Required for new one- and two-family dwellings in Longview, reviewed under the 2021 International Residential Code as adopted through Chapter 51-51 WAC.
Verified 2026-09-16 · Source
When you need this permit
- “Chapter 51-51 WAC (2021 International Residential Code), including the Appendix Chapters G and H” (LMC 16.02.010)
- PLAN REVIEW IS AN EXTRA 65 PERCENT of the building permit fee for IRC one- and two-family reviews, “in addition to the permit fees”
- A “Same As” master plan can cut repeat plan review to 30 percent, within one subdivision and one code cycle
- Five of the IBC Section 105.2 permit exemptions are deleted locally (subsections 1, 2, 4, 6 and 12)
- Appeals go to the Appeal Board of Adjustment under LMC Chapter 19.12
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
LMC 16.02.020 replaces IBC Section 109.2 and adds 109.2.1: “The fee for each building permit shall be as established in the community and economic development department master fee schedule.” The… Show full citationHide
LMC 16.02.020 replaces IBC Section 109.2 and adds 109.2.1: “The fee for each building permit shall be as established in the community and economic development department master fee schedule.” The same wording covers mechanical (109.2.2) and plumbing (109.2.3) permits. NO DOLLAR AMOUNT APPEARS IN THE CODE and none is asserted here — but unlike most of this Washington set, the PERCENTAGES that sit on top of that schedule ARE published, and they are recorded separately below.LMC 16.02.020 Section 109.6: “Not more than 80 percent of the permit fee paid when no work has been done”, and the same cap on plan review fees where an application is withdrawn or cancelled “before… Show full citationHide
LMC 16.02.020 Section 109.6: “Not more than 80 percent of the permit fee paid when no work has been done”, and the same cap on plan review fees where an application is withdrawn or cancelled “before any plan review effort has been expended.” Written application required “not later than 180 days after the date of fee payment.”Review timeline
Inspection process
Tips
- Budget the plan review separately and early. It is 65 percent of the building permit fee for a one- or two-family dwelling, the code states expressly that it is “in addition to” the permit fee, and it is payable when you submit the documents rather than at issuance.
- If you are building the same house more than once in one subdivision, ask about a “Same As” master plan before the first submittal. It drops later plan reviews to 30 percent, but the conditions are strict — same subdivision, same code cycle, and no deviation from the approved master plan.
- Check IBC Section 105.2 as amended before concluding you need no permit. Longview deletes subsections 1, 2, 4, 6 and 12 outright and narrows subsection 11 to “Swings and other playground equipment”, so several exemptions that hold elsewhere in Washington do not hold here.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-09-16.
Codes & ordinances
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Longview building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Longview's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Longview yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Longview lands. Privacy.
Other permits in Longview
Residential Building Permit (New Construction) in other cities
Compare residential building permit (new construction) fees across Washington →
Look up this fee in a different city →
Related guides
Now live
Build your Longview project checklist
Describe your project once and get every permit, document, and fee it triggers in Longview — in one checklist. Free, for any city and any number of projects.
Get started →