Fire Sprinkler Permit in Unincorporated Utah County, Utah

Required for installation of an automatic fire sprinkler system in unincorporated Utah County, issued by the Utah County Fire Marshal's Office (a separate office from the Community Development Building Division, though in the same building) under International Fire Code (IFC) § 105.7.1. The Fire Marshal's own published Permit Fee Schedule lists a distinct dollar fee for this permit, separate from the general building permit.

Verified 2026-07-20 · Source

When you need this permit

  • Installation of a new automatic fire sprinkler system, per IFC § 105.7.1
  • Plans reviewed by the Utah County Fire Marshal's Office; a rough-in inspection and a final inspection are included in the base permit fee
  • Applies in addition to, not instead of, any building permit required from the Community Development Building Division for the same project

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Automatic Fire Sprinkler — up to 10,000 sq ft (residential)Utah County Fire Marshal Permit Fee Schedule, item 2.a: 'Overview of plans, rough-in and final site inspections up to 10,000 square feet.' Plus a Zone travel fee where applicable ($15-$65 depending on distance from the Fire Marshal's office).
$230.00
Automatic Fire Sprinkler — CommercialUtah County Fire Marshal Permit Fee Schedule, item 2.b. Plus applicable Zone travel fee.
$330.00
Automatic Fire Sprinkler — over 10,000 sq ft (per sq ft, in addition to base fee)Utah County Fire Marshal Permit Fee Schedule, item 2.c.
$0.025 per sq ft
Zone Fee (travel time/distance, added to most Fire Marshal permits)Utah County Fire Marshal Permit Fee Schedule, Zone Fee table (Zones 1-4).
$15.00 (10 mi or less) / $30.00 (over 10 mi) / $45.00 (over 20 mi) / $65.00 (over 30 mi), one way from the Fire Marshal's office
Re-inspection after non-compliance of initial inspectionUtah County Fire Marshal Permit Fee Schedule, Miscellaneous Permits and Fees, item 2. Plus applicable Zone Fee.
$70.00

Review timeline

Plan review
Not published — contact the department

How long did your Fire Sprinkler Permit permit actually take in Unincorporated Utah County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In

    Site inspection of sprinkler piping/heads before concealment, included in the base permit fee per the Fire Marshal's fee schedule.

  2. 2

    Final

    Final site inspection and test, included in the base permit fee.

See the full Unincorporated Utah County inspection guide — scheduling & re-inspection fees →

Tips

  • This is a separate permit and separate fee from the general Community Development building permit — the Fire Marshal's Office (Suite 120) and the Building Division (Suite 117) are different offices at the same 51 South University Avenue, Provo address.
  • A Zone Fee based on travel distance from the Fire Marshal's office is added to most Fire Marshal permit fees, including this one — confirm your zone before budgeting.
  • The Fire Marshal's Permit Fee Schedule PDF is filed under a 2024-dated filename ('fee-schedule-v8-2024.pdf') but its own header text still states 'Effective December 25, 2014' — the dollar figures below are quoted as currently published; confirm with the Fire Marshal's Office (801-851-8348) that no newer figures have superseded this schedule.
  • This department only serves unincorporated Utah County — properties within a city (Provo, Orem, Spanish Fork, etc.) must go through that city's own fire authority.

Frequently asked questions

Unincorporated Utah County requires a fire sprinkler permit for: Installation of a new automatic fire sprinkler system, per IFC § 105.7.1; Plans reviewed by the Utah County Fire Marshal's Office; a rough-in inspection and a final inspection are included in the base permit fee; Applies in addition to, not instead of, any building permit required from the Community Development Building Division for the same project. If your project isn't listed, confirm with Utah County Community Development — Building Division at (801) 851-8342 before starting work.

Per the Utah County Fire Marshal's Permit Fee Schedule: $230.00 for a residential system up to 10,000 sq ft, $330.00 for a commercial system, and $0.025 per sq ft for systems over 10,000 sq ft — each plus a Zone travel fee ($15-$65 depending on distance from the Fire Marshal's office in Provo).

Unincorporated Utah County does not publish a plan-review timeline for this permit. Contact Utah County Community Development — Building Division at (801) 851-8342 for current turnaround.

You'll need: Fire Sprinkler Permit Application / Plan Submittal. See the required-documents checklist on this page for details on each.

Unincorporated Utah County requires 2 inspection(s) for a fire sprinkler permit, in order: Rough-In, Final. Schedule each through Utah County Community Development — Building Division ((801) 851-8342).

Apply through Utah County Community Development — Building Division at 51 South University Avenue, Suite 117, Provo, UT 84601. Phone: (801) 851-8342, email: comdev@utahcounty.gov. Office hours: Mon–Fri 8:00 AM – 4:30 PM (inspection scheduling: ShaunaL@utahcounty.gov). Official information: https://codev.utahcounty.gov/building.

Unincorporated Utah County, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — current statewide code per Utah Code § 15A-2-103(1)(a), in force since July 1, 2026 (superseded the 2021 IBC); confirmed matching the County's own Building page, which lists 'International Building Code 2024' as of 2026-07-16; 2021 International Residential Code (IRC) — Utah Code § 15A-2-103(1)(b); unchanged by the July 1, 2026 code cycle flip; confirmed matching the County's own Building page, which lists 'International Residential Code 2021' as of 2026-07-16; 2024 International Plumbing Code (IPC) — current statewide code per Utah Code § 15A-2-103(1)(d), in force since July 1, 2026 (superseded the 2021 IPC); confirmed matching the County's own Building page as of 2026-07-16; 2024 International Mechanical Code (IMC) — current statewide code per Utah Code § 15A-2-103(1)(e), in force since July 1, 2026 (superseded the 2021 IMC); confirmed matching the County's own Building page as of 2026-07-16; 2024 International Fuel Gas Code (IFGC) — current statewide code per Utah Code § 15A-2-103(1)(f), in force since July 1, 2026 (superseded the 2021 IFGC); confirmed matching the County's own Building page as of 2026-07-16; 2023 National Electrical Code (NEC) — Utah Code § 15A-2-103(1)(g); unchanged by the July 1, 2026 code cycle flip; confirmed matching the County's own Building page as of 2026-07-16; 2024 International Energy Conservation Code (IECC) — current statewide code per Utah Code § 15A-2-103(1)(h), in force since July 1, 2026 (superseded the 2021 IECC; one edition applies statewide, no separate residential/commercial split); confirmed matching the County's own Building page as of 2026-07-16; 2024 International Existing Building Code (IEBC) — current statewide code per Utah Code § 15A-2-103(1)(i), in force since July 1, 2026 (superseded the 2021 IEBC); confirmed matching the County's own Building page as of 2026-07-16; Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — current statewide code per Utah Code § 15A-2-103(1)(n), in force since July 1, 2026 (superseded the 2021 ISPSC); not separately itemized on the County's own Building page as of 2026-07-16, added here as it applies statewide; NOTE: The July 1, 2026 statewide code cycle flip (Utah Code § 15A-2-103, amended by Ch. 47, 2026 General Session) is now in effect. The County's own Building page was re-checked live on 2026-07-16 and has ALREADY been updated to reflect it — it now lists IBC 2024, IPC 2024, IMC 2024, IFGC 2024, IECC 2024, and IEBC 2024, alongside the unchanged IRC 2021 and NEC 2023. This supersedes the prior 2026-06-30 note recorded here (which said the page still showed '2021 IBC'); the County's page is current, not lagging.. Local amendments apply — see the Unincorporated Utah County overview page for the full list.

No. The Utah County Fire Marshal's Office issues the fire sprinkler permit separately from the Community Development Building Division's building permit, with its own fee schedule and application, even though both offices are at the same address.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Utah County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.