Skip to main content
PermitBase

Riverdale building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Riverdale, Utah.

Verified 2026-07-08 · Source

How to schedule

Inspections are requested through the building department below.

Address
4600 South Weber River Drive, Riverdale, Utah 84405
Phone
(801) 394-5541 ext. 1276
Office hours

Inspection sequence

Applies to: Commercial Building Permit

  1. 1

    Footing/Foundation

    Required inspection prior to placing concrete, per Riverdale's official Building Inspections page list of typical required inspections (not distinguished by permit type).

  2. 2

    Underground Plumbing

    Required inspection of underground plumbing lines before backfill.

  3. 3

    Framing / Electrical / Plumbing / Mechanical

    Combined rough-in inspection of framing and MEP trades.

  4. 4

    Insulation

    Required inspection of insulation installation prior to covering.

  5. 5

    Final

    Final site inspection required for occupancy. Scheduled via the cityinspect.com portal or by calling ext. 1276.

Applies to: Residential Building Permit

  1. 1

    Footing/Foundation

    Required inspection prior to placing concrete, per Riverdale's official Building Inspections page list of typical required inspections.

  2. 2

    Underground Plumbing

    Required inspection of underground plumbing lines before backfill, per Riverdale's official Building Inspections page.

  3. 3

    Framing / Electrical / Plumbing / Mechanical

    Combined rough-in inspection of framing and MEP trades, per Riverdale's official Building Inspections page.

  4. 4

    Insulation

    Required inspection of insulation installation prior to covering, per Riverdale's official Building Inspections page.

  5. 5

    Final

    Final site inspection required for occupancy, per Riverdale's official Building Inspections page. Scheduled via the cityinspect.com portal or by calling ext. 1276; the city notes its inspection schedule generally fills up one to two days ahead of time.

Applies to: Commercial Tenant Improvement / Tenant Finish Permit

  1. 1

    Framing / MEP Rough-In

    Scope-dependent framing and MEP rough-in inspection, per Riverdale's official Building Inspections page (no distinct tenant-improvement sequence is separately published).

  2. 2

    Final

    Final site inspection required for occupancy. Scheduled via the cityinspect.com portal or by calling ext. 1276.

Sources & verification

Verified against official sources. Last reviewed 2026-07-08.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Riverdale building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Riverdale building permits

Get alerts for Riverdale

We'll email you when Riverdale's fees, documents, or codes change — not often.