Unincorporated Weber County building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Unincorporated Weber County, Utah.
Verified 2026-07-16 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 2380 Washington Blvd., Suite 270, Ogden, UT 84401
- Phone
- (801) 399-8770
- Office hours
- Mon–Fri 8:00 AM – 5:00 PM (excluding legal holidays)
- Website
- Official site
Published scheduling rules
- Schedule all inspections at least 24 hours in advance. Have the permit number, owner/contractor name, site address, inspection type, and contact phone number ready. (Residential Building Permit)
- Schedule inspections at least 24 hours in advance by calling (801) 399-8770. (Roofing Permit)
- Schedule all inspections at least 24 hours in advance by calling (801) 399-8770. (Demolition Permit)
- All inspections must be scheduled at least 24 hours in advance. Have the permit number, owner/contractor name, site address, inspection type, and contact phone ready when calling (801) 399-8770. (General)
Inspection sequence
Applies to: Residential Building Permit
- 1
Footing
After excavations complete, forms set, reinforcing in place. Distance from property lines verified. Survey may be required. Schedule at least 24 hours in advance.
- 2
Foundation
When forms, reinforcing steel, structural straps, and imbeds are in place — before concrete pour.
- 3
Underslab
Before fill or concrete — all in-slab or underslab service equipment, conduit, piping, and heating ducts in place. Air or water test required for all piping.
- 4
Roof Sheathing
When roof framing and sheathing are completed, BEFORE roof is dried in. Failure to have this inspection may result in removal of roof coverings.
- 5
Four-Way (Rough) / Flashing
After framing, roof, fire blocking, exterior sheathing, flashing, and braced panels are in place and all pipes, vents, chimneys, rough plumbing, rough heating, and rough electrical are complete. Must pass before installing insulation, drywall, or exterior wall coverings.
- 6
Insulation
After wall insulation installed and before any drywall. REScheck must be on-site.
- 7
Drywall Nailing (Fire-Resistive Construction)
When drywall is nailed, prior to taping — required for fire-resistive construction.
- 8
Power to Panel (Permanent Electrical)
After electrical service equipment and grounding are installed and four-way inspection is passed. Power clearance not given until four-way passes.
- 9
Final
When building is complete and ready for occupancy. All site work including sidewalks, driveways, and grading must be complete.
Applies to: Commercial Building Permit
- 1
Footing
After excavations complete, forms set, reinforcing in place. Schedule at least 24 hours in advance.
- 2
Foundation
When forms, reinforcing steel, structural straps, and imbeds are in place — before concrete pour.
- 3
Underslab
Before fill or concrete — all in-slab or underslab service equipment, conduit, piping, and heating ducts in place.
- 4
Four-Way (Rough) / Flashing
After framing, roof, fire blocking, exterior sheathing, flashing, and braced panels are in place and all pipes, vents, chimneys, rough plumbing, rough heating, and rough electrical are complete.
- 5
Power to Panel (Permanent Electrical)
After electrical service equipment and grounding are installed and four-way inspection is passed.
- 6
Final
When building is complete and ready for occupancy. All site work including sidewalks, driveways, and grading must be complete.
Applies to: Basement Finish Permit
- 1
Framing / Four-Way
Wall framing, fire blocking, egress window openings, rough plumbing/electrical/mechanical complete — before insulation or drywall
- 2
Insulation
After wall insulation installed, before drywall. REScheck must be on-site.
- 3
Drywall Nailing (if fire-resistive construction)
When drywall is nailed, prior to taping — required for fire-resistive assemblies
- 4
Final
All work complete — drywall, fixtures, smoke/CO detectors on every level and in/near every bedroom
Applies to: Deck Permit
- 1
Footing
Footing excavation, forms, and reinforcing before concrete pour — verify footing depth below frost line
- 2
Framing / Four-Way
Posts, beams, joists, ledger connection, and hardware inspected
- 3
Final
Decking, stairs, guards, and railings complete — 36-inch guard height required for decks 30 inches or more above grade
Applies to: Electrical Permit
- 1
Rough-In / Four-Way
Wiring installed before walls closed — completed as part of the Four-Way (Rough) inspection per the Weber County Required Inspections List
- 2
Power to Panel
Electrical service equipment and grounding installed; power clearance not given until four-way inspection passes
- 3
Final
All devices installed, GFCI/AFCI protection verified, panel labeled, building ready for occupancy
Applies to: EV Charger / EVSE Permit
- 1
Rough-In / Four-Way
Wiring installed before walls closed — completed as part of the Four-Way (Rough) inspection per the Weber County Required Inspections List.
- 2
Power to Panel
Electrical service equipment and grounding installed; power clearance not given until four-way inspection passes.
- 3
Final
Charger installed and operational, GFCI/AFCI protection verified, panel labeled.
Applies to: Plumbing Permit
- 1
Underslab / Underground
Before fill or concrete — all underslab piping in place, air or water test required per Weber County Required Inspections List
- 2
Rough-In (Four-Way)
After pipes installed, before walls closed — air or water test required for all piping
- 3
Final
All fixtures connected, water flowing, no leaks, proper venting verified
Applies to: Commercial Tenant Improvement / Tenant Finish Permit
- 1
Four-Way (Rough)
Framing, fire blocking, rough plumbing, rough heating, and rough electrical for the TI/remodel scope, complete before insulation, drywall, or wall coverings.
- 2
Final
Completed TI/remodel work verified before occupancy sign-off.
Applies to: Demolition Permit
- 1
Pre-Demolition
Verify utility disconnects are complete and any required asbestos clearance is obtained before work begins. Per Weber County Code § 12-3-5, utilities must be disconnected before service can be terminated.
- 2
Final / Site Clear
Site cleared, foundation removed or capped per permit scope, site conditions verified
Applies to: Fire Alarm System Permit
- 1
Rough-In / Progress Inspection
One of the two inspections included in the permit fee; fire sprinkler and alarm final inspections are coordinated and scheduled together per Weber Fire District's Plan Reviews & Permits page.
- 2
Final Inspection
Second of the two inspections included in the permit fee.
Applies to: Fire Sprinkler System Permit
- 1
Rough-In / Progress Inspection
One of the two inspections included in the permit fee; fire sprinkler and alarm final inspections are coordinated and scheduled together per Weber Fire District's Plan Reviews & Permits page.
- 2
Final Inspection
Second of the two inspections included in the permit fee. All fire-system piping must be visible for a proper inspection.
Applies to: Mechanical / HVAC Permit
- 1
Rough-In (Four-Way)
Ductwork and gas piping installed, before walls closed — completed as part of the Four-Way inspection per the Weber County Required Inspections List
- 2
Final
Equipment operational, combustion air verified, gas pressure tested, thermostat functional
Applies to: Roofing Permit
- 1
Roof Sheathing
Required when roof framing and sheathing are complete, BEFORE roof is dried in. Failure to have this inspection may result in removal of roof coverings. Per Weber County Required Inspections List (Revised 1/7/21).
- 2
Final
Completed roof — verify ice and water shield, flashing, drip edge, nailing pattern, and ventilation
Applies to: Solar Panel Permit
- 1
Rough Electrical
Conduit runs, wire sizing, disconnect placement before energizing
- 2
Final
Panel mounting, racking attachment, roof penetration sealing, and electrical connections verified
Final inspection only: Sign Permit (Land Use Permit), Water Heater Permit
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-16.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Weber County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Unincorporated Weber County building permits
Get alerts for Unincorporated Weber County
We'll email you when Unincorporated Weber County's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.