Inspection sequence
Applies to: Commercial Building Permit
- 1
Footing/Foundation
Required inspection prior to placing concrete, per Riverdale's official Building Inspections page list of typical required inspections (not distinguished by permit type).
- 2
Underground Plumbing
Required inspection of underground plumbing lines before backfill.
- 3
Framing / Electrical / Plumbing / Mechanical
Combined rough-in inspection of framing and MEP trades.
- 4
Insulation
Required inspection of insulation installation prior to covering.
- 5
Final
Final site inspection required for occupancy. Scheduled via the cityinspect.com portal or by calling ext. 1276.
Applies to: Residential Building Permit
- 1
Footing/Foundation
Required inspection prior to placing concrete, per Riverdale's official Building Inspections page list of typical required inspections.
- 2
Underground Plumbing
Required inspection of underground plumbing lines before backfill, per Riverdale's official Building Inspections page.
- 3
Framing / Electrical / Plumbing / Mechanical
Combined rough-in inspection of framing and MEP trades, per Riverdale's official Building Inspections page.
- 4
Insulation
Required inspection of insulation installation prior to covering, per Riverdale's official Building Inspections page.
- 5
Final
Final site inspection required for occupancy, per Riverdale's official Building Inspections page. Scheduled via the cityinspect.com portal or by calling ext. 1276; the city notes its inspection schedule generally fills up one to two days ahead of time.
Applies to: Commercial Tenant Improvement / Tenant Finish Permit
- 1
Framing / MEP Rough-In
Scope-dependent framing and MEP rough-in inspection, per Riverdale's official Building Inspections page (no distinct tenant-improvement sequence is separately published).
- 2
Final
Final site inspection required for occupancy. Scheduled via the cityinspect.com portal or by calling ext. 1276.
Sources & verification
Verified against official sources. Last reviewed 2026-07-08.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Riverdale building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Riverdale building permits
Get alerts for Riverdale
We'll email you when Riverdale's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.