Unincorporated Utah County building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Unincorporated Utah County, Utah.

Verified 2026-07-16 · Source

How to schedule

Inspections are requested through the building department below.

Address
51 South University Avenue, Suite 117, Provo, UT 84601
Phone
(801) 851-8342
Office hours
Mon–Fri 8:00 AM – 4:30 PM (inspection scheduling: ShaunaL@utahcounty.gov)

Published scheduling rules

  • Schedule inspections with at least 3 days advance notice via email to ShaunaL@utahcounty.gov or call (801) 851-8342. (Residential Building Permit)
  • Schedule inspections with at least 3 business days advance notice. Contact: ShaunaL@utahcounty.gov or (801) 851-8342. (General)

Inspection sequence

Applies to: Accessory Dwelling Unit (ADU)

  1. 1

    Foundation

    Footings, forms, rebar — before concrete pour

  2. 2

    Framing

    Structure, fire separation between units, egress windows

  3. 3

    MEP Rough-In

    Mechanical, electrical, plumbing rough-ins before walls closed

  4. 4

    Insulation

    Insulation and vapor barrier before drywall

  5. 5

    Final

    All work complete, smoke/CO detectors installed, address posted, ready for occupancy

Applies to: Basement Finish Permit

  1. 1

    Framing

    Wall framing, fire blocking, and egress window openings

  2. 2

    MEP Rough-In

    Electrical, plumbing, and HVAC rough-ins before walls closed

  3. 3

    Insulation

    Insulation on exterior walls before drywall

  4. 4

    Final

    Drywall, fixtures, smoke/CO detectors, and all finishes complete

Applies to: Residential Building Permit

  1. 1

    Foundation / Footings

    Before concrete pour — forms, rebar, anchor bolts; provide up to 3 days advance notice for inspection scheduling

  2. 2

    Framing

    After framing, sheathing, and roof — before insulation or wall cover

  3. 3

    Insulation

    After insulation installed, before drywall

  4. 4

    Final

    All work complete — Certificate of Occupancy issued upon passing. Occupancy prohibited until final inspection approved.

Applies to: Swimming Pool Permit

  1. 1

    Excavation / Steel

    Pool shell excavation, rebar, and plumbing before gunite/shotcrete

  2. 2

    Electrical / Bonding

    Pool bonding grid, equipment connections, GFCI protection

  3. 3

    Barrier

    Pool fence / barrier — 48-inch minimum height, self-closing / self-latching gates

  4. 4

    Final

    Pool complete, filled, equipment operational, all barriers in place

Applies to: Commercial Building Permit

  1. 1

    Foundation / Footing

    Before concrete pour. Utah County's own materials do not publish a commercial-specific inspection checklist distinct from the general building inspection sequence used for the residential-building-permit entry in this record.

  2. 2

    Framing

    After framing, sheathing, and roof — before insulation or wall cover.

  3. 3

    Final

    All work complete — Certificate of Occupancy issued upon passing.

Applies to: Deck Permit

  1. 1

    Footings

    Verify footing depth (below frost line at 30 inches minimum), diameter, and rebar before concrete pour

  2. 2

    Framing

    Posts, beams, joists, ledger connection, and hardware

  3. 3

    Final

    Decking, stairs, guards, and railings complete — 36-inch guard height required per IRC

Applies to: Electrical Permit

  1. 1

    Rough-In

    After wiring installed, before walls closed — verify box placement, wire sizing, proper support

  2. 2

    Service / Panel

    Panel installation, grounding electrode system, service entrance conductors

  3. 3

    Final

    All devices installed, GFCI/AFCI protection verified, panel labeled

Applies to: Grading & Excavation Permit

  1. 1

    Erosion Control

    Silt fence, inlet protection, and stabilization measures in place before work begins

  2. 2

    Rough Grade

    Cut/fill completed, verify elevations match approved plan

  3. 3

    Final Grade

    Drainage verified, slopes stabilized, permanent landscaping or erosion control in place

Applies to: Plumbing Permit

  1. 1

    Underground / Slab

    Before concrete pour — verify pipe slope, materials, and cleanouts

  2. 2

    Rough-In

    After pipes installed, before walls closed — pressure test required

  3. 3

    Final

    All fixtures connected, water flowing, no leaks, proper venting verified

Applies to: Commercial Tenant Improvement / Tenant Finish Permit

  1. 1

    Framing / Structural

    Where structural or MEP changes are part of the tenant-improvement scope, before close-in.

  2. 2

    Final

    All work complete — Certificate of Occupancy issued upon passing.

Applies to: Demolition Permit

  1. 1

    Pre-Demolition

    Verify utility disconnects are complete and any required asbestos clearance is obtained before work begins

  2. 2

    Final / Site Clear

    Site cleared, foundation removed or capped, site conditions verified

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough-In

    After wiring installed, before walls closed — verify box placement, wire sizing, proper support

  2. 2

    Final

    Charger installed and operational, GFCI/AFCI protection verified, panel labeled

Applies to: Fire Alarm System Permit

  1. 1

    Rough-In

    Visual site inspection of alarm wiring/devices before concealment, included in the base permit fee.

  2. 2

    Final Test

    Final functional test of the alarm system, included in the base permit fee.

Applies to: Fire Sprinkler Permit

  1. 1

    Rough-In

    Site inspection of sprinkler piping/heads before concealment, included in the base permit fee per the Fire Marshal's fee schedule.

  2. 2

    Final

    Final site inspection and test, included in the base permit fee.

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In

    Ductwork and gas piping installed, before walls closed — verify clearances, support, and combustion air

  2. 2

    Final

    Equipment operational, combustion air verified, gas pressure tested, thermostat functional

Applies to: Roofing Permit

  1. 1

    Deck / Substrate

    After tear-off — verify sheathing condition, replace damaged decking before proceeding

  2. 2

    Final

    Completed roof — verify ice and water shield, flashing, drip edge, and nailing pattern

Applies to: Solar Panel Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before energizing

  2. 2

    Final / Structural

    Panel mounting, racking attachment, roof penetration sealing, and electrical connections verified

Re-inspection fees

Electrical PermitRe-Inspection Fee (Normal Business Hours) · Utah County Code, Fee Schedule — Building Permits, Exhibit A (effective 4/3/2012).
$101.00
EV Charger / EVSE PermitRe-Inspection Fee (Normal Business Hours) · Utah County Code, Fee Schedule — Building Permits, Exhibit A (effective 4/3/2012).
$101.00
Mechanical / HVAC PermitRe-Inspection Fee (Normal Business Hours) · Utah County Code, Fee Schedule — Building Permits, Exhibit A (effective 4/3/2012).
$101.00
Fire Sprinkler PermitRe-inspection after non-compliance of initial inspection · Utah County Fire Marshal Permit Fee Schedule, Miscellaneous Permits and Fees, item 2. Plus applicable Zone Fee.
$70.00
Fire Alarm System PermitRe-inspection after non-compliance of initial inspection · Utah County Fire Marshal Permit Fee Schedule, Miscellaneous Permits and Fees, item 2. Plus applicable Zone Fee.
$70.00

Sources & verification

Verified against official sources. Last reviewed 2026-07-16.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Utah County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Unincorporated Utah County building permits

Get alerts for Unincorporated Utah County

We'll email you when Unincorporated Utah County's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.