Rough Electrical
Conduit runs, wire sizing, disconnect placement before energizing
- 2
Final / Structural
Panel mounting, racking attachment, roof penetration sealing, and electrical connections verified
Final inspection only: Change of Use / Certificate of Occupancy Permit, Fence Permit, Water Heater Permit
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-16.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Utah County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Unincorporated Utah County building permits
Get alerts for Unincorporated Utah County