Residential Building Permit (New Construction) — Issaquah, Washington · Requirements sheet
Verified 2026-09-16 · Source: https://issaquah.municipal.codes/IMC/16.04
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Building Permit (New Construction) in Issaquah, Washington
Required for new one- and two-family dwellings and townhouses in Issaquah, reviewed under the 2021 International Residential Code and administered through the city's own Construction Administrative Code.
Verified 2026-09-16 · Source
When you need this permit
- “2021 International Residential Code – Chapter 51-51 WAC” (CAC 101.2)
- IRC Appendices F (Radon Control Methods), Q (Tiny Houses) and U (Dwelling Unit Fire Sprinkler Systems) are included; other appendices “shall not apply unless specifically adopted”
- The IRC also covers adult family homes, foster family care homes and family day care homes licensed by the Washington State Department of Social and Health Services (CAC 101.4.2)
- Fees are charged on valuation under Table A, and valuation includes the contractor's overhead and profit
- Applications expire 18 months after filing; permits expire 2 years after issuance (CAC 105.3.4, 105.5)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
ISSAQUAH ACTUALLY PUBLISHES THE NUMBERS — the first city in this Washington set to do so. Show full citationHide
ISSAQUAH ACTUALLY PUBLISHES THE NUMBERS — the first city in this Washington set to do so. Construction Administrative Code Section 109.2, Table A: “$1.00 to $500.00 — $33.26”; “$501.00 to $2,000.00 — $33.26 for the first $500.00 plus $4.16 for each additional $100.00, or fraction thereof”; then bases of $99.16 at $2,000, $558.75 at $25,000, $919.23 at $50,000, $1,418.35 at $100,000, $4,618.29 at $500,000 and $8,009.61 above $1,000,000, with marginal rates of $20.13, $14.61, $9.69, $8.00, $6.67 and $5.54 per $1,000. Fees are charged on VALUATION as determined under CAC 109.4. CONTINUITY CONTROL RUN ON TABLE A, AND IT FIRES AT 6 OF 7 BRACKET BOUNDARIES. Carrying each bracket's stated base plus its marginal rate across the bracket width does not reproduce the next bracket's stated base: at $2,000 the carry gives $95.66 against a stated $99.16 (+$3.50); at $25,000, $562.15 against $558.75 (-$3.40); at $50,000, $924.00 against $919.23 (-$4.77); at $100,000, $1,403.73 against $1,418.35 (+$14.62); at $500,000, $4,618.35 against $4,618.29 (-$0.06); at $1,000,000, $7,953.29 against $8,009.61 (+$56.32). Only the $500 boundary reconciles exactly. THIS IS NOT ASSERTED TO BE AN ERROR — the residuals run in both directions and are mostly small, which is what per-row derivation with independent rounding looks like rather than a drafting mistake. The practical consequence is the useful part: USE THE STATED BASE FOR YOUR OWN BRACKET AND DO NOT ACCUMULATE UP FROM A LOWER ONE, because the two methods disagree.Review timeline
Inspection process
Tips
- Do not build your fee estimate by adding up through the brackets. Table A states a base for each valuation band, and carrying the band below it forward gives a different answer at six of the seven boundaries — from $4.77 low to $56.32 high. Take the base for the band your valuation actually falls in.
- Valuation is not your contract price. CAC 101.2.1(16) defines it as the estimated cost to replace the building and its service equipment in kind at current material and labour rates, and says it “shall also include the contractor's overhead and profit” — so the city's figure can sit above the number you were working to.
- If any of the units qualify as affordable housing under Chapter 18.102 IMC, the building permit fee is waived rather than reduced, and a partly-affordable building has its fees pro-rated by the number of affordable units. That definition lives in the Land Use Code, which is a separate document from the Municipal Code.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-09-16.
Codes & ordinances
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Issaquah building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Issaquah's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Issaquah yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Issaquah lands. Privacy.
Other permits in Issaquah
Residential Building Permit (New Construction) in other cities
Compare residential building permit (new construction) fees across Washington →
Look up this fee in a different city →
Related guides
Now live
Build your Issaquah project checklist
Describe your project once and get every permit, document, and fee it triggers in Issaquah — in one checklist. Free, for any city and any number of projects.
Get started →